Turner employs rare 'collapsible' steel truss system at Seattle light rail station

Turner employs rare 'collapsible' steel truss system at Seattle light rail station

Innovative formwork will speed construction of below-grade construction at the $110 million Capitol Hill Station.


By BD+C Staff | February 25, 2013
To speed construction of the $110 million Capitol Hill Station light-rail statio
To speed construction of the $110 million Capitol Hill Station light-rail station in Seattle, general contractor Turner Construc

To speed construction of the $110 million Capitol Hill Station light-rail station in Seattle, general contractor Turner Construction will use an unusual temporary framing method for the project's underground spaces.

Like building a ship in a bottle, the "collapsible" steel truss system will be lowered into the shaft and expanded to form the framework for the station's concrete walls and floors, according to CHS Capitol Hill Seattle Blog.

Using the steel truss system, Turner will complete 40 feet at a time. Once the concrete is dry, the framework will be collapsed and used to create the next section. The frame system also incorporates PVC piping that will circulate cool water to assist in concrete curing time.

The station is scheduled to open in 2016.

(http://www.capitolhillseattle.com/2013/02/22/innovative-wall-floor-construction-set-to-begin-inside-capitol-hill-station)

Related Stories

| Aug 11, 2010

Theater Renovation—A First-Class Production

In 1985, the city of San Diego ordered the historic Balboa Theatre, its beleaguered performing arts center, to be shuttered due to seismic safety concerns. It would take another two decades to restore the landmark building.

| Aug 11, 2010

American Concrete Institute forms technical committee on BIM for concrete structures

The American Concrete Institute (ACI) announces the formation of a new technical committee on Building Information Modeling (BIM) of Concrete Structures.

| Aug 11, 2010

10 tips for mitigating influenza in buildings

Adopting simple, common-sense measures and proper maintenance protocols can help mitigate the spread of influenza in buildings. In addition, there are system upgrades that can be performed to further mitigate risks. Trane Commercial Systems offers 10 tips to consider during the cold and flu season.

| Aug 11, 2010

NAVFAC releases guidelines for sustainable reconstruction of Navy facilities

The guidelines provide specific guidance for installation commanders, assessment teams, estimators, programmers and building designers for identifying the sustainable opportunities, synergies, strategies, features and benefits for improving installations following a disaster instead of simply repairing or replacing them as they were prior to the disaster.

| Aug 11, 2010

Proposed EPA regulations threaten thousands of jobs, says Portland Cement Association

A proposed hazardous air pollutant regulation for the cement industry undermines the balance between environmental protection and economic viability, according to statements the Portland Cement Association (PCA) is issuing this week at a series of public hearings.

| Aug 11, 2010

Turner, Webcor, Hensel Phelps top BD+C's list of the 75 largest green contractors

With more than $3 billion in value of construction put in place for green buildings in 2008, Turner Construction tops BD+C’s ranking of the nation’s 75 largest green contractors, published as part of the Giants 300 report. Webcor Builders ($2.27 billion), Hensel Phelps Construction ($2.10 billion), The Whiting-Turner Contracting Co. ($1.97 billion), and Clark Group ($1.89 billion) round out the top five.

boombox1
boombox2
native1

More In Category




Contractors

Contractors expect to spend more time on prefabrication, according to FMI study

Get ready for a surge in prefabrication activity by contractors. FMI, the consulting and investment banking firm, recently polled contractors about how much time they were spending, in craft labor hours, on prefabrication for construction projects. More than 250 contractors participated in the survey, and the average response to that question was 18%. More revealing, however, was the participants’ anticipation that craft hours dedicated to prefab would essentially double, to 34%, within the next five years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021