Sutter Health’s new surgical care center finishes three months early, $3 million under budget

Healthcare Facilities

Sutter Health’s new surgical care center finishes three months early, $3 million under budget

Robotics and Takt Planning credited for boosting efficient performance


By Peter Fabris, Contributing Editor | August 21, 2023
Sutter Health’s new Samaritan Court Ambulatory Care and Surgery Center finishes three months early, $3 million under budget
Pictured: A mock surgery room at Sutter Health’s new Samaritan Court Ambulatory Care and Surgery Center. Photo courtesy Sutter Health

Sutter Health’s Samaritan Court Ambulatory Care and Surgery Center (Samaritan Court), a three-story, 69,000 sf medical office building, was recently completed three months early and $3 million under budget, according to general contractor Skanska

The project “marks the first time a general contractor has collaborated seamlessly with all trade partners (mechanical, electrical, plumbing, framing, and drywall) on layout strategy and responsibilities simultaneously,” Skanska says.

The accomplishment was aided by Dusty Robotics, a robot tool that its manufacturer says, “allows project teams to dramatically reduce schedule time and rework costs through accurate, full-scale floor layout.” Skanska worked with trade partners specializing in mechanical, electrical, plumbing, framing and drywall, to develop a combined layout plan in a “first-of-its-kind collaboration and implementation of Dusty Robotics.”

Sutter Health’s new Samaritan Court Ambulatory Care and Surgery Center finishes three months early, $3 million under budget
Photo courtesy Sutter Health

The project team also used a virtual punch list and Takt Planning, starting punch list activities during the design and preconstruction phases rather than in the closeout phase. The team focused on where improvements could be made to cut rework in half in comparison to projects of similar size and complexity. 

The virtual punch list allowed each stakeholder to review final conditions—furniture, casework and equipment placement, ADA clearances, device and outlet alignment, utility connections, and item placements that would require unique finish details—in the building model. This allowed the team to achieve its goal of cutting rework by 50% on the project.  

The design team strove for a warm, timeless, easy-to-maintain, and inviting space by incorporating warm woods, recessed modern lighting, natural stone, and visually stimulating wayfinding graphics. Wayfinding throughout the building used imagery of local flora and fauna elemental themes assigned to each floor, such as water, pebbles, and trees. Natural element-themed graphics were assigned to each medical practice to create an intuitive orientation in the building.    

Located near the border of San Jose and Los Gatos, Calif., the building aims for patient-centered care. Design highlights include:

  • Single entry/exit for patients, promoting clear wayfinding 
  • Centralized reception areas for upper floors at patient entry points 
  • Centralized waiting spaces on upper floors to allow a variety of clinical services to share seating and maximize efficiency for staff movement
  • Localized departments to achieve the greatest operational efficiency for the best patient care with ease of access to core modalities including Diagnostic Imaging and Laboratory Services 
  • Departmental adjacencies to share point-of-care rooms and support spaces between clinic modules and services
  • Locating of the surgery center on the first floor for ease of patient access and discharge 
  • Orientation of patient care and recovery rooms toward pleasant views of the natural environment to encourage patient recovery

On the project team:  
Owner and/or developer: Sutter Health 
Design architect: Boulder Associates 
Architect of record: Boulder Associates 
MEP engineer: Southland Industries (mechanical, plumbing); Prime Electric (electric);  
Structural engineer: Miyamoto 
General contractor/construction manager: Skanska

Sutter Health’s new Samaritan Court Ambulatory Care and Surgery Center finishes three months early, $3 million under budget
Photo courtesy Sutter Health
Sutter Health’s new Samaritan Court Ambulatory Care and Surgery Center finishes three months early, $3 million under budget
Photo courtesy Sutter Health

 

Related Stories

Healthcare Facilities | Mar 18, 2015

Healthcare design partnership asks: What about the doctor?

HDR's Abbie Clary discusses the design of healthcare facilities and how they affect doctors.

Healthcare Facilities | Mar 16, 2015

Healthcare planning in a post-ACA world: 3 strategies for success

Healthcare providers are seeking direction on how to plan for a value-based world while still very much operating in a volume-based market. CBRE Healthcare's Curtis Skolnick offers helpful strategies. 

Retail Centers | Mar 10, 2015

Retrofit projects give dying malls new purpose

Approximately one-third of the country’s 1,200 enclosed malls are dead or dying. The good news is that a sizable portion of that building stock is being repurposed.

Codes and Standards | Mar 5, 2015

Charlotte, N.C., considers rule for gender-neutral public bathrooms

A few other cities, including Philadelphia, Austin, Texas, and Washington D.C., already have gender-neutral bathroom regulations.

Healthcare Facilities | Mar 1, 2015

Are you ready for high-rise hospitals?

The vertical hospital environment may be the wave of the future, but it is not without its design challenges.

Healthcare Facilities | Feb 26, 2015

Florida lifts 14-year ban on nursing home construction

Some $430 million of new space for senior care in Florida has been approved after the state ended a 14-year ban on nursing home construction.

Healthcare Facilities | Feb 17, 2015

10 healthcare trends worth sharing

The rise of the medical home model of care and ongoing Lean value stream improvement are among the top healthcare industry trends.

Healthcare Facilities | Feb 11, 2015

Primer: Using 'parallel estimating' to pinpoint costs on healthcare construction projects

As pressure increases to understand capital cost prior to the first spade touching dirt, more healthcare owners are turning to advanced estimating processes, like parallel estimating, to improve understanding of exposure, writes CBRE Healthcare's Andrew Sumner.

Cultural Facilities | Feb 5, 2015

5 developments selected as 'best in urban placemaking'

Falls Park on the Reedy in Greenville, S.C., and the Grand Rapids (Mich.) Downtown Market are among the finalists for the 2015 Rudy Bruner Award for Urban Excellence.

Healthcare Facilities | Feb 1, 2015

7 new factors shaping hospital emergency departments

A new generation of highly efficient emergency care facilities is upping the ante on patient care and convenience while helping to reposition hospital systems within their local markets.

boombox1
boombox2
native1

More In Category

Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.




Mass Timber

British Columbia hospital features mass timber community hall

The Cowichan District Hospital Replacement Project in Duncan, British Columbia, features an expansive community hall featuring mass timber construction. The hall, designed to promote social interaction and connection to give patients, families, and staff a warm and welcoming environment, connects a Diagnostic and Treatment (“D&T”) Block and Inpatient Tower.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021