Sutter Health’s new surgical care center finishes three months early, $3 million under budget

Healthcare Facilities

Sutter Health’s new surgical care center finishes three months early, $3 million under budget

Robotics and Takt Planning credited for boosting efficient performance


By Peter Fabris, Contributing Editor | August 21, 2023
Sutter Health’s new Samaritan Court Ambulatory Care and Surgery Center finishes three months early, $3 million under budget
Pictured: A mock surgery room at Sutter Health’s new Samaritan Court Ambulatory Care and Surgery Center. Photo courtesy Sutter Health

Sutter Health’s Samaritan Court Ambulatory Care and Surgery Center (Samaritan Court), a three-story, 69,000 sf medical office building, was recently completed three months early and $3 million under budget, according to general contractor Skanska

The project “marks the first time a general contractor has collaborated seamlessly with all trade partners (mechanical, electrical, plumbing, framing, and drywall) on layout strategy and responsibilities simultaneously,” Skanska says.

The accomplishment was aided by Dusty Robotics, a robot tool that its manufacturer says, “allows project teams to dramatically reduce schedule time and rework costs through accurate, full-scale floor layout.” Skanska worked with trade partners specializing in mechanical, electrical, plumbing, framing and drywall, to develop a combined layout plan in a “first-of-its-kind collaboration and implementation of Dusty Robotics.”

Sutter Health’s new Samaritan Court Ambulatory Care and Surgery Center finishes three months early, $3 million under budget
Photo courtesy Sutter Health

The project team also used a virtual punch list and Takt Planning, starting punch list activities during the design and preconstruction phases rather than in the closeout phase. The team focused on where improvements could be made to cut rework in half in comparison to projects of similar size and complexity. 

The virtual punch list allowed each stakeholder to review final conditions—furniture, casework and equipment placement, ADA clearances, device and outlet alignment, utility connections, and item placements that would require unique finish details—in the building model. This allowed the team to achieve its goal of cutting rework by 50% on the project.  

The design team strove for a warm, timeless, easy-to-maintain, and inviting space by incorporating warm woods, recessed modern lighting, natural stone, and visually stimulating wayfinding graphics. Wayfinding throughout the building used imagery of local flora and fauna elemental themes assigned to each floor, such as water, pebbles, and trees. Natural element-themed graphics were assigned to each medical practice to create an intuitive orientation in the building.    

Located near the border of San Jose and Los Gatos, Calif., the building aims for patient-centered care. Design highlights include:

  • Single entry/exit for patients, promoting clear wayfinding 
  • Centralized reception areas for upper floors at patient entry points 
  • Centralized waiting spaces on upper floors to allow a variety of clinical services to share seating and maximize efficiency for staff movement
  • Localized departments to achieve the greatest operational efficiency for the best patient care with ease of access to core modalities including Diagnostic Imaging and Laboratory Services 
  • Departmental adjacencies to share point-of-care rooms and support spaces between clinic modules and services
  • Locating of the surgery center on the first floor for ease of patient access and discharge 
  • Orientation of patient care and recovery rooms toward pleasant views of the natural environment to encourage patient recovery

On the project team:  
Owner and/or developer: Sutter Health 
Design architect: Boulder Associates 
Architect of record: Boulder Associates 
MEP engineer: Southland Industries (mechanical, plumbing); Prime Electric (electric);  
Structural engineer: Miyamoto 
General contractor/construction manager: Skanska

Sutter Health’s new Samaritan Court Ambulatory Care and Surgery Center finishes three months early, $3 million under budget
Photo courtesy Sutter Health
Sutter Health’s new Samaritan Court Ambulatory Care and Surgery Center finishes three months early, $3 million under budget
Photo courtesy Sutter Health

 

Related Stories

| Sep 24, 2013

8 grand green roofs (and walls)

A dramatic interior green wall at Drexel University and a massive, 4.4-acre vegetated roof at the Kauffman Performing Arts Center in Kansas City are among the projects honored in the 2013 Green Roof and Wall Awards of Excellence. 

Sponsored | | Sep 23, 2013

Nichiha USA panels provide cost savings for community project

When tasked with the design and development of a newly constructed Gateway Rehabilitation Center, architects at Rothschild Doyno Collaborative first designed the new center to include metal panels. When the numbers came back, they were challenged with finding a product that would help cut costs and keep them within the construction budget. Nichiha’s fiber cement panels come in a half or less of the metal panel cost.

Sponsored | | Sep 23, 2013

HKS leverages Revu and Bluebeam Studio for IPD on the Banner Health MD Anderson Health Center project

Read how HKS is working collaboratively with all project partners and streamlining information flow using Bluebeam Revu and Bluebeam Studio to digitize communication and deliver the facility using IPD.

| Sep 19, 2013

What we can learn from the world’s greenest buildings

Renowned green building author, Jerry Yudelson, offers five valuable lessons for designers, contractors, and building owners, based on a study of 55 high-performance projects from around the world.

| Sep 19, 2013

6 emerging energy-management glazing technologies

Phase-change materials, electrochromic glass, and building-integrated PVs are among the breakthrough glazing technologies that are taking energy performance to a new level. 

| Sep 19, 2013

Roof renovation tips: Making the choice between overlayment and tear-off

When embarking upon a roofing renovation project, one of the first decisions for the Building Team is whether to tear off and replace the existing roof or to overlay the new roof right on top of the old one. Roofing experts offer guidance on making this assessment.

| Sep 17, 2013

Healthcare project will merge outpatient clinic with YMCA to promote wellness and prevention

Penrose-St. Francis Health Services and the YMCA of the Pikes Peak Region announce collaboration, along with developer The Boldt Company, to create next-generation wellness facility.  

| Sep 16, 2013

Study analyzes effectiveness of reflective ceilings

Engineers at Brinjac quantify the illuminance and energy consumption levels achieved by increasing the ceiling’s light reflectance.

| Sep 11, 2013

BUILDINGChicago eShow Daily – Day 3 coverage

Day 3 coverage of the BUILDINGChicago/Greening the Heartland conference and expo, taking place this week at the Holiday Inn Chicago Mart Plaza.

| Sep 10, 2013

The new medical office building: 7 things to know about today’s outpatient clinic

Regulatory pressures, economic constraints, and emerging technologies are transforming healthcare. Learn how Building Teams are responding with efficient, appealing, boundary-blurring outpatient buildings. 

boombox1
boombox2
native1

More In Category

Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.




Mass Timber

British Columbia hospital features mass timber community hall

The Cowichan District Hospital Replacement Project in Duncan, British Columbia, features an expansive community hall featuring mass timber construction. The hall, designed to promote social interaction and connection to give patients, families, and staff a warm and welcoming environment, connects a Diagnostic and Treatment (“D&T”) Block and Inpatient Tower.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021