Updated AIA contracts clarify the role of construction managers

Contractors

Updated AIA contracts clarify the role of construction managers

The revised documents refine how CMs serve as general contractors or project advisers.


By John Caulfield, Senior Editor | November 5, 2019

This schematic shows how the family of Construction Manager as Constructor contracts works as a delivery method. Images: AIA

On Nov. 15, the American Institute of Architects (AIA) plans to release its new and updated Construction Manager as Constructor (CMc) family of contract documents. Next February, the AIA will release its updated Construction Manager as Adviser (CMa) family of documents.

These documents get updated on a 10-year revision cycle.

The AIA divides its contract documents into nine families, organized by delivery method. These include families for design-bid-build (the most widely used contract model), design-build, and integrated project delivery, as well as contracts that specifically cover interiors, small projects, and digital practices. The design-bid-build document family was updated in 2017.

Under CMc, the Construction Manager comes on the project during the preconstruction phase to provide early collaboration. In the construction phase, the CM does the construction work, as if it were a General Contractor.

Under the CMa, the Construction Manager is also retained by the owner for early collaboration during the preconstruction phase. But the CMas don’t perform the construction work. The CMa documents are designed for complex projects with more than one prime contractor. During the construction phase, the CMa coordinates and manages the contractors, as well as providing cost estimating and other functions.

Susan Van Bell, Senior Director and Counsel – AIA Contract Documents Content, tells BD+C that the AIA solicited input from CM practitioners about revisions to the documents so that they’d better reflect current practices.

From those conversations, CMs suggested that one change they wanted was a way to tailor the document for the scope of preconstruction services without having the standard contract language be too restrictive.

Van Bell says the 2019 CMc revision addresses this issue by inserting “fill points” into the contract where more preconstruction details can be identified. The update also makes some edits to the standard preconstruction services scope.

A schematic of the family of documents for Construction Manager as Advisor.

 

The CMc documents now include insurance and bond exhibits, which had been added to the design-bid-build document family in its 2017 revision. Van Bell says there are also new exhibits for both the CMc and CMa documents that cover the role of the CM in sustainable projects.

The revised CMa documents clarify the CMa’s role in such areas as analyzing and coordinating the contractors’ schedules. The CMa is also the responsible party for managing a project’s digital information systems. “We clarified the communication process,” Van Bell says. The 2017 updates that required the establishment of protocols for digital data and BIM were carried into the CMc and CMa updates.

Related Stories

| Aug 1, 2016

K-12 SCHOOL GIANTS: In a new era of K-12 education, flexibility is crucial to design

Space flexibility is critical to classroom design. Spaces have to be adaptable, even allowing for drastic changes such as a doubling of classroom size.

| Aug 1, 2016

Top 80 K-12 School Construction Firms

Gilbane, Balfour Beatty, and Core Construction head Building Design+Construction’s annual ranking of the nation’s largest K-12 school sector construction and construction management firms, as reported in the 2016 Giants 300 Report.

| Jul 29, 2016

AIRPORT FACILITIES GIANTS: Airports binge on construction during busy year for travel

Terminal construction will grow by nearly $1 billion this year, and it will keep increasing. Airports are expanding and modernizing their facilities to keep passengers moving.

| Jul 29, 2016

Top 45 Airport Terminal Construction and CM Firms

Hensel Phelps generated more than $660 million in revenue last year to earn the top spot on BD+C’s annual ranking of the nation’s largest airport terminal construction and CM firms.  

| Jul 27, 2016

Turner turns to design-build, P3, Lean practices, and engineering services

Design-build has accounted for a notable portion of Turner’s work over the last few years.

| Jul 27, 2016

CONSTRUCTION GIANTS: Economists forecast moderation for nonresidential projects

Construction spending is up this year and is expected to continue to increase through 2017. But, economists identified factors that could slow construction spending.

| Jul 27, 2016

Top 70 Construction Management Firms

Hill International, Jacobs, and JLL head Building Design+Construction's 2016 ranking of the largest construction management and project management firms in the United States. 

| Jul 27, 2016

Top 115 Contractor Firms

Turner Construction, Whiting-Turner Contracting, Fluor, and Skanska top Building Design+Construction's 2016 ranking of the largest contractors in the United States. 

Sports and Recreational Facilities | Jul 20, 2016

San Diego’s waterfront redevelopment would go beyond a mere ‘project’

Its developers envision a thriving business, education, and entertainment district, highlighted by a huge observation tower and aquarium.

| Jul 19, 2016

2016 GIANTS 300 REPORT: Ranking the nation's largest architecture, engineering, and construction firms

Now in its 40th year, BD+C’s annual Giants 300 report ranks AEC firms by discipline and across more than 20 building sectors and specialty services.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021