Temporary fix to CityCenter's Harmon would cost $2 million, contractor says

Temporary fix to CityCenter's Harmon would cost $2 million, contractor says

By contrast, CityCenter half-owner and developer MGM Resorts International determined last year that the Harmon would collapse in a strong quake and can't be fixed in an economical way. It favors implosion at a cost of $30 million.


By By Tim O'Reiley, Las Vegas Review-Journal | March 16, 2012
The repair was not proposed as a permanent solution to the building's flaws, but
The repair was not proposed as a permanent solution to the building's flaws, but as a way to keep it stable through a larger tri

As the hearing over whether to raze the unfinished Harmon Hotel plodded through its third day, Perini Building Co. injected a surprise by unveiling a temporary $2 million fix to keep it standing in the event of a serious earthquake.

Perini, general contractor on the $8.5 billion CityCenter that includes the Harmon, has long insisted that it could and would fix any structural defects but previously had not laid out specifics.

Steve Schiller, president of the engineering firm John A. Martin & Associates of Nevada, outlined from the witness stand the $2 million patch that would take six-to-eight weeks to complete. The firm, hired by Perini for the case, essentially calls for constructing eight columns, bookended metal plates, from the base of the fourth floor to the subterranean foundation as a way to absorb any seismic shocks and transfer them harmlessly to the ground.

The repair was not proposed as a permanent solution to the building's flaws, but as a way to keep it stable through a larger trial over CityCenter's construction next year.

By contrast, CityCenter half-owner and developer MGM Resorts International determined last year that the Harmon would collapse in a strong quake and can't be fixed in an economical way. It favors implosion at a cost of $30 million.

Click here to read more. BD+C

Related Stories

| Sep 28, 2012

Seattle is home to first LEED-certified modular radiation center

By using modular construction and strategic site design, RAD Medical Systems built the first radiation center to receive LEED certification.

| Sep 26, 2012

EDITORIAL OPPORTUNITY – BD+C Greenbuild 2012 Issue

Your firm is invited to contribute to this special issue, which will be distributed at Greenbuild San Francisco, Nov. 14-16, 2012.

| Sep 24, 2012

Reed Construction completes Lafarge headquarters in Chicago

Reed Construction was contracted to complete the full third floor build-out which included the construction of new open area work space, private offices, four conference rooms with videoconferencing capabilities and an executive conference boardroom.

| Sep 24, 2012

Chicago Lakeside shortlisted for the Sustainia Award

The “Lakeside Idea” is about bridging a brownfield industrial past to a green lifestyle future, from steel mill to innovation mill.

| Sep 24, 2012

$3.8-million athletic field and track opens in Glen Head, N.Y.

The complex also includes a new, one-story, multi-purpose building that serves as the main entry port to the athletic facilities.

| Sep 21, 2012

AAMA and WDMA release updated review and forecast that predicts industry trends

Significant volume is expected to return to the entry and interior door market as new construction demand is expected to grow at double-digit rates, outpacing remodeling and replacement activity as the housing market recovers.

| Sep 20, 2012

Mid-box retail study shows lack of available sites in Chicago

Existing supply is tight everywhere and almost non-existent in the most attractive zones.

| Sep 20, 2012

Forrester begins construction of freestanding cancer center in Montgomery County, Md.

The new 51,000-square-foot building will include two linear accelerator vaults for radiation equipment.

| Sep 19, 2012

Modular, LEED-Gold Certified Dormitory Accommodates Appalachian State University Growth

By using modular construction, the university was able to open a dorm a full year earlier than a similar dorm built at the same time with traditional construction.

| Sep 19, 2012

ABI back into positive territory

South continues to lead regions in demand for design services.

boombox1
boombox2
native1

More In Category




Great Solutions

41 Great Solutions for architects, engineers, and contractors

AI ChatBots, ambient computing, floating MRIs, low-carbon cement, sunshine on demand, next-generation top-down construction. These and 35 other innovations make up our 2024 Great Solutions Report, which highlights fresh ideas and innovations from leading architecture, engineering, and construction firms.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021