Supply chain constraints, shifting consumer demands adding cost pressures to office fit-outs

Codes and Standards

Supply chain constraints, shifting consumer demands adding cost pressures to office fit-outs

Contractors expect continuing increases in material lead time, project timelines this year.
 


By Peter Fabris, Contributing Editor | April 25, 2022
Office fit out
Courtesy Pexels.

Cushman & Wakefield’s 2022 Americas Office Fit-Out Cost Guide found supply chain constraints and shifting consumer demands will continue to add pressure to costs, both in materials and labor.
 
Increases in construction and customer demand for durable and non-durable goods have driven supply chain disruptions over the past two years. COVID-19 outbreaks and labor shortages have also wreaked havoc through ports and on trucking, transportation, and distribution capacities. The supply chain stress indices for both China and the U.S. ended 2021 up over 40% from pre-pandemic levels.
 
For office construction and fit-outs, these stressors have created increased delays, greater uncertainty, and higher costs. There appears to be some light at the end of the tunnel, though,
as the supplier delivery index that measures manufacturer delays has been receding
since the middle of 2021, the report says.
 
The waning of the pandemic may add more fuel to cost pressures, however, as office tenants are targeting the first half of 2022 for employees to return to a more standard office attendance model. “As office space usage increases, we expect organizations will expand their piloting and testing of different types of layouts related to hybrid work,” the report says. “This is likely to increase the amount of fit-out and office space construction activity in the coming quarters, creating even more demand for materials and labor.”

Related Stories

| Mar 15, 2012

New Florida building code establishes flood and storm surge provisions

The new 2010 code establishes minimum design and construction requirements to protect buildings from wind, rain, floods, and storm surges.

| Mar 15, 2012

Illinois city rejects international code due to home sprinkler requirement

Macomb, Illinois aldermen voted to recommend that the city not adopt 2012 international building and residential code standards requiring the installation of overhead sprinkler systems in newly constructed one-family and two-family homes.

| Mar 15, 2012

Tenant advocates propose licensing landlords in New York City

With thousands of New York City rental units posing potential dangers to tenants, city advocates are proposing measures to make landlords improve building safety.

| Mar 15, 2012

Construction industry a big winner in federal small disadvantaged business procurement

Last year, only 5% of federal contract dollars went to small disadvantaged businesses. Construction and facilities support firms were the biggest beneficiaries.

| Mar 15, 2012

ANSI approves new fall protection standards

The American National Standards Institute (ANSI) has approved two American Society of Safety Engineers' (ASSE) standards addressing fall protection.

| Mar 8, 2012

Engineering innovation provides new option for meeting seismic codes in skyscrapers

Two University of Toronto engineers have developed “viscoelastic-energy-dissipating dampers” to replace many of the heavy concrete beams used in tall structures.

| Mar 8, 2012

CSI webinar on building code compliance March 22

A March 22 webinar will provide an overview of a 28-step process during the design of a building to ensure compliance with building codes.

| Mar 8, 2012

Federal silica dust rule caught in bureaucratic limbo

A federal rule meant to protect the lungs of workers has been caught in bureaucratic purgatory for more than a year.

| Mar 8, 2012

New LEED-EBOM rating has requirements for specific project types

Several key changes are proposed for the LEED-EBOM Rating System in 2012.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021