Team Tames Impossible Site

Team Tames Impossible Site

“For the purpose of instructing persons, who may choose to apply themselves, in the application of science to the common purposes of life.” — Stephen Van Rensselaer, III, in a letter establishing Rensselaer Polytechnic Institute, in 1824


By By Jeff Yoders, Senior Associate Editor | August 11, 2010
This article first appeared in the 200908 issue of BD+C.
EMPAC is built into a hillside overlooking the Hudson Valley on the RPI campus. Grimshaw’s design was chosen partially because of how it took advantage of the site.

Rensselaer Polytechnic Institute, the nation's oldest technology university, has long prided itself on its state-of-the-art design and engineering curriculum. Several years ago, to call attention to its equally estimable media and performing arts programs, RPI commissioned British architect Sir Nicholas Grimshaw to design the Curtis R. Priem Experimental Media and Performing Arts Center (EMPAC).
 

As we recently noted (see “BIM + IPD: 3 Success Stories,” April;), Grimshaw's clever and dramatic “ship-in-a-bottle” structure has become the centerpiece of the Troy, N.Y. campus.

In judging the EMPAC project for the 2009 Building Team Awards, the judges were impressed with the way in which the Building Team addressed the site, a steep hillside overlooking the Hudson Valley. “One of the things that led to our decision to select Grimshaw was that they captured early on how to best take advantage of the site,” said Claude Rounds, the university's VP of administration. “They not only gave an architectural concept of how the structure would fit, but how it would actually complement and enhance the site.” From the early days of the project, RPI wanted a Building Team that would make the most effective use of the difficult site conditions. 
                                         

The walls of EMPAC’s two studios are composed of adjustable acoustic diffusion panels painted matte black to allow an acoustic con• guration for any performance. Studio 1 (above) is capable of audio presentation but is optimized for dance, visualization, multi-screen, and immersive performances. PHOTO: TURNER CONSTRUCTION CO

In 2004, RPI turned to the integrated project delivery team at the nation's largest construction firm, Turner Construction Co., to fulfill Grimshaw's vision. The project's original construction manager had parted ways with Rensselaer earlier that year due to constructability issues. Turner assembled a blue-ribbon team: Architectural Woodwork Industries, Philadelphia (custom woodwork), Supermetals Structures, Quebec (structural steel design), Radius Track of Minnesota (steel fabrication), Gartner (curtain wall), Davis Brody Bond (architect of record), Buro Happold (structural and mechanical engineering systems), GeoTech (site engineers), Fisher Dachs Associates (theater consultant), and Kirkegaard Associates (acoustician).

“We only asked for proposals from people who would come to it in a collaborative fashion,” said Stephen Coates, project manager for Turner. Language was written into the IPD contract documents to make it clear that all participants were responsible for participating in an iterative design process, according to Coates. RPI also demanded the highest standards of performance and acoustics in the statement of program and design intent.

An intense, four-month design process followed the selection of the Building Team members. At Grimshaw's suggestion everyone used Rhinoceros, a 3D design application that allowed the team to model and test the curved surfaces of EMPAC. The team was literally passing new models back and forth to each other on a daily basis. Grimshaw's computational design director, Shane Burger, said using Rhino as a common design tool helped achieve not only a common aesthetic goal, but also a common technical and construction goal.
                                                

Because of the difficult site, EMPAC was built into the hillside site in staggered steps. The performance spaces were acoustically isolated on one side of the building with lobbies and offices on the other side. PHOTO: TURNER CONSTRUCTION CO.

The initial design went through three major conceptual changes during this process. In the end, the team found a way to deliver four primary performance spaces and all the office space that the university needed, each in an isolated portion of the building, while still staying honest to Grimshaw's aesthetic vision.

Instead of fighting against the site, the final design took advantage of it, maximizing views for patrons with glass curtain wall on all sides. By building the structure into the hill, the design used all the space available to create an unmistakable focus for the RPI campus.

The collaboration continued into the construction process. Gartner supervised installation of EMPAC's north curtain wall and created a rules system in the model for installation of the custom panels in the performance spaces; this consisted of a collection of custom panels of varying depth. For audience comfort, each seat in the theater has an air supply below it. Buro Happold created a computational fluid dynamics analysis for each seating design change.
                                             

Major structural elements of EMPAC include lagged shoring walls, caissons, mini-piles, pile caps and grade beams, a concrete superstructure (top), steel framing, and composite decks. Turner Construction Company delivered the complex design on time and on budget.

Every interior space is connected through fiber-optic cables to a supercomputer on campus—at RPI, computing is intrinsically related to delivering the performing arts. “The space had to be tunable, just as you'd tune an instrument,” said Burger.

Theater consultant Fisher Dachs Associates and acoustician Kirkegaard Associates worked closely with the design team to deliver EMPAC's dramatic 1,200-seat theater space. The ceiling consists of panels of Nomex-brand heat- and fire-resistant fabric, each less than one millimeter thick, supported on a web of stainless-steel cables.

Nomex was selected for its ability to gently reflect high-frequency sound while remaining transparent to mid- and low-frequency sound. This combination of attributes provides acoustic support to the musicians on the platform while allowing the volume above the ceiling to contribute to the reverberance expected of a first-rate orchestral hall.

The fabric ceiling, like the walls, is gently convex in shape and masks the electrical and mechanical equipment and light fixtures situated above. An aural study of the acoustic design was done before construction to verify its feasibility. “It was the intense focus on creating a world-class venue for acoustics that we felt set [the project] apart,” said Grimshaw supervising partner Mark Husser.

