VA construction program ‘a disaster,’ says congressman

Healthcare Facilities

VA construction program ‘a disaster,’ says congressman

Colorado hospital more than $1 billion over budget


By Peter Fabris, Contributing Editor | March 28, 2015
VA construction program ‘a disaster,’ says congressman

The 182-bed Aurora, Colo., hospital has incurred more than $1 billion in cost overruns. The Army Corps of Engineers has taken over the management of the project. Rendering: VA

The VA construction program took more hits recently after the chairman of a congressional Committee on Veterans’ Affairs called an Aurora, Colo., hospital project “a disaster,” and a key VA official resigned abruptly.

The 182-bed Aurora hospital has incurred more than $1 billion in cost overruns. The Army Corps of Engineers has taken over the management of the project. Colorado Rep. Mike Coffman, chairman of the House Veterans Affairs Oversight and Investigation Subcommittee, said the breakdown was due to “pure incompetence.” Democrats on that committee last week proposed stripping the VA of any construction authority.

Contractor Kiewit-Turner ceased construction on the Aurora hospital in December after the United States Civilian Board of Contract Appeals determined that the VA breached its contract by failing to provide a design that could be built for $582,840,000.

Rep. Jeff Miller called for the agency to fire the executives responsible for construction of VA hospitals. Amid this controversy, Glenn Haggstrom, principal executive director of the Office of Acquisition, Logistics and Construction with the VA abruptly resigned his post.

Related Stories

Healthcare Facilities | Feb 17, 2015

10 healthcare trends worth sharing

The rise of the medical home model of care and ongoing Lean value stream improvement are among the top healthcare industry trends.

Healthcare Facilities | Feb 11, 2015

Primer: Using 'parallel estimating' to pinpoint costs on healthcare construction projects

As pressure increases to understand capital cost prior to the first spade touching dirt, more healthcare owners are turning to advanced estimating processes, like parallel estimating, to improve understanding of exposure, writes CBRE Healthcare's Andrew Sumner.

Cultural Facilities | Feb 5, 2015

5 developments selected as 'best in urban placemaking'

Falls Park on the Reedy in Greenville, S.C., and the Grand Rapids (Mich.) Downtown Market are among the finalists for the 2015 Rudy Bruner Award for Urban Excellence.

Healthcare Facilities | Feb 1, 2015

7 new factors shaping hospital emergency departments

A new generation of highly efficient emergency care facilities is upping the ante on patient care and convenience while helping to reposition hospital systems within their local markets.

Healthcare Facilities | Jan 30, 2015

Mega medical complex opens in San Francisco’s Mission Bay neighborhood

The new UCSF Medical Center is actually three hospitals in one.

Sponsored | | Jan 8, 2015

Healthcare facilities promoting wellness from the inside out

The healthcare industry is in the midst of a shift to a wellness model of care, and the built environment plays an important role in that. This is driving new design elements in healthcare facilities—from the inside out. 

| Jan 2, 2015

Construction put in place enjoyed healthy gains in 2014

Construction consultant FMI foresees—with some caveats—continuing growth in the office, lodging, and manufacturing sectors. But funding uncertainties raise red flags in education and healthcare.

| Dec 30, 2014

The future of healthcare facilities: new products, changing delivery models, and strategic relationships

Healthcare continues to shift toward Madison Avenue and Silicon Valley as it revamps business practices to focus on consumerism and efficiency, writes CBRE Healthcare's Patrick Duke.

| Dec 29, 2014

HDR and Hill International to turn three floors of a jail into a modern, secure healthcare center [BD+C's 2014 Great Solutions Report]

By bringing healthcare services in house, Dallas County Jail will greatly minimize the security risk and added cost of transferring ill or injured prisoners to a nearby hospital. The project was named a 2014 Great Solution by the editors of Building Design+Construction.

| Dec 29, 2014

New mobile unit takes the worry out of equipment sterilization during healthcare construction [BD+C's 2014 Great Solutions Report]

Infection control, a constant worry for hospital administrators and clinical staffs, is heightened when the hospital is undergoing a major construction project. Mobile Sterilization Solutions, a mobile sterile-processing department, is designed to simplify the task. The technology was named a 2014 Great Solution by the editors of Building Design+Construction.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021