VA construction program ‘a disaster,’ says congressman

Healthcare Facilities

VA construction program ‘a disaster,’ says congressman

Colorado hospital more than $1 billion over budget


By Peter Fabris, Contributing Editor | March 28, 2015
VA construction program ‘a disaster,’ says congressman

The 182-bed Aurora, Colo., hospital has incurred more than $1 billion in cost overruns. The Army Corps of Engineers has taken over the management of the project. Rendering: VA

The VA construction program took more hits recently after the chairman of a congressional Committee on Veterans’ Affairs called an Aurora, Colo., hospital project “a disaster,” and a key VA official resigned abruptly.

The 182-bed Aurora hospital has incurred more than $1 billion in cost overruns. The Army Corps of Engineers has taken over the management of the project. Colorado Rep. Mike Coffman, chairman of the House Veterans Affairs Oversight and Investigation Subcommittee, said the breakdown was due to “pure incompetence.” Democrats on that committee last week proposed stripping the VA of any construction authority.

Contractor Kiewit-Turner ceased construction on the Aurora hospital in December after the United States Civilian Board of Contract Appeals determined that the VA breached its contract by failing to provide a design that could be built for $582,840,000.

Rep. Jeff Miller called for the agency to fire the executives responsible for construction of VA hospitals. Amid this controversy, Glenn Haggstrom, principal executive director of the Office of Acquisition, Logistics and Construction with the VA abruptly resigned his post.

Related Stories

Healthcare Facilities | Mar 4, 2021

Behavior mapping: Taking care of the caregivers through technology

Research suggests that the built environment may help reduce burnout.

Healthcare Facilities | Feb 25, 2021

The Weekly show, Feb 25, 2021: When healthcare designers become patients, and machine learning for building design

This week on The Weekly show, BD+C editors speak with AEC industry leaders from BK Facility Consulting, cove.tool, and HMC Architects about what two healthcare designers learned about the shortcomings—and happy surprises—of healthcare facilities in which they found themselves as patients, and how AEC firms can use machine learning to optimize design, cost, and sustainability, and prioritize efficiency protocols. 

Market Data | Feb 24, 2021

2021 won’t be a growth year for construction spending, says latest JLL forecast

Predicts second-half improvement toward normalization next year.

Healthcare Facilities | Feb 18, 2021

The Weekly show, Feb 18, 2021: What patients want from healthcare facilities, and Post-COVID retail trends

This week on The Weekly show, BD+C editors speak with AEC industry leaders from JLL and Landini Associates about what patients want from healthcare facilities, based on JLL's recent survey of 4,015 patients, and making online sales work for a retail sector recovery.

Healthcare Facilities | Feb 5, 2021

Healthcare design in a post-COVID world

COVID-19’s spread exposed cracks in the healthcare sector, but also opportunities in this sector for AEC firms.

Modular Building | Jan 26, 2021

Offsite manufacturing startup iBUILT positions itself to reduce commercial developers’ risks

iBUILT plans to double its production capacity this year, and usher in more technology and automation to the delivery process.

Healthcare Facilities | Jan 16, 2021

New patient pavilion is Poughkeepsie, N.Y.’s largest construction project to date

The pavilion includes a 66-room Emergency Department.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021