In bestowing its only Platinum Award this year on EMPAC, BD+C's Building Team Awards jury praised both its design and construction excellence. “The acoustical features are incorporated into the design instead of being tacked on during construction,” said Tracy Nicholas, VP, Alter Construction Management, Skokie, Ill. “They used BIM and fully integrated project delivery to the fullest extent to deliver a great project.”

“The project had to do something beyond ordinary, and this does it,” said Carol Ross Barney, FAIA, of Chicago's Ross Barney + Jankowski, designer of the Oklahoma City Federal Building and many university projects. “It's an example of aesthetics and technology done together very well. It makes me think about acoustics in a whole new way.”

Related Stories

| Aug 11, 2010

Firehouse converted to hip hot property

Sound the alarm! A 9,000-sf former firehouse is being converted into a new multipurpose space for ZUMIX, a nonprofit music and arts organization that's partnering on the project with Landmark Structures of Woburn, Mass., and the East Boston Community Development Corporation. The $2 million renovation of the 1920s structure, known as Engine Company 40 Firehouse, includes a complete gut job to ma...

| Aug 11, 2010

And the world's tallest building is…

At more than 2,600 feet high, the Burj Dubai (right) can still lay claim to the title of world's tallest building—although like all other super-tall buildings, its exact height will have to be recalculated now that the Council on Tall Buildings and Urban Habitat (CTBUH) announced a change to its height criteria.

| Aug 11, 2010

Project is music to school's ears

Florida Gulf Coast University is building a $7.55 million Fine Arts Building on its campus near Ft. Myers, Fla. The 25,000-sf building—the first project in the school's plan for an entire music complex—will house the music program of the College of Arts and Sciences. The facility includes a 200-seat recital hall, rehearsal hall, music labs, studio rooms, and administration offices.

| Aug 11, 2010

Theater offers spectacular views inside and out

A 500-seat proscenium theater sits at the heart of the 35,000-sf Performing Arts Pavilion at the Jackson Hole Center for the Arts. The entertainment and cultural facility, designed by Stephen Dynia Architects, Jackson Hole, Wyo., also houses glass-walled rehearsal rooms that offer passersby views of the activity going on inside and multifunction lobby with views of Snow King Mountain.

| Aug 11, 2010

Design for Miami Art Museum triples gallery space

Herzog & de Meuron has completed design development for the Miami Art Museum’s new complex, which will anchor the city’s 29-acre Museum Park, overlooking Biscayne Bay. At 120,000 sf with 32,000 sf of gallery space, the three-story museum will be three times larger than the current facility.

| Aug 11, 2010

Community college’s hillside learning center

The Earl E. and Dorothy J. Dellinger Learning Resource Center at Southwest Virginia Community College in Richlands, Va., is the centerpiece of this mountainside school. Designed by Arlington, Va.-based The Lukmire Partnership, the 50,000-sf, two-story building connects the upper and lower campuses, which are separated by a 70-foot vertical grade change.

| Aug 11, 2010

Thom Mayne unveils ‘floating cube’ design for the Perot Museum of Nature and Science

Calling it a “living educational tool featuring architecture inspired by nature and science,” Pritzker Prize Laureate Thom Mayne unveiled the schematic designs and building model for the Perot Museum of Nature & Science at Victory Park in Dallas. The $185 million, 180,000-sf structure is 170 feet tall—equivalent to approximately 14 stories—and is conceived as a large...

| Aug 11, 2010

BIG beats out Foster and Hadid in design competition for Kazakhstan's National Library

Invited as one of five pre-selected architect-led teams that included Lord Norman Foster and Zaha Hadid, Copenhagen-based BIG was awarded first prize in an international design competition for the new National Library in Astana, Kazakhstan. The 33,000-square-meter facility will be organized as a “circular loop of knowledge” that allows for clear, intuitive orientation of the vast co...

| Aug 11, 2010

Broadway-style theater headed to Kentucky

One of Kentucky's largest performing arts venues should open in 2011—that's when construction is expected to wrap up on Eastern Kentucky University's Business & Technology Center for Performing Arts. The 93,000-sf Broadway-caliber theater will seat 2,000 audience members and have a 60×24-foot stage proscenium and a fly loft.

| Aug 11, 2010

Dallas Center for the Performing Arts opens

The Dallas Center for the Performing Arts, a new multi-venue center for music, opera, theater, and dance, will open this month, completing the 25-year vision of the Dallas Arts District. Foster + Partners, Rem Koolhaas, Joshua Prince-Ramus, and Skidmore Owings & Merrill are among the architecture firms involved in the development, which includes four venues unified by a 10-acre park.

boombox1
boombox2
native1

More In Category


Adaptive Reuse

Detroit’s Michigan Central Station, centerpiece of innovation hub, opens

The recently opened Michigan Central Station in Detroit is the centerpiece of a 30-acre technology and cultural hub that will include development of urban transportation solutions. The six-year adaptive reuse project of the 640,000 sf historic station, created by the same architect as New York’s Grand Central Station, is the latest sign of a reinvigorating Detroit.


Museums

Connecticut’s Bruce Museum more than doubles its size with a 42,000-sf, three-floor addition

In Greenwich, Conn., the Bruce Museum, a multidisciplinary institution highlighting art, science, and history, has undergone a campus revitalization and expansion that more than doubles the museum’s size. Designed by EskewDumezRipple and built by Turner Construction, the project includes a 42,000-sf, three-floor addition as well as a comprehensive renovation of the 32,500-sf museum, which was originally built as a private home in the mid-19th century and expanded in the early 1990s. 


halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021