When is a train station not a train station? When it’s a performance venue

When is a train station not a train station? When it’s a performance venue

You can catch a train at Minneapolis’s new Target Field Station. You can also share in an experience. That’s what ‘Open Transit’ is all about.


By Robert Cassidy, Executive Editor | January 17, 2015
Minneapoliss Target Field Station opened last May 17. The $82.5 million hub is
Minneapoliss Target Field Station opened last May 17. The $82.5 million hub is the western terminus of the new Green Line, whic

Start with the train. Add something called “urban experience.” Turn it into a performance.

That was the thinking behind Target Field Station, which opened last May 17 in Minneapolis. The new light rail station connects the western terminus of the Metro Transit Green Line at Target Field, home of Major League Baseball’s Minnesota Twins, to its bookend 11 miles east at Union Station in St. Paul.

The 7,022-sf station, part of a 140,000-sf complex in the city’s ultra-hot North Loop, is the product of an intense design competition held in late 2011.

A design-build team led by New York–based architecture firm Perkins Eastman and local GC firm Knutson Construction beat four competitors to win the $82.5 million contract.

The design firm’s “Open Transit” concept was the key to the project. “It’s a design philosophy that comes from one principle: to create transit facilities that are so attractive people want to be there regardless of whether or not they’re taking a train,” says Peter Cavaluzzi, FAIA, Principal, Perkins Eastman. “Think about it as a live performance, and the trains are part of the performance.”

Cavaluzzi, who came to Perkins Eastman in a merger with EE&K in 2011, singles out New York’s Grand Central Terminal as the embodiment of Open Transit. “You have 750,000 people a day using Grand Central, but less than half actually board a train or subway car,” he says. Most come to shop, dine, people-watch, or simply to breathe in the magnificence of the space. 

 


The amphitheater has become a popular space for civic events, concerts, and informal gatherings. It is a key element of the “Open Transit” philosophy, a design approach that seeks to make transit facilities so attractive people want to be there even if they’re not taking the train. Photo: © Morgan Sheff

 

As we’ll see, Target Field Station has, in its brief lifespan, already established itself as a lively performance space, attracting crowds for music, films, and sporting events. It is igniting real estate development in the North Loop at a sizzling rate. It has become the node of integration for multiple modes of transport—busses, trains, bicycles and, yes, even cars. And, in less than a year, it has turned into something of a—dare we say it? —iconic destination in the Twin Cities.

But first, let’s take a step back a bit into the station’s history.

 

KEEPING UP WITH DEMAND FOR TRANSIT

Before there was a Green Line, there was the Hiawatha, a 12-mile light rail line from downtown Minneapolis to the airport and the Mall of America, in Bloomington. The Hiawatha made its first headway on June 26, 2004. In November 2009, a new station, the Interchange, was opened to serve the North Loop neighborhood and Target Field, the nearly completed new home of the Twins.

Preliminary engineering for a second transit line was started in late 2006. Called the Central Corridor, it was planned to run along University Avenue from downtown St. Paul and the University of Minnesota to Minneapolis, terminating at the Interchange.

It took another four years for the Metropolitan Council, the regional planning agency in charge of the project, to come up with the initial $909 million funding and obtain environmental impact approvals from the federal government. Final design for the new rail line was completed in May 2010, shortly after Target Field opened. 

Even before construction got under way, in late 2010, local officials worried that they had what Hennepin County Commissioner Peter McLaughlin would later call “a transit capacity problem.” Ridership on the Hiawatha, which had been strong from the start, went off the charts, especially on game days. “More people were taking the train to Target Field than we had expected,” he says.

Transit planners were concerned that, with the anticipated additional ridership from the Central Corridor line, and with two more extensions planned to the northwest and southwest, it might take two hours to clear the Interchange platform on a busy game day. Commuters were also attempting to cross live tracks to get from the Northstar suburban line to the transit platform.

 


The Cascade provides a three-dimensional experience for commuters and visitors to the station, some of whom have been known to run up the stairs and thrust their arms in the air à la Rocky. Rendering courtesy Perkins Eastman

 

“We needed to deal with the safety problems, and we needed better service,” said McLaughlin, Chair of the five-county regional Counties Transit Improvement Board. It was clear that the Interchange hub would have to be completely revamped, and it would have to be elevated.

