flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

Supply chain constraints, shifting consumer demands adding cost pressures to office fit-outs

Codes and Standards

Supply chain constraints, shifting consumer demands adding cost pressures to office fit-outs

Contractors expect continuing increases in material lead time, project timelines this year.
 


By Peter Fabris, Contributing Editor | April 25, 2022
Office fit out
Courtesy Pexels.

Cushman & Wakefield’s 2022 Americas Office Fit-Out Cost Guide found supply chain constraints and shifting consumer demands will continue to add pressure to costs, both in materials and labor.
 
Increases in construction and customer demand for durable and non-durable goods have driven supply chain disruptions over the past two years. COVID-19 outbreaks and labor shortages have also wreaked havoc through ports and on trucking, transportation, and distribution capacities. The supply chain stress indices for both China and the U.S. ended 2021 up over 40% from pre-pandemic levels.
 
For office construction and fit-outs, these stressors have created increased delays, greater uncertainty, and higher costs. There appears to be some light at the end of the tunnel, though,
as the supplier delivery index that measures manufacturer delays has been receding
since the middle of 2021, the report says.
 
The waning of the pandemic may add more fuel to cost pressures, however, as office tenants are targeting the first half of 2022 for employees to return to a more standard office attendance model. “As office space usage increases, we expect organizations will expand their piloting and testing of different types of layouts related to hybrid work,” the report says. “This is likely to increase the amount of fit-out and office space construction activity in the coming quarters, creating even more demand for materials and labor.”

Related Stories

Codes and Standards | Mar 2, 2021

New Seattle building code eliminates fossil fuels for most space and water heating

Also increases on-site solar photovoltaics, reduces envelope heat loss, air leakage, and interior lighting power allowances.

Codes and Standards | Feb 25, 2021

It’s not just lumber—roofing material prices are also on the rise

Lower demand for petroleum products means less asphalt production.

Codes and Standards | Feb 23, 2021

ASHRAE Epidemic Task Force releases updated Building Readiness Guide

Includes flush calculations to reduce time and energy to clear contaminants between occupancy periods.

Codes and Standards | Feb 22, 2021

Preservation of Affordable Housing develops climate resilience strategy

Includes backup power for resident and staff “area of refuge”.

Codes and Standards | Feb 18, 2021

Construction industry moves toward comprehensive U.S. BIM standard

NIBS hosts roundtable to create coordinated program to advance collaboration.

Codes and Standards | Feb 17, 2021

Construction on international sports venues is ripe for corruption

Poor planning, complex contracting, a lack of accountability and high levels of collusion to blame.

Codes and Standards | Feb 16, 2021

Feds may fund removal of some urban highways

Senate bill proposes pilot program to reknit communities.

Codes and Standards | Feb 16, 2021

Bechtel joins international heat resilience organization

Experience designing resilience standards to aid effort to protect communities from extreme heat.

Codes and Standards | Feb 10, 2021

More than two-thirds of construction companies say COVID-19 has not impacted their ESOP

Half of survey respondents say 2020 project profitability decreased due to pandemic.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021