U.S. House moves to give Army Corps of Engineers management of V.A. projects

Healthcare Facilities

U.S. House moves to give Army Corps of Engineers management of V.A. projects

Bill would also put restrictions on planning and design funding.


By Peter Fabris, Contributing Editor | February 19, 2016
U.S. House moves to give Army Corps of Engineers management of V.A. projects

The 182-bed Aurora, Colo., hospital has incurred more than $1 billion in cost overruns. The Army Corps of Engineers has taken over the management of the project. Rendering: V.A.

The U.S. House of Representatives approved a bill that increases oversight and management of Department of Veterans Affairs projects costing more than $100 million. 

The bill would put management of these projects into the hands of the Army Corps of Engineers or other federal agencies. It would also require that the V.A. provide Congress with progress reports.

The legislation would also place financial restrictions on V.A. projects, with a 60-day notice requirement for planning and design funding. The House’s action came after concerns over mismanagement and cost overruns on a new V.A. hospital project in Aurora, Colo. That project is now expected to cost $1.7 billion — three times the original contract price — and is scheduled to open four years behind schedule in 2018. 

Investigators say the project’s problems stem from design changes, and the V.A.'s decision to use a complicated contract process. The bill also authorizes expansion of a Tampa, Fla., V.A. hospital, and provides $561.4 million for five other projects.

The bill will go to the Senate for a vote.

Related Stories

Healthcare Facilities | Feb 16, 2018

Cancer centers' 'one-stop shop'

Healthcare systems ask their AEC partners for design flexibility that is adjustable to advances in medicine and technology.

Healthcare Facilities | Feb 14, 2018

Satellite centers keep cancer treatment closer to patients' orbit

This treatment center is half new construction, half renovation of a building that had been used for family services.

Healthcare Facilities | Feb 1, 2018

Early supplier engagement provides exceptional project outcomes

Efficient supply chains enable companies to be more competitive in the marketplace.

Healthcare Facilities | Jan 30, 2018

Buffett, Bezos, Dimon partner to tackle the U.S. healthcare system

The three mega companies—Amazon, Berkshire Hathaway, and JPMorgan Chase—will pursue the formation of an independent company that is “free from profit-making incentives and constraints” when it comes to U.S. employee healthcare.

Healthcare Facilities | Jan 29, 2018

The new Virginia Tech Biomedical Research Addition will include research facilities in five thematic areas

The project is a collaboration between Carilion Clinic and Virginia Tech.

Healthcare Facilities | Jan 10, 2018

Healthcare market year in review for 2017

While we have not fully turned the corner on healthcare reform and in particular healthcare payment reform, 2017 confirmed trends of consumerism and the need for more proximate low-cost options.

Retail Centers | Jan 9, 2018

The addition of a medical practice is part of the cure for reviving a shopping mall in Scranton, Pa.

Delta Medix is one of several tenants that are changing the image of the Marketplace at Steamtown.

Healthcare Facilities | Jan 6, 2018

A new precision dental center embodies Columbia University’s latest direction for oral medicine education

The facility, which nests at “the core” of the university’s Medical Center, relies heavily on technology and big data. 

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021