Before that could happen, McLaughlin and other transit advocates had to sell the idea to the North Loop community, which Forbes would later name one of America’s top 20 hipster neighborhoods. “There were a lot of New Urbanist sensibilities there, and they opposed having an elevated station,” says McLaughlin. “They wanted it at street level.”

In late 2011, at a two-day charrette with stakeholders, the transit planners came up with a scheme to pull the station closer to the adjacent Hennepin Energy Recovery Center (“The HERC”), the county’s waste-to-energy facility. This would clear enough room to elevate the tracks, open up space for a storage track, and pave the way for much-needed street improvements in the surrounding neighborhood. 

Getting the job done in the worst winter in 30 years

The last six months of construction on Target Field Station took place during the worst winter in 30 years in Minnesota, and that’s saying something. Crews from Knutson Construction had to bear up against 23 days of -25?F weather. They worked six days a week and some Sundays to get the station ready for its May 17, 2014, opening. 

Pouring colored concrete for the plaza and walkways took some doing. “Colored concrete is so finicky,” says Rob Bremer, Knutson’s Project Manager on the job. To to maintain the consistency in the frigid cold, crews erected 20x20-foot stick-frame shelters, covered them with plastic, and poured the concrete in 10x10-foot squares. It was not fun. “Working in a 20x20 enclosure, your productivity goes way down,” he says. 

Knutson crews had to take a similar tack in order to paint and caulk the massive canopy that covers the station platform. They erected scaffolding over the entire structure and covered it in reinforced polyethylene tarp. Three-fourths of the forms for the 286-car parking ramp had to be cut and set by hand to account for numerous dimensional changes.

The city wanted nothing to do with hauling snow from the station, so more than 50 miles of snow-melt tubing was installed. “Salt would only discolor the concrete,” says Bremer.

The logistical problems seemed endless. The plan called for reconfiguring the entrance to the waste-to-energy facility, but HERC staff were deaf to any talk of interrupting the flow of their trucks—365 a day. Knutson put in a temporary road for the haulers, and then created a wider entrance with a snow-melt system. The contractor also had to rebuild nearly 250 feet of a four-lane road right next to the municipal bus hub.

Work had to be halted to accommodate 10-12 BNSF freight trains every day. “We had to have a BNSF flagger out there, and when the train was a mile away, everything had to stop, and then we’d have to wait till it was a mile past us,” says Bremer.

Structural engineering for the project was equally problematic, says Swami Palanisami, PE, Owner and Principal, Palanisami & Associates. No task was more difficult than getting the loads right for the Cascade. Palanisami used a technique he calls staged post-tensioning: “We’d put some load on and tension the cable, then more load and tension the cable, and so on,” he recalls. “Every beam, every column was like a piece of artwork.”

Palanisami says Target Field Station posed “some of the most complex geometries I’ve ever worked on in my 44 years as an engineer.”

“The charrette turned the tide,” says McLaughlin. The North Loop neighborhood bought into elevating the Interchange. In 2011, Hennepin County issued an RFP to design-build teams to bid on the project.

All the bids came in over budget, and the county had to recalibrate its numbers. In December 2011, the five finalists were given until March, less than three months away, to resubmit their bids.

 

COMING IN STRONG FROM WAY BACK IN THE PACK

“We were a dark horse,” says Cavaluzzi, referring to the Perkins Eastman/Knutson Construction design-build team. “We came in late, but the good thing is, it became a contest for the best design, not just the lowest bidder.”

In July 2012, their $85.2 million bid was selected. As Hennepin County’s McLaughlin put it, “The RFP process was difficult, but we got a great product.”

Last May 17, less than two years from the start of construction, the newly named Target Field Station officially opened. (Target Corporation paid $1.75 million for the naming rights.) On June 14, 2014, the newly christened Green Line started service at 18 new stations and five it shares with the Blue Line, the new name for the Hiawatha Line.

Two features put the Perkins Eastman/Knutson bid over the top in the bidding: the Great Lawn and the Cascade. These Open Transit elements transfigured what could have been a run-of-the-mill train stop into an instant urban village. 

