Transforming a landmark coastal resort

Transforming a landmark coastal resort

Originally built in 1973, the building had received several alterations over the years but the progressive deterioration caused by the harsh salt water environment had never been addressed.


November 8, 2011
The extent of concrete deterioration was so severe that the balconies and walkways were completely removed and replaced with new

The Royal Floridian is a seven story vacation resort that is a major economic driver in the small coastal town of Ormond Beach, Fla. Originally built in 1973, the building had received several alterations over the years but the progressive deterioration caused by the harsh salt water environment had never been addressed.

The restoration team, led by ConTech Construction, was hired 1½ years before construction started, which allowed for extensive planning. The engineer performed both non-destructive and limited destructive testing to determine the extent and cause of structural deficiencies. These explorations uncovered severe corrosion of the structural steel support columns and beams under the north and south cantilevered ends of the building. Other findings were chloride content in the concrete balconies of over 5 lbs per cubic yard, hundreds of top and bottom spalls, and large areas of cracked and disbonded stucco. Water intrusion was causing deterioration inside the living areas.

The extent of concrete deterioration was so severe that the balconies and walkways were completely removed and replaced with new concrete containing a corrosion inhibitor admixture. Other concrete areas were selectively repaired with pre-packaged structural repair mortars.

The team also executed an architectural aesthetic make over that transformed the worn out, drab facility into a gorgeous, modern destination resort. The entire east face of the building was reconstructed, including new balconies, new insulated windows and doors and 15 BASF products, including Sonoguard waterproofing membranes and Thorocoat, Thorolastic and Thorosheen acrylic exterior coatings.

New pavers were installed over the waterproofing membrane on the pool deck over the parking garage, and new concrete swimming pools completed the transformation of this landmark resort. 

To learn more about the Royal Floridian project, click here to watch the video. BD+C

Related Stories

Sponsored | Building Team | Dec 12, 2017

3 tips to address the top causes of budget overruns

The most cited issues are communication breakdowns, inadequate fees for the work provided, and unrealistic deadlines or schedules.

Multifamily Housing | Dec 12, 2017

Call for technical experts: Dog wash station design

The editors of Multifamily Design + Construction magazine need your expertise.

Government Buildings | Dec 11, 2017

Is this the world’s most humane prison?

The C.F. Møller-designed prison’s architecture supports the inmates’ and staff’s mental and physical well-being.

Architects | Dec 7, 2017

Snow Kreilich Architects receives the 2018 AIA Architecture Firm Award

Julie Snow, FAIA, founded the firm in Minneapolis in 1995, and later was joined by partner Matt Kreilich, AIA.

Architects | Dec 7, 2017

2018 AIA Gold Medal awarded to James Stewart Polshek

In 1963 Polshek started his first architecture firm, James Stewart Polshek Architect.

Architects | Dec 4, 2017

Architects to Congress: ‘You're making a terrible mistake’

House and Senate gut historic building credits and penalize architecture firms.

Architects | Dec 1, 2017

The third wave of urban waterfront development

The nature of waterfront redevelopment has been evolutionary, in the truest sense of the word.

Multifamily Housing | Nov 29, 2017

First Porsche, now Aston Martin: Sports car maker co-develops Miami condo tower *UPDATED

The 391-unit Aston Martin Residences will feature seven penthouses and a duplex penthouse, all with private pools and terraces overlooking Biscayne Bay.

Industry Research | Nov 28, 2017

2018 outlook: Economists point to slowdown, AEC professionals say ‘no way’

Multifamily housing and senior living developments head the list of the hottest sectors heading into 2018, according a survey of 356 AEC professionals.

Multifamily Housing | Nov 28, 2017

Elementary school, daycare campus will serve Toronto’s skyrise neighborhood

The $65 million Canoe Landing Campus brings much needed social infrastructure to the 20,000 residents of Toronto’s CityPlace towers.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021