A watchtower in Harlem, once a firefighter’s lookout, is restored as a landmark

Cultural Facilities

A watchtower in Harlem, once a firefighter’s lookout, is restored as a landmark

The nearly $8 million project required major structural interventions.


By John Caulfield, Senior Editor | October 29, 2019

The restoration of the Harlem Fire Watchtower in North Manhattan, which took two years to complete, required new cross bracing. Images: Courtesy of Thornton Tomasetti 

In the 1800s, firefighters in New York City watched over their communities perched from cast-iron watchtowers that dotted the metro, and rang bells in those towers to alert nearby fire companies.

Pull boxes for fire alarms rendered the towers obsolete in the 1870s, and over the decades those structures fell into disrepair and near collapse. One of the structures—the Harlem Fire Watchtower, the third such tower in the city, built in 1856 within Mount Morris Park (renamed Marcus Garvey Park in 1973), and deemed a NYC Landmark by the National Register of Historic Places in 1967—has been restored and reconstructed, thanks to the activism of Harlem’s community.

City officials retained the engineering firm Thornton Tomasetti to reconstruct the watchtower. Its restoration design included structural assessment, historical documentation, and a finite element analysis of the cast-iron structure.

Elements of the watchtower’s cast iron structure that analysis deemed too deteriorated for reuse were replicated. The old structure failed under wind load tests, and required interventions to satisfy structural and historic preservation goals. The reconstruction included a new bracing system. The historic metals were painted the original color, while supplemental elements were stainless steel.

The tower’s 5,000-lb bell, dating back from 1865, underwent a non-destructive testing that confirmed casting anomalies and micro cracking. The bell was shipped to the Netherlands for brazing to reconstitute its structure.

Using historic photos as its guide, Thornton Tomasetti recreated or restored several of the watchtower’s lost features, such as its copper sheet roof. Landscaping around the tower was modified with ADA-compliant access. Ground-level security screens, a modern twist, nevertheless recall the original enclosure. Lighting protection, concealed within the structure, is incorporated into the roof filial.

 

 

Engineers from Thornton Tomasetti inspect a portion of the Harlem Fire Watchtower.

 

The city’s Landmarks Preservation Commission approved the reconstruction of the four-story octagonal watchtower on July 14, 2015. The project’s funding was $7,970,000, and reconstruction began in July 2017. Its Reconstruction Team included the NYC Department of Parks & Recreation (which owns and operates the park), Mueser Rutledge (engineering consultant), Nicholson and Galloway (copper roofing), Allen Architectural Metals (cast iron structure), and Verdin Bell Company.

The reinstalled watchtower was revealed at a ceremony on October 26 at the Acropolis, which overlooks the park. The Marcus Garvey Park Alliance/Public Arts Initiative has requested city funding to install lights and cameras on the Acropolis.

Related Stories

Libraries | Jun 1, 2018

New library offers a one-stop shop for what society is craving: hands-on learning

Beyond lending books and DVDs, the Elkridge (Md.) branch library loans household tools like ladders, wheelbarrows, and sewing machines.

| May 24, 2018

Accelerate Live! talk: Security and the built environment: Insights from an embassy designer

In this 15-minute talk at BD+C’s Accelerate Live! conference (May 10, 2018, Chicago), embassy designer Tom Jacobs explores ways that provide the needed protection while keeping intact the representational and inspirational qualities of a design.

Cultural Facilities | Apr 16, 2018

Best in library design 2018: Six projects earn AIA/ALA library awards

Austin Central Library and the Tulsa City-County Central Library are among the top projects for 2018. 

Cultural Facilities | Jan 23, 2018

BIG reveals revised Smithsonian Campus master plan

The original proposal was first unveiled in 2014.

Mixed-Use | Dec 12, 2017

A new live/work neighborhood is about to get under way in Omaha, Neb.

Walkability and recreation will be key features of West Farm.

Cultural Facilities | Nov 2, 2017

Perkins Eastman wins competition to redesign San Francisco’s Harvey Milk Plaza

The Friends of Harvey Milk Plaza unanimously selected the Perkins Eastman entry as the winner.

Museums | Oct 3, 2017

Denmark’s new LEGO experience hub looks like it’s made out of giant LEGO blocks

The 12,000-sm building is part of Billund, Denmark’s goal to become the ‘Capital for Children.’

Museums | Aug 15, 2017

Underground Railroad Visitor Center tells story of oppression, then freedom

The museum is conceived as a series of abstracted forms made up of two main structures, one administrative and one exhibit.

boombox1
boombox2
native1

More In Category

Adaptive Reuse

Detroit’s Michigan Central Station, centerpiece of innovation hub, opens

The recently opened Michigan Central Station in Detroit is the centerpiece of a 30-acre technology and cultural hub that will include development of urban transportation solutions. The six-year adaptive reuse project of the 640,000 sf historic station, created by the same architect as New York’s Grand Central Station, is the latest sign of a reinvigorating Detroit.


Museums

Connecticut’s Bruce Museum more than doubles its size with a 42,000-sf, three-floor addition

In Greenwich, Conn., the Bruce Museum, a multidisciplinary institution highlighting art, science, and history, has undergone a campus revitalization and expansion that more than doubles the museum’s size. Designed by EskewDumezRipple and built by Turner Construction, the project includes a 42,000-sf, three-floor addition as well as a comprehensive renovation of the 32,500-sf museum, which was originally built as a private home in the mid-19th century and expanded in the early 1990s. 



Cultural Facilities

Multipurpose sports facility will be first completed building at Obama Presidential Center

When it opens in late 2025, the Home Court will be the first completed space on the Obama Presidential Center campus in Chicago. Located on the southwest corner of the 19.3-acre Obama Presidential Center in Jackson Park, the Home Court will be the largest gathering space on the campus. Renderings recently have been released of the 45,000-sf multipurpose sports facility and events space designed by Moody Nolan.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021