Supply chain constraints, shifting consumer demands adding cost pressures to office fit-outs

Codes and Standards

Supply chain constraints, shifting consumer demands adding cost pressures to office fit-outs

Contractors expect continuing increases in material lead time, project timelines this year.
 


By Peter Fabris, Contributing Editor | April 25, 2022
Office fit out
Courtesy Pexels.

Cushman & Wakefield’s 2022 Americas Office Fit-Out Cost Guide found supply chain constraints and shifting consumer demands will continue to add pressure to costs, both in materials and labor.
 
Increases in construction and customer demand for durable and non-durable goods have driven supply chain disruptions over the past two years. COVID-19 outbreaks and labor shortages have also wreaked havoc through ports and on trucking, transportation, and distribution capacities. The supply chain stress indices for both China and the U.S. ended 2021 up over 40% from pre-pandemic levels.
 
For office construction and fit-outs, these stressors have created increased delays, greater uncertainty, and higher costs. There appears to be some light at the end of the tunnel, though,
as the supplier delivery index that measures manufacturer delays has been receding
since the middle of 2021, the report says.
 
The waning of the pandemic may add more fuel to cost pressures, however, as office tenants are targeting the first half of 2022 for employees to return to a more standard office attendance model. “As office space usage increases, we expect organizations will expand their piloting and testing of different types of layouts related to hybrid work,” the report says. “This is likely to increase the amount of fit-out and office space construction activity in the coming quarters, creating even more demand for materials and labor.”

Related Stories

Codes and Standards | Jun 1, 2021

Passive House standards proving their worth in multifamily sector

Energy performance beats conventionally built by 32% to 58%.

Codes and Standards | May 27, 2021

Pittsburgh combats construction fraud

Crackdown on tax, insurance, and workers’ comp malfeasance.

Codes and Standards | May 26, 2021

Proposal to add photovoltaic panels to the R2 Standard for electronics recycling

Hundreds of facilities in 33 countries could begin recycling PVs.

Codes and Standards | May 25, 2021

International Energy Agency lays out roadmap to net zero

Focus is on energy generation, but building efficiency also plays a role.

Codes and Standards | May 24, 2021

Biden Administration will make new investments in building energy efficiency

Focus on grid-interactive buildings; Energy Star expansion; new targets for energy, water reduction.

Codes and Standards | May 20, 2021

Solar panel trade group issues guidelines to rid use of components built with forced labor

Growing concern that PV industry is dependent on work camps in China.

Codes and Standards | May 19, 2021

Smart electric panels can aid transition to renewable energy

Allow customers better control of circuits; utilities can better manage demand.

Codes and Standards | May 18, 2021

Cross-laminated timber performs better than expected in shear test

Tests conducted in support of new criteria for design of CLT diaphragm.

Codes and Standards | May 13, 2021

LEED-certified federal buildings don’t use less energy than average

May be due to trade-offs on how score is developed.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021