Memorial Field House, once the lovely Collegiate Gothic (ca. 1933) centerpiece (along with neighboring University Hall) of the University of Toledo campus, took its share of abuse after a new athletic arena made it redundant, in 1976. The ultimate insult occurred when the ROTC used it as a paintball venue.

All that changed in 2006, when the university, facing a burst in student enrollment, an expansion of program offerings, and concern about future space needs, commissioned a major overhaul that, three years later, recast the 134,200-sf gymnasium into a LEED Gold learning environment housing classrooms, teaching labs, faculty offices, and space for future growth.

The extensive Building Team, led by Cincinnati’s BHDP Architecture, literally constructed a building within a building, expanding the single-floor high-bay arena into three floors within the existing building envelope. The tri-level structure, with its exposed steel truss supports, features a dramatic cruciform skylight above a “Town Hall” atrium that has become one of the most popular meeting and study spaces on campus.

Planning for the project ensured that the university would have sufficient classroom space to meet its enrollment projections through 2020. Fifty-four classrooms, varying in size for classes of 20, 30, or 40, were built. A practice gym was converted into a 250-seat, three-screen auditorium; another was repurposed for language laboratories. The “Collegiate Loft” on the new third floor houses the UT Center for Teaching and Learning. The latest A/V equipment—flat panel monitors, electronic whiteboards, audience response systems—enables multiple teaching styles.

Memorial Field House was the university’s first LEED Gold building. Two noteworthy innovations: 1) the Building Team kept a chilled water plant housed in the building’s central courtyard fully operation, along with a 15kV electrical substation and main campus communications fiber; and 2) the team field erected new air-handling units in two old basketball gyms and integrated engineered smoke control with the new skylight system.

“They definitely did their homework,” said jurist Tom Brooks, VP of Reconstruction at Chicago’s Berglund Construction. “They maintained the façade, which is important to me, and did it all on a budget so low it almost looks like a typo.” For the record, construction costs were $21.5 million, or $160/sf. BD+C

PROJECT SUMMARY

Building Team

Owner: The University of Toledo

Submitting firm: BHDP Architecture (architect, interior designer)

Civil/structural engineer: Poggemeyer Design Group

MEP engineer: Heapy Engineering

Program analyst: Comprehensive Facilities Planning, Inc.

General contractor: A. Z. Shimina, Inc.

A/V, IT, acoustics consultant: The Sextant Group

Steel construction: Mosser Construction

Cost consultant: ProjDel Corp.

General Information

Area: 134,200 gsf

Construction cost: $21.5 million

Construction time: January 2006 to January 2009

Related Stories

Codes and Standards | Jun 1, 2022

HKS, U. of Texas Dallas partner on brain health study

HKS and The University of Texas at Dallas’ Center for BrainHealth are conducting a six-month study to improve the way the firm’s employees work, collaborate, and innovate, both individually and as an organization, according to a news release.

Building Team | Jun 1, 2022

Pennsylvania’s Longwood Gardens to get a $250 million transformation

Longwood Gardens, a botanical garden with about 1,100 acres in Pennsylvania’s Brandywine Valley, recently announced plans to transform its core area of conservatory gardens.

Mass Timber | May 31, 2022

Tall mass timber buildings number 139 worldwide

An audit of tall mass timber buildings turned up 139 such structures around the world either complete, under construction, or proposed.

Hotel Facilities | May 31, 2022

Checking out: Tips for converting hotels to housing

Many building owners are considering repositioning their hotels into another property type, such as senior living communities and rental apartments. Here's advice for getting started. 

Museums | May 31, 2022

University of Texas at Dallas breaks ground on new 12-acre cultural district

The University of Texas at Dallas (UT Dallas) recently broke ground on the Crow Museum of Asian Art, the first phase of a new 12-acre cultural district on campus.

BAS and Security | May 26, 2022

Can your intelligent building outsmart hackers?

ESD's security services studio leader Coleman Wolf offers tips, advice, and lessons for protecting real estate assets from cyberattacks.

Sports and Recreational Facilities | May 26, 2022

WNBA practice facility will offer training opportunities for female athletes and youth

The Seattle Storm’s Center for Basketball Performance will feature amenities for community youth, including basketball courts, a nutrition center, and strength and conditioning training spaces.

Multifamily Housing | May 25, 2022

9 noteworthy multifamily developments to debut in 2022

A 1980s-era shopping mall turned mixed-use housing and a mid-rise multifamily tower with unusual rowhomes highlight the innovative multifamily developments to debut recently.

Coronavirus | May 20, 2022

Center for Green Schools says U.S. schools need more support to fight COVID-19

  The Center for Green Schools at the U.S. Green Building Council released a new report detailing how school districts around the country have managed air quality within their buildings during the second year of the COVID-19 pandemic.

Regulations | May 20, 2022

Biden’s Clean Air in Buildings Challenge aims to reduce COVID-⁠19 spread

The Biden Administration recently launched the Clean Air in Buildings Challenge that calls on all building owners and operators, schools, colleges and universities, and organizations to adopt strategies to improve indoor air quality in their buildings and reduce the spread of COVID-19.

boombox1
boombox2
native1

More In Category


Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.



halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021