The 7,100-sf Great Lawn, designed in cooperation with landscape architect Olin/SEH, quickly turned into a popular gathering spot for pregame events, concerts, and casual outdoor activities. A 16x29-foot video board (donated by Target Corporation) sits atop the elevator core, making it visible from the Great Lawn and upper plaza. Last summer, it became the place to watch World Cup soccer and Twins games, and there were movie nights and music events.

A 1,000-seat amphitheater and a sloping, informal seating area form the second Open Transit feature, the Cascade. To Cavaluzzi, the amphitheater’s thrust stage recalls Ralph Rapson’s Guthrie Theater. (Cavaluzzi received his MArch from the University of Minnesota and was a Minnesota Architectural Foundation Ralph Rapson Fellow.) Live concerts sponsored by a local radio station have attracted enthusiastic crowds.

Cavaluzzi says the Cascade pays homage to Olmsted and Vaux’s Bethesda Terrace in New York’s Central Park—with a touch of Philadelphia thrown in: “People feel compelled to dash up to the top and pump their fists like Rocky,” he says.

All the while the trains glide in overhead—“almost whisper-quiet,” says Cavaluzzi. “Think of it as a live performance venue, and the trains are part of the performance.” 

In addition to the Great Lawn and the Cascade, Target Field Station benefits from many hidden touches, chief of which is a snow-melt system that uses waste heat from “The HERC” to pump warm water through 50 miles of pipe. This keeps the plaza clear of snow and makes it much more attractive, even in the worst days of the Minnesota winter. Colored concrete was scored, sandblasted, and otherwise treated with a variety of finishes for optimal aesthetic effect.

The green roof and a system of tree pits collect stormwater, which is filtered and stored in giant cisterns that can hold 40,000 gallons. Lighting designer Schuler Shook created a light garden with nine programmable wall fixtures and light sticks; the canopy above the LRT station platform is lit with programmable LEDs.

 

 
The Great Lawn has become the place where even a Yankee fan can enjoy the live broadcast of a Minnesota Twins’ game. Last June and July it was the hot spot to catch World Cup soccer on the 16x29-foot video board. Landscaping and architectural features like this have made Target Field Station an entertainment venue and community gathering space, not just a transportation hub. Photo: © Morgan Sheff

 

The project is certified under LEED and Minnesota’s “Buildings, Benchmarks and Beyond” guidelines. Cavaluzzi says that standard measures of sustainability are difficult to apply to a transit station. He argues that, by enabling year-round use, the station is, by its very nature, highly sustainable.

According to the Minneapolis Star-Tribune, about a third of the financing came from the federal government, 30% from the county, 20% from the state, and the rest from the city and the Minnesota Ballpark Authority. The Twins and United Properties, a division of the Pohlan Family Companies (the owners of the ballpark), chipped in $3.6 million.

 

TALLYING UP THE PAYOFF

Development activity in the North Loop is proceeding at what the Star-Tribune has called “a blistering pace.” Office buildings, retail stores, and apartment buildings are replacing desolate parking lots in the old red-brick industrial district.

In November, Trammell Crow had no trouble flipping its 182-unit Junction Flats apartment complex, which it completed just a few months before, for $49 million.  

Hines has several projects going in the North Loop, the latest a 210,000-sf, seven-story wooden speculative office building it’s calling T3 (for “timber, transit, technology”).

United Properties is beavering away on a $60 million headquarters that will house 800 employees of Be the Match, the nonprofit bone marrow registry. United also completed the renovation of the 10-story Ford Center, a 270,131-sf historic Model T factory across from the station, and the 112,645-sf Loose-Wiles Biscuit Company Building; both are about 99% leased.

In November, United Properties announced plans for Target Field Station Center, a 10-story, 240,000-sf office building that it will develop on spec—another sign of the transit node’s vitality. United is in the process of buying a three-quarter-acre parcel for the project from Hennepin County for $1.5 million; the county will get $15/sf (minus the $1.5 million) from future leases. “That could net out to $2 million,” says Commissioner McLaughlin.

McLaughlin recently reflected on the county’s original vision for the project. “We wanted a transit station that worked well, but we also wanted a public space that would be noteworthy, a statement—not just for 81 home baseball games, but a great civic space that would function 365 days a year.”

