Updated AIA contracts clarify the role of construction managers

Contractors

Updated AIA contracts clarify the role of construction managers

The revised documents refine how CMs serve as general contractors or project advisers.


By John Caulfield, Senior Editor | November 5, 2019

This schematic shows how the family of Construction Manager as Constructor contracts works as a delivery method. Images: AIA

On Nov. 15, the American Institute of Architects (AIA) plans to release its new and updated Construction Manager as Constructor (CMc) family of contract documents. Next February, the AIA will release its updated Construction Manager as Adviser (CMa) family of documents.

These documents get updated on a 10-year revision cycle.

The AIA divides its contract documents into nine families, organized by delivery method. These include families for design-bid-build (the most widely used contract model), design-build, and integrated project delivery, as well as contracts that specifically cover interiors, small projects, and digital practices. The design-bid-build document family was updated in 2017.

Under CMc, the Construction Manager comes on the project during the preconstruction phase to provide early collaboration. In the construction phase, the CM does the construction work, as if it were a General Contractor.

Under the CMa, the Construction Manager is also retained by the owner for early collaboration during the preconstruction phase. But the CMas don’t perform the construction work. The CMa documents are designed for complex projects with more than one prime contractor. During the construction phase, the CMa coordinates and manages the contractors, as well as providing cost estimating and other functions.

Susan Van Bell, Senior Director and Counsel – AIA Contract Documents Content, tells BD+C that the AIA solicited input from CM practitioners about revisions to the documents so that they’d better reflect current practices.

From those conversations, CMs suggested that one change they wanted was a way to tailor the document for the scope of preconstruction services without having the standard contract language be too restrictive.

Van Bell says the 2019 CMc revision addresses this issue by inserting “fill points” into the contract where more preconstruction details can be identified. The update also makes some edits to the standard preconstruction services scope.

A schematic of the family of documents for Construction Manager as Advisor.

 

The CMc documents now include insurance and bond exhibits, which had been added to the design-bid-build document family in its 2017 revision. Van Bell says there are also new exhibits for both the CMc and CMa documents that cover the role of the CM in sustainable projects.

The revised CMa documents clarify the CMa’s role in such areas as analyzing and coordinating the contractors’ schedules. The CMa is also the responsible party for managing a project’s digital information systems. “We clarified the communication process,” Van Bell says. The 2017 updates that required the establishment of protocols for digital data and BIM were carried into the CMc and CMa updates.

Related Stories

| Jun 27, 2012

KBE Building wins honor for Armed Forces Reserve Center

The construction phase was completed in just 16 months.

| Jun 27, 2012

SOM’s Baker receives honorary doctorate in engineering from Heriot-Watt University

Baker recognized for his career and influential contribution in the field of structural engineering.

| Jun 25, 2012

Living green wall planned for InterContinental Chicago

Project, with price tag of $2 million to $3 million, needs council approval.

| Jun 25, 2012

AIA-NJ honors DMR Architects

The academic building, completed in 2009, provides classrooms, computer labs, faculty offices, and meeting spaces for the College, which has a steady 7% annual increase in enrollment.

| Jun 25, 2012

Thornton Tomasetti appoints Hofmeister and Zhu to board of directors

The addition of Hofmeister and Zhu brings the number of directors to 10.

| Jun 15, 2012

Beck Group/Atlanta wins AGC Build Georgia Award

Site-specific safety plan, BIM analysis and third-party structural review contributed to successful implementation.

| Jun 15, 2012

Baldwin joins Charlotte office of Perkins Eastman as principal

Experience in healthcare planning and design to expand national healthcare practice in South and Mid-Atlantic.

| Jun 15, 2012

InPro’s bio-content becomes Cradle-to-Cradle CertifiedCM Silver

Two main components of G2 Blend formula now C2C Certified Silver.

| Jun 14, 2012

A. Eugene Kohn Watercolor Exhibition a showcase of KPF artwork in NYC

Kohn's watercolors have previously been displayed at the Guggenheim Museum in a show for the works of well-known architects.

boombox1
boombox2
native1

More In Category



Curtain Wall

7 steps to investigating curtain wall leaks

It is common for significant curtain wall leakage to involve multiple variables. Therefore, a comprehensive multi-faceted investigation is required to determine the origin of leakage, according to building enclosure consultants Richard Aeck and John A. Rudisill with Rimkus. 


halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021