Rank | Company | 2013 Data Center Revenue |
1 | Holder Construction | $1,124,000,000 |
2 | Turner Construction | 512,000,000 |
3 | DPR Construction | 506,001,637 |
4 | Structure Tone | 400,450,000 |
5 | Mortenson Construction | 298,590,000 |
6 | Gilbane | 241,967,522 |
7 | Balfour Beatty US | 202,427,241 |
8 | Hensel Phelps | 177,120,000 |
9 | Hoffman Construction | 168,000,000 |
10 | HITT Contracting | 136,900,000 |
11 | Fortis Construction | 136,102,000 |
12 | Carlson Design Construct | 114,070,000 |
13 | Clune Construction | 101,583,530 |
14 | James G. Davis Construction | 98,601,699 |
15 | Skanska USA | 95,067,555 |
16 | Beck Group, The | 91,445,591 |
17 | JE Dunn Construction | 91,178,219 |
18 | Yates Companies, The | 30,000,000 |
19 | URS Corp. | 25,100,000 |
20 | McGough | 24,000,000 |
21 | Tutor Perini Corp. | 18,036,474 |
22 | BlueScope Construction | 17,849,218 |
23 | IMC Construction | 13,000,000 |
24 | Parsons Brinckerhoff | 12,185,435 |
25 | Brasfield & Gorrie | 11,948,769 |
26 | Flintco | 11,300,000 |
27 | Pepper Construction | 10,880,000 |
28 | Ryan Companies US | 9,802,824 |
29 | Hunt Construction Group | 8,000,000 |
30 | Hathaway Dinwiddie Construction | 6,000,000 |
31 | Hill International | 6,000,000 |
32 | Austin Commercial | 4,210,253 |
33 | Harkins Builders | 3,700,000 |
34 | Weitz Company, The | 2,566,066 |
35 | O'Neil Industries/W.E. O'Neil | 2,441,614 |
36 | JLL | 2,334,082 |
37 | Walsh Group, The | 2,242,483 |
38 | Layton Construction | 1,700,000 |
39 | Messer Construction | 1,433,071 |
40 | W. M. Jordan Company | 682,821 |
41 | Heery International | 589,726 |
42 | Wight & Company | 502,000 |
43 | STV | 217,000 |
44 | Sundt Construction | 69,754 |
45 | Allen & Shariff | 65,000 |
Read the Data Center Giants article
Read BD+C's full 2014 Giants 300 Report
Related Stories
Office Buildings | Jun 3, 2024
Insights for working well in a hybrid world
GBBN Principal and Interior Designer Beth Latto, NCIDQ, LEED AP, ID+C, WELL AP, share a few takeaways, insights, and lessons learned from a recent Post Occupancy Evaluation of the firm's Cincinnati, Ohio, office.
Multifamily Housing | Jun 3, 2024
Grassroots groups becoming a force in housing advocacy
A growing movement of grassroots organizing to support new housing construction is having an impact in city halls across the country. Fed up with high housing costs and the commonly hostile reception to new housing proposals, advocacy groups have sprung up in many communities to attend public meetings to speak in support of developments.
MFPRO+ News | Jun 3, 2024
New York’s office to residential conversion program draws interest from 64 owners
New York City’s Office Conversion Accelerator Program has been contacted by the owners of 64 commercial buildings interested in converting their properties to residential use.
MFPRO+ News | Jun 3, 2024
Seattle mayor wants to scale back energy code to spur more housing construction
Seattle’s mayor recently proposed that the city scale back a scheduled revamping of its building energy code to help boost housing production. The proposal would halt an update to the city’s multifamily and commercial building energy code that is scheduled to take effect later this year.
Mass Timber | May 31, 2024
Mass timber a big part of Western Washington University’s net-zero ambitions
Western Washington University, in Bellingham, Wash., 90 miles from Seattle, is in the process of expanding its ABET-accredited programs for electrical engineering, computer engineering and science, and energy science. As part of that process, the university is building Kaiser Borsari Hall, the 54,000-sf new home for those academic disciplines that will include teaching labs, research labs, classrooms, collaborative spaces, and administrative offices.
Construction Costs | May 31, 2024
Despite challenges, 2024 construction material prices continue to stabilize
Gordian’s Q2 2024 Quarterly Construction Cost Insights Report indicates that supply chain issues notwithstanding, many commodities are exhibiting price normalization.
University Buildings | May 30, 2024
Washington University School of Medicine opens one of the world’s largest neuroscience research buildings
In St. Louis’ Cortex Innovation District, Washington University School of Medicine recently opened its new Jeffrey T. Fort Neuroscience Research Building. Designed by CannonDesign and Perkins&Will, the 11-story, 609,000-sf facility is one of the largest neuroscience buildings in the world.
Architects | May 30, 2024
AE firm Goodwyn Mills Cawood merges with Southland Engineering
Architecture and engineering firm Goodwyn Mills Cawood (GMC) is further expanding its services through a strategic merger with engineering firm Southland Engineering in Cartersville, Ga.
K-12 Schools | May 30, 2024
Inclusive design strategies to transform learning spaces
Students with disabilities and those experiencing mental health and behavioral conditions represent a group of the most vulnerable students at risk for failing to connect educationally and socially. Educators and school districts are struggling to accommodate all of these nuanced and, at times, overlapping conditions.
MFPRO+ New Projects | May 29, 2024
Two San Francisco multifamily high rises install onsite water recycling systems
Two high-rise apartment buildings in San Francisco have installed onsite water recycling systems that will reuse a total of 3.9 million gallons of wastewater annually. The recycled water will be used for toilet flushing, cooling towers, and landscape irrigation to significantly reduce water usage in both buildings.