By all accounts, Target Field Station is well on its way to realizing that vision. 

 

PROJECT SUMMARY
Target Field Station
Minneapolis, Minn.
 
Building Team
Owner: Hennepin County, Minn.
Design architect, AOR: Perkins Eastman
Structural engineer: Palanisami & Associates
Mechanical engineer: Michaud Colley Erickson
Electrical engineer: Parsons Electric
Landscape architect: Olin/SHE
Lighting designer: Schuler Shook
General contractor: Knutson Construction Co.
 
General Information
Size: 104,111 sf (ramp, plaza, shell space), 29,430 sf (HERC administration area), 7,022 sf (LRT platform); 286 parking spaces
Construction cost: $82.5 million
Construction time: July 2012 to May 2014
Delivery method: Design-build

Related Stories

Multifamily Housing | Feb 11, 2023

8 Gold and Platinum multifamily projects from the NAHB's BALA Awards

This year's top BALA multifamily winners showcase leading design trends, judged by eight industry professionals from across the country.

Multifamily Housing | Feb 10, 2023

Dallas to get a 19-story, 351-unit residential high-rise

In Dallas, work has begun on a new multifamily high-rise called The Oliver. The 19-story, 351-unit apartment building will be located within The Central, a 27-acre mixed-use development near the Knox/Henderson neighborhood north of downtown Dallas. 

Sustainability | Feb 9, 2023

New guide for planning, designing, and operating onsite water reuse systems

The Pacific Institute, a global nonpartisan water think tank, has released guidance for developers to plan, design, and operate onsite water reuse systems. The Guide for Developing Onsite Water Systems to Support Regional Water Resilience advances circular, localized approaches to managing water that reduce a site’s water footprint, improve its resilience to water shortage or other disruptions, and provide benefits for local communities and regional water systems.

Office Buildings | Feb 9, 2023

Post-Covid Manhattan office market rebound gaining momentum

Office workers in Manhattan continue to return to their workplaces in sufficient numbers for many of their employers to maintain or expand their footprint in the city, according to a survey of more than 140 major Manhattan office employers conducted in January by The Partnership for New York City.

Giants 400 | Feb 9, 2023

New Giants 400 download: Get the complete at-a-glance 2022 Giants 400 rankings in Excel

See how your architecture, engineering, or construction firm stacks up against the nation's AEC Giants. For more than 45 years, the editors of Building Design+Construction have surveyed the largest AEC firms in the U.S./Canada to create the annual Giants 400 report. This year, a record 519 firms participated in the Giants 400 report. The final report includes 137 rankings across 25 building sectors and specialty categories.   

University Buildings | Feb 8, 2023

STEM-focused Kettering University opens Stantec-designed Learning Commons

In Flint, Mich., Kettering University opened its new $63 million Learning Commons, designed by Stantec. The new facility will support collaboration, ideation, and digital technology for the STEM-focused higher learning institution.

Sustainability | Feb 8, 2023

A wind energy system—without the blades—can be placed on commercial building rooftops

Aeromine Technologies’ bladeless system captures and amplifies a building’s airflow like airfoils on a race car.

Codes and Standards | Feb 8, 2023

GSA releases draft of federal low embodied carbon material standards

The General Services Administration recently released a document that outlines standards for low embodied carbon materials and products to be used on federal construction projects.

University Buildings | Feb 7, 2023

Kansas City University's Center for Medical Education Innovation can adapt to changes in medical curriculum

The Center for Medical Education Innovation (CMEI) at Kansas City University was designed to adapt to changes in medical curriculum and pedagogy. The project program supported the mission of training leaders in osteopathic medicine with a state-of-the-art facility that leverages active-learning and simulation-based training.

Multifamily Housing | Feb 7, 2023

Multifamily housing rents flat in January, developers remain optimistic

Multifamily rents were flat in January 2023 as a strong jobs report indicated that fears of a significant economic recession may be overblown. U.S. asking rents averaged $1,701, unchanged from the prior month, according to the latest Yardi Matrix National Multifamily Report.

boombox1
boombox2
native1

More In Category

Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021