Undoing 5 myths of IPD and Lean construction

Contractors

Undoing 5 myths of IPD and Lean construction

The Lean Construction Institute, one of this year’s Movers+Shapers, has been sponsoring valuable research recently.


By Robert Cassidy, Executive Editor | March 9, 2018

Motivation and Means: How and Why IPD and Lean Lead to Success”, co-sponsored by the Integrated Project Delivery Alliance, explodes several myths about Lean and IPD.

Myth #1: Delivery matters less than choosing the right people; behaviors can’t be dictated by a contract. You won’t get the A Team every time, but you can still foster positive behavior, says principal author Renée Cheng, PhD, AIA, Professor, School of Architecture, University of Minnesota. Think through which players you want on your team, how to create the right culture, and how to get rid of nonperformers.

Myth #2: IPD contracts are too complicated, Lean tools are too rigid. IPD and Lean are “a lot more flexible than people think,” says Cheng. Investing the time up front for designing your IPD and Lean procedures can pay off in huge ROI. Teams also vary in how they use IPD and Lean. It’s not as rigid as commonly believed, she says.

Myth #3: IPD only works on large complex healthcare projects. Teams new to IPD and Lean are at a disadvantage. Cheng says there’s no evidence that small projects cannot benefit from using an IPD and Lean. Moreover, you can have a team that’s new to IPD, or one that has half its team members experienced in IPD and Lean, and both can still work, she says.

Myth #4: Owners aren’t getting best value; or, owners are getting value but the team is not making a profit. Cheng says it’s hard to get at “pure results” for owners because “it usually depends on how well the owner sets the cost and schedule targets.” The research did show that 100% of owners in the study said their IPD/Lean projects met or exceeded expectations.

In terms of meeting schedule, some teams were just a bit over, a number were under. Similarly, with regard to budgets, one project team went over, some were at budget, a number were under.

As for profitability, Cheng says some project teams have reported making 20-30% more in an IPD than under a non-IPD. “I did see teams working collectively with the owner to determine a target cost, and this drove the original allowable cost way below market, and the profit was distributed.”

Myth #5: IPD and IPD-lite are essentially the same; financial incentives and release of liability are no big deal. Cheng says the behavior is “strikingly different” between those who have skin in the game and those who do not. “Those in the signatory pool behave much more collaboratively, there’s a lot more fluidity in how they’re willing to trade scope, and they’re much more willing to call out behavior that’s not productive.”

Finally, there’s a lot more “fun and enjoyment” in true IPD projects, says Cheng—“a lot more time being spent on positive things. It’s very positive and collaborative.”

Related Stories

| Nov 11, 2012

Under40 Leadership Summit draws 71 young leaders to Chicago

More than 70 young—that is, under age 40—architects, engineers, and construction professionals descended on Chicago in early October with one thought in mind: to learn how to “create with clarity.”

| Nov 11, 2012

AIA: Building Envelope

Preventing and treating failure in glazed curtain wall systems. Earn 1.0 AIA/CES learning units by studying this article and successfully completing the online exam.

| Nov 11, 2012

Greenbuild 2012 Report: Hospitality

Hotel boom signals good news for greener lodging facilities

| Nov 11, 2012

Greenbuild 2012 Report: Government & Military

Public sector remains a bastion of sustainability

| Nov 11, 2012

Greenbuild 2012 Report: Healthcare

Green medical facilities extend beyond hospital walls

| Nov 11, 2012

Greenbuild 2012 Report: Multifamily

Sustainably designed apartments are apples of developers’ eyes

| Nov 11, 2012

Greenbuild 2012 Report: Higher Education

More and more colleges and universities see sustainainably designed buildings as a given

| Nov 11, 2012

Greenbuild 2012 Report: K-12

High-performance schools put ‘sustainability’ in the lesson plan

| Nov 11, 2012

Greenbuild 2012 Report

Enter the new era of ‘disclosure and transparency’

| Nov 7, 2012

John Portman & Associates awarded new high rise in China

108-story building to rise in Nanning, the Capital City of Guangxi Province.

boombox1
boombox2
native1

More In Category

Great Solutions

41 Great Solutions for architects, engineers, and contractors

AI ChatBots, ambient computing, floating MRIs, low-carbon cement, sunshine on demand, next-generation top-down construction. These and 35 other innovations make up our 2024 Great Solutions Report, which highlights fresh ideas and innovations from leading architecture, engineering, and construction firms.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021