University of Toledo, Memorial Field House

University of Toledo, Memorial Field House


By By Robert Cassidy, Editorial Director | October 12, 2010

Memorial Field House, once the lovely Collegiate Gothic (ca. 1933) centerpiece (along with neighboring University Hall) of the University of Toledo campus, took its share of abuse after a new athletic arena made it redundant, in 1976. The ultimate insult occurred when the ROTC used it as a paintball venue.

All that changed in 2006, when the university, facing a burst in student enrollment, an expansion of program offerings, and concern about future space needs, commissioned a major overhaul that, three years later, recast the 134,200-sf gymnasium into a LEED Gold learning environment housing classrooms, teaching labs, faculty offices, and space for future growth.

The extensive Building Team, led by Cincinnati’s BHDP Architecture, literally constructed a building within a building, expanding the single-floor high-bay arena into three floors within the existing building envelope. The tri-level structure, with its exposed steel truss supports, features a dramatic cruciform skylight above a “Town Hall” atrium that has become one of the most popular meeting and study spaces on campus.

Planning for the project ensured that the university would have sufficient classroom space to meet its enrollment projections through 2020. Fifty-four classrooms, varying in size for classes of 20, 30, or 40, were built. A practice gym was converted into a 250-seat, three-screen auditorium; another was repurposed for language laboratories. The “Collegiate Loft” on the new third floor houses the UT Center for Teaching and Learning. The latest A/V equipment—flat panel monitors, electronic whiteboards, audience response systems—enables multiple teaching styles.

Memorial Field House was the university’s first LEED Gold building. Two noteworthy innovations: 1) the Building Team kept a chilled water plant housed in the building’s central courtyard fully operation, along with a 15kV electrical substation and main campus communications fiber; and 2) the team field erected new air-handling units in two old basketball gyms and integrated engineered smoke control with the new skylight system.

“They definitely did their homework,” said jurist Tom Brooks, VP of Reconstruction at Chicago’s Berglund Construction. “They maintained the façade, which is important to me, and did it all on a budget so low it almost looks like a typo.” For the record, construction costs were $21.5 million, or $160/sf. BD+C

PROJECT SUMMARY

Building Team

Owner: The University of Toledo

Submitting firm: BHDP Architecture (architect, interior designer)

Civil/structural engineer: Poggemeyer Design Group

MEP engineer: Heapy Engineering

Program analyst: Comprehensive Facilities Planning, Inc.

General contractor: A. Z. Shimina, Inc.

A/V, IT, acoustics consultant: The Sextant Group

Steel construction: Mosser Construction

Cost consultant: ProjDel Corp.

General Information

Area: 134,200 gsf

Construction cost: $21.5 million

Construction time: January 2006 to January 2009

Related Stories

BIM and Information Technology | Aug 6, 2015

After refueling its capital tank, WeWork acquires BIM consultant Case

The merger is expected to help standardize how WeWork designs and builds out office space. 

Giants 400 | Aug 6, 2015

BIM GIANTS: Robotic reality capture, gaming systems, virtual reality—AEC Giants continue tech frenzy

Given their size, AEC Giants possess the resources and scale to research and test the bevy of software and hardware solutions on the market. Some have created internal innovation labs and fabrication shops to tinker with emerging technologies and create custom software tools. Others have formed R&D teams to test tech tools on the job site.

Giants 400 | Aug 6, 2015

GIANTS 300 REPORT: Top 115 Healthcare Architecture Firms

HDR, Stantec, and Perkins+Will top Building Design+Construction's 2015 ranking of the largest healthcare architecture and architecture/engineering firms in the U.S. 

Giants 400 | Aug 6, 2015

HEALTHCARE AEC GIANTS: Hospital and medical office construction facing a slow but steady recovery

Construction of hospitals and medical offices is expected to shake off its lethargy in 2015 and recover modestly over the next several years, according to BD+C's 2015 Giants 300 report.

Codes and Standards | Aug 6, 2015

ConsensusDocs releases new CM agency contract standard agreement

For use when owner acts as the construction manager, hires a construction manager, or uses multiple prime contractors

Giants 400 | Aug 5, 2015

GIANTS 300 REPORT: Top 135 Office Sector Architecture Firms

Gensler, HOK, and Perkins+Will top BD+C's ranking of the nation's largest office sector architecture and architecture/engineering firms. 

Giants 400 | Aug 5, 2015

OFFICE SECTOR GIANTS: Today’s workplace design must appeal to Millennials’ ‘activity-based’ lifestyle

Office market AEC Giants discuss the latest trends workplace design, and the state of the office construction sector.

Giants 400 | Aug 5, 2015

GIANTS 300 REPORT: Top 37 Engineering/Architecture Firms

Jacobs, AECOM, and Thornton Tomasetti head Building Design+Construction's 2015 ranking of the largest engineering/architecture firms in the United States. 

Giants 400 | Aug 5, 2015

ENGINEERING GIANTS: Profits, revenue on the rise at U.S. engineering firms as economy sputters back to life

The vast majority of engineering firms are decidedly bullish on revenue growth for 2015, and profitability is nearing a six-year high, according to BD+C's 2015 Giants 300 report.  

Giants 400 | Aug 4, 2015

GIANTS 300 REPORT: Top 64 Architecture/Engineering Firms

Stantec, HOK, and Callison RTKL top Building Design+Construction's 2015 ranking of the largest architecture/engineering firms in the United States. 

boombox1
boombox2
native1

More In Category

Construction Costs

Data center construction costs for 2024

Gordian’s data features more than 100 building models, including computer data centers. These localized models allow architects, engineers, and other preconstruction professionals to quickly and accurately create conceptual estimates for future builds. This table shows a five-year view of costs per square foot for one-story computer data centers. 


Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.



Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021