flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

User input on aquatics center keeps students in the swim [2014 Building Team Awards]

User input on aquatics center keeps students in the swim [2014 Building Team Awards]

Collaborative spirit abounds in the expansion and renovation of a high school pool facility in suburban Chicago.


By Raissa Rocha, Associate Editor | July 16, 2014
Special features of the new competition pool at Niles North High School include
Special features of the new competition pool at Niles North High School include regenerative media filtration and UV treatment s

The Building Team for the new Aquatics Center at Niles North High School in Skokie, Ill., included Chicago-area firms Legat Architects and IHC Construction—but a case could be made for listing a much larger group of official participants. The AEC firms made a concerted effort to involve not only district officials but also the user community. As a result, the project became a unique learning experience for students, staff, and neighbors.

The Niles North Aquatics Center serves 2,200 students—all of whom must take swimming—as well as 275 competitive student athletes in swimming, diving, and water polo. Feeder programs from park districts and local partners are also housed there. By 2012, the pool in the 48-year-old building was considered too small and shallow to meet current requirements.

Stakeholders asked for a new competition “cold pool,” a renovated community-accessible “warm pool,” a new public connecting corridor, locker room renovations, coaches’ offices, and meeting and storage space. Lighting and mechanical systems also needed an energy upgrade.

SILVER AWARD
Project summary

Niles North High School Aquatics Center
Skokie, Ill.

BUILDING TEAM
Submitting firm: Legat Architects (architect)
Owner/developer: Niles Township High School District 219
Structural: KJWW Engineering Consultants
Mechanical/plumbing: AMSCO Engineering
Electrical: Hansen Palmer Associates
Civil: Gewalt Hamilton
CM: IHC Construction Companies

GENERAL INFORMATION
Project size: 39,200 sf (24,600 sf new + 14,600 sf renovated)
Construction cost: $15 million
Construction period: April 2012 to August 2013
Delivery method: Design-bid-build

District 219 teamed with Legat Architects to plan the revitalization. Students and community members were surveyed regarding their priorities, and the Building Team held design workshops that elicited feedback for the floor plan. Daylighting is an important aspect of the final design, including a mix of clerestories, clear windows, translucent windows, and internal glazing to offer glare-free illumination and visual connections. 

Eventually, the project was incorporated into the district’s architecture and engineering class curriculum. Biweekly tours were coordinated with faculty to focus on current classroom topics, and students were able to receive insights on various career paths.

“It became quite the living classroom,” says Building Team Awards judge Nathan Snydacker, PE, LEED AP, Vice President at Environmental Systems Design.

 “It’s a lot of involvement you’d want in a school project of this type,” adds BTA judge Terry Fielden, LEED AP BD+C, Director of K-12 Education for International Contractors.

The Building Team phased construction over two summers to minimize disruption, keeping the community involved with a blog, video tours, signage with QR codes, and outreach to local news outlets.

In spring 2013, a severe flood created leaks in the lower-level filtration room. The damage stalled excavation and construction of the pool slab and walls, but IHC Construction, Legat, D219 staff, and other contractors managed to keep the job on schedule and within budget.

The result is a more functional, accessible, energy-efficient facility, designed to use 42% less water and 44% less energy than typical natatoriums. The project, whose heat-recovery dehumidification units should also sharply reduce CO2 emissions, is expected to become the first aquatic center in Illinois to achieve LEED for Schools Gold certification.

Related Stories

Architects | Feb 15, 2022

Binkley Garcia Architecture and Goodwyn Mills Cawood join forces in Nashville

Goodwyn Mills Cawood (GMC) is pleased to announce the acquisition of architecture and interior design firm Binkley Garcia Architecture in Nashville. 

Resiliency | Feb 15, 2022

Design strategies for resilient buildings

LEO A DALY's National Director of Engineering Kim Cowman takes a building-level look at resilient design. 

Products and Materials | Feb 14, 2022

How building owners and developers can get ahead of the next supply chain disaster

Global supply chain interruptions that started at the very beginning of the pandemic are still with us and compounding every step of the way. Below are a few proven tips on how to avert some of the costly fallout should we be faced with similar commercial disasters at any time in the future.

Urban Planning | Feb 14, 2022

5 steps to remake suburbs into green communities where people want to live, work, and play

Stantec's John Bachmann offers proven tactic for retrofitting communities for success in the post-COVID era.

Urban Planning | Feb 11, 2022

6 ways to breathe life into mixed-use spaces

To activate mixed-use spaces and realize their fullest potential, project teams should aim to create a sense of community and pay homage to the local history.

Senior Living Design | Feb 11, 2022

Design for senior living: A chat with Rocky Berg, AIA

Rob Cassidy, Editor of MULTIFAMILY Design + Construction, chats with Rocky Berg, AIA, Principal with Dallas architecture firm three, about how to design senior living communities to meet the needs of the owner, seniors, their families, and staff.

Architects | Feb 11, 2022

How computer simulations of vision loss create more empathetic buildings for the visually impaired

Here is a look at four challenges identified from our research and how the design responds accordingly.

Healthcare Facilities | Feb 10, 2022

Respite for the weary healthcare worker

The pandemic has shined a light on the severe occupational stress facing healthcare workers. Creating restorative hospital environments can ease their feelings of anxiety and burnout while improving their ability to care for patients.

Architects | Feb 8, 2022

Perkins Eastman and BLT Architects merge

Expanding services in hospitality, education, and mixed-use sectors to better serve clients.

Architects | Feb 3, 2022

SmithGroup elevates Mark Adams to lead workplace practice

In his new role, Adams leads the firm’s practice devoted to the design of corporate and commercial facilities.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021