Turner employs rare 'collapsible' steel truss system at Seattle light rail station

Turner employs rare 'collapsible' steel truss system at Seattle light rail station

Innovative formwork will speed construction of below-grade construction at the $110 million Capitol Hill Station.


By BD+C Staff | February 25, 2013
To speed construction of the $110 million Capitol Hill Station light-rail statio
To speed construction of the $110 million Capitol Hill Station light-rail station in Seattle, general contractor Turner Construc

To speed construction of the $110 million Capitol Hill Station light-rail station in Seattle, general contractor Turner Construction will use an unusual temporary framing method for the project's underground spaces.

Like building a ship in a bottle, the "collapsible" steel truss system will be lowered into the shaft and expanded to form the framework for the station's concrete walls and floors, according to CHS Capitol Hill Seattle Blog.

Using the steel truss system, Turner will complete 40 feet at a time. Once the concrete is dry, the framework will be collapsed and used to create the next section. The frame system also incorporates PVC piping that will circulate cool water to assist in concrete curing time.

The station is scheduled to open in 2016.

(http://www.capitolhillseattle.com/2013/02/22/innovative-wall-floor-construction-set-to-begin-inside-capitol-hill-station)

Related Stories

| Dec 28, 2014

Robots, drones, and printed buildings: The promise of automated construction

Building Teams across the globe are employing advanced robotics to simplify what is inherently a complex, messy process—construction.

BIM and Information Technology | Dec 28, 2014

The Big Data revolution: How data-driven design is transforming project planning

There are literally hundreds of applications for deep analytics in planning and design projects, not to mention the many benefits for construction teams, building owners, and facility managers. We profile some early successful applications.  

| Dec 23, 2014

5 tech trends transforming BIM/VDC

From energy modeling on the fly to prefabrication of building systems, these advancements are potential game changers for AEC firms that are serious about building information modeling. 

| Dec 17, 2014

ULI report looks at growing appeal of micro unit apartments

New research from the Urban Land Institute suggests that micro units have staying power as a housing type that appeals to urban dwellers in high-cost markets who are willing to trade space for improved affordability and proximity to downtown neighborhoods.

| Nov 3, 2014

Novel 'self-climbing' elevator operates during construction of high-rise buildings

The JumpLift system from KONE uses a mobile machine room that moves upward as the construction progresses, speeding construction of tall towers. 

| Oct 14, 2014

Slash energy consumption in data centers with liquid-based ‘immersive-cooling’ technology

A new technology promises to push the limits of data center energy efficiency by using liquid instead of air to cool the servers.

| Sep 10, 2014

Must See: Shape-shifting architecture that responds to heat

Students in Barcelona have created a composite material using shape memory polymers that can deform and return to their original state when activated by cues like heat, humidity, and light.

| Aug 4, 2014

Facebook’s prefab data center concept aims to slash construction time in half

Less than a year after opening its ultra-green, hydropowered data center facility in Luleå, Sweden, Facebook is back at it in Mother Svea with yet another novel approach to data center design.

| Aug 4, 2014

BIM Giants: Firms enhance BIM/VDC with advanced collaboration tools [2014 Giants 300 Report]

Cloud-based data sharing, rapid iterative design, and cross-discipline collaboration are among the emerging trends in the BIM/VDC field, according to BD+C's 2014 Giants 300 Report.

| Jul 15, 2014

A look into the history of modular construction

Modular construction is more than a century old, and throughout its lifespan, the methods have been readapted to meet specific needs of different eras.

boombox1
boombox2
native1

More In Category




Contractors

Contractors expect to spend more time on prefabrication, according to FMI study

Get ready for a surge in prefabrication activity by contractors. FMI, the consulting and investment banking firm, recently polled contractors about how much time they were spending, in craft labor hours, on prefabrication for construction projects. More than 250 contractors participated in the survey, and the average response to that question was 18%. More revealing, however, was the participants’ anticipation that craft hours dedicated to prefab would essentially double, to 34%, within the next five years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021