Too many construction projects don’t meet owners’ expectations: KPMG report

Contractors

Too many construction projects don’t meet owners’ expectations: KPMG report

Causes for delays, overruns, and underperformance include project management talent shortages, distrust between owners and contractors, and the lack of fully integrated project management systems. 


By John Caulfield, Senior Editor | April 20, 2015
Too many construction projects still don’t meet owners’ expectations: KPMG report

KPMG International's Global Construction Survery 2015 reported that 53% of owners say they suffered one or more underperforming projects in the previous year. Image: Wikimedia Commons

Despite their planning and risk management efforts, owners are still finding that a sizable percentage of their projects are either failing or aren’t coming in anywhere near on time or on budget.

More than half—53%—of owners say they suffered one or more underperforming projects in the previous year, a number that rises to 61% for larger organizations, according to KPMG International’s ninth annual Global Construction Survey 2015, based on interviews with 109 senior leaders from private and public organizations around the world that conduct construction activity.

Only 31% of respondents’ projects over the past three years came in within 10% of their budgeted cost. And only one quarter of projects over that period came in within 10% of their original deadlines.

The owners imply that these failures, delays, and overruns are less the result of poor project oversight than of talent shortages and the lack of integration of project management information systems into these companies’ accounting and procurement software programs.

 

 

Most owners polled assert that their companies use formal screening, prioritizing, and approval processes for projects, including financial and risk analysis (84%). More than 80% of respondents state that the majority of their capital projects are planned. Thirty percent of respondents use a design-bid-build project delivery strategy, while 32% use engineer-procure-construct.

“All potential projects should be systematically identified, classified, screened, prioritized, evaluated and selected,” writes Jeff Shaw, Director-KPMG in South Africa. “This process must be supported by an appropriate budget allocation and monitoring process. Throughout the capital allocation process, alignment between strategic objectives and the capital project portfolio must be tested.”

The report notes, however, that owners are challenged finding qualified project management personnel. Forty-five percent of respondents say they struggle to attract qualified craft labor, planners and project management professionals. 

While 64% of respondents believe their management controls are either “optimized” or “monitored,” nearly one-third concede that their controls are “standardized,” with no testing or reporting or reporting to management and only limited staff training.

Most construction companies rely heavily on software to manage projects. Fifty-five percent of respondents say they are “satisfied” or “mostly satisfied” about the return on investment from project management tools and training. And 73% say they are confident about the accuracy and timeliness of reports they receive from managers and contractors. 

However, only about half of respondents say their organizations have introduced an integrated project management information system (PMIS). Consequently, less than one-fifth of respondents could answer “yes” definitively when asked if investments in project governance and controls have reduced project costs. 

In planning for delays and cost overruns, senior executives polled identify a range of methods to calculate contingency levels. The two most popular are setting aside an specific amount of contingency for all projects (e.g., 10%), and quantitative risk analysis. “The relative sophistication of the latter suggests that owners are trying to become more accurate in their forecasting,” the report states.

Sixty-nine percent of owners polled say that “poor contractor performance” is one of the biggest reasons for failing projects, delays, or cost overruns. And there’s definitely something negative going when only one-third could say they have a “high” level of trust with pros. 

More than eight in 10 respondents expect greater collaboration with contractors over the next five years. How much these relationships actually change, though,  remains to be seen. The report suggests that lump-sum, fixed-price contracts, which dominate among the survey’s respondents, are one reason for the fragile state of owner-contractor relationships, primarily because they defer risk onto the contractor. And owners believe the balance of power is shifting toward them; nearly half expect to have more negotiating strength when delivering capital projects over the next five years.

KPMG International offers five steps for owners to improve the performance of their projects:

  • Take a fresh approach to talent management through more effective recruitment, development, and retention strategies;
  • Execute a fully integrated PMIS for swift coordination and real-time reporting;
  • Demand practical targets from contractors based on realistic expectations of what can go wrong;
  • Use contingency planning to control costs rather than excuse overruns; and
  • Invest in relationships with contractors by creating integrated project teams. 

Related Stories

Codes and Standards | Jul 31, 2018

Workers allegedly held in captivity by construction subcontractor in San Jose pay theft case

Contractor pays $250,000 in back wages in Dept. of Labor enforcement action.

Building Team | Jul 30, 2018

Construction tech is the new investment darling for VC funds

In the first half of 2018, venture capital firms invested $1.05 billion in global construction tech startups, setting a record high.

Modular Building | Jul 23, 2018

Offsite construction: Why it’s important for the survival of your firm

The industry is approaching its “heart attack moment,” with so many large projects that are chronically late, over budget, and unprofitable, writes FMI Capital Advisors’ Michael Swistun.

Building Owners | Jul 17, 2018

Are we facing a new era in Foreign Direct Investment?

The construction industry is already feeling the effects of the recent tariffs, not only with higher steel and aluminum prices, but with higher prices on Canadian lumber.

Office Buildings | Jul 17, 2018

Transwestern report: Office buildings near transit earn 65% higher lease rates

Analysis of 15 major metros shows the average rent in central business districts was $43.48/sf for transit-accessible buildings versus $26.01/sf for car-dependent buildings.

Giants 400 | Jul 16, 2018

5 'giant' trends poised to change the face of construction

We’ve identified five emerging trends that are likely to transform the construction market in the near future.

Adaptive Reuse | Jul 9, 2018

Work, park, live: Inside Cincinnati’s parking garage turned lifestyle hotel

The Summit hotel and conference center is a converted parking garage that was once a factory.

Accelerate Live! | Jun 24, 2018

Watch all 19 Accelerate Live! talks on demand

BD+C’s second annual Accelerate Live! AEC innovation conference (May 10, 2018, Chicago) featured talks on AI for construction scheduling, regenerative design, the micro-buildings movement, post-occupancy evaluation, predictive visual data analytics, digital fabrication, and more. Take in all 19 talks on demand.

Multifamily Housing | Jun 13, 2018

Multifamily visionaries: KTGY’s extraordinary expectations

KTGY Architecture + Planning keeps pushing the boundaries of multifamily housing design in the U.S., Asia, and the Middle East.

| Jun 11, 2018

Accelerate Live! talk: Regenerative design — When sustainability is not enough

In this 15-minute talk at BD+C’s Accelerate Live! conference (May 10, 2018, Chicago), HMC’s Eric Carbonnier poses the question: What if buildings could actually rejuvenate ecosystems?

boombox1
boombox2
native1

More In Category

Geothermal Technology

Rochester, Minn., plans extensive geothermal network

The city of Rochester, Minn., home of the famed Mayo Clinic, is going big on geothermal networks. The city is constructing Thermal Energy Networks (TENs) that consist of ambient pipe loops connecting multiple buildings and delivering thermal heating and cooling energy via water-source heat pumps.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021