Updated AIA contracts clarify the role of construction managers

Contractors

Updated AIA contracts clarify the role of construction managers

The revised documents refine how CMs serve as general contractors or project advisers.


By John Caulfield, Senior Editor | November 5, 2019

This schematic shows how the family of Construction Manager as Constructor contracts works as a delivery method. Images: AIA

On Nov. 15, the American Institute of Architects (AIA) plans to release its new and updated Construction Manager as Constructor (CMc) family of contract documents. Next February, the AIA will release its updated Construction Manager as Adviser (CMa) family of documents.

These documents get updated on a 10-year revision cycle.

The AIA divides its contract documents into nine families, organized by delivery method. These include families for design-bid-build (the most widely used contract model), design-build, and integrated project delivery, as well as contracts that specifically cover interiors, small projects, and digital practices. The design-bid-build document family was updated in 2017.

Under CMc, the Construction Manager comes on the project during the preconstruction phase to provide early collaboration. In the construction phase, the CM does the construction work, as if it were a General Contractor.

Under the CMa, the Construction Manager is also retained by the owner for early collaboration during the preconstruction phase. But the CMas don’t perform the construction work. The CMa documents are designed for complex projects with more than one prime contractor. During the construction phase, the CMa coordinates and manages the contractors, as well as providing cost estimating and other functions.

Susan Van Bell, Senior Director and Counsel – AIA Contract Documents Content, tells BD+C that the AIA solicited input from CM practitioners about revisions to the documents so that they’d better reflect current practices.

From those conversations, CMs suggested that one change they wanted was a way to tailor the document for the scope of preconstruction services without having the standard contract language be too restrictive.

Van Bell says the 2019 CMc revision addresses this issue by inserting “fill points” into the contract where more preconstruction details can be identified. The update also makes some edits to the standard preconstruction services scope.

A schematic of the family of documents for Construction Manager as Advisor.

 

The CMc documents now include insurance and bond exhibits, which had been added to the design-bid-build document family in its 2017 revision. Van Bell says there are also new exhibits for both the CMc and CMa documents that cover the role of the CM in sustainable projects.

The revised CMa documents clarify the CMa’s role in such areas as analyzing and coordinating the contractors’ schedules. The CMa is also the responsible party for managing a project’s digital information systems. “We clarified the communication process,” Van Bell says. The 2017 updates that required the establishment of protocols for digital data and BIM were carried into the CMc and CMa updates.

Related Stories

Contractors | Feb 13, 2015

Survey shows craft labor shortage may slow construction

32% of surveyed contract professionals said they will experience slow growth if their companies cannot reasonably meet the need for skilled labor and tradespeople.

Mixed-Use | Feb 13, 2015

First Look: Sacramento Planning Commission approves mixed-use tower by the new Kings arena

The project, named Downtown Plaza Tower, will have 16 stories and will include a public lobby, retail and office space, 250 hotel rooms, and residences at the top of the tower. 

Architects | Feb 13, 2015

OMA commissioned to design newest New York High Line addition

Rem Koolhaas is the latest addition to the list of starchitects working on projects near the High Line elevated park.

Codes and Standards | Feb 12, 2015

ASHRAE, USGBC, IES consider biomass requirements in green building standard

The proposal would add biomass to approved renewables.

Codes and Standards | Feb 12, 2015

New Appraisal Institute form aids in analysis of green commercial building features

The Institute’s Commercial Green and Energy Efficient Addendum offers a communication tool that lenders can use as part of the scope of work. 

Office Buildings | Feb 12, 2015

Is Houston headed for an office glut?

More than 13 million sf could be completed this year, adding to this metro’s double-digit vacancy woes.

Modular Building | Feb 12, 2015

New shipping container complex begins construction in Albuquerque

The Green Jeans Farmery already has a hydroponic farm component courtesy of owner and entrepreneur Roy Solomon.

Transit Facilities | Feb 12, 2015

Gensler proposes network of cycle highways in London’s unused underground

Unused tube lines would host pedestrian paths, cycle routes, cultural spaces, and retail outlets.

Healthcare Facilities | Feb 11, 2015

Primer: Using 'parallel estimating' to pinpoint costs on healthcare construction projects

As pressure increases to understand capital cost prior to the first spade touching dirt, more healthcare owners are turning to advanced estimating processes, like parallel estimating, to improve understanding of exposure, writes CBRE Healthcare's Andrew Sumner.

Transportation & Parking Facilities | Feb 11, 2015

11 of the nation’s best ‘Complete Streets’ policies of 2014

Austin, Texas, and Troy, N.Y., are among the cities with the strongest safe streets policies, according to a new report.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021