Supply chain constraints, shifting consumer demands adding cost pressures to office fit-outs

Codes and Standards

Supply chain constraints, shifting consumer demands adding cost pressures to office fit-outs

Contractors expect continuing increases in material lead time, project timelines this year.
 


By Peter Fabris, Contributing Editor | April 25, 2022
Office fit out
Courtesy Pexels.

Cushman & Wakefield’s 2022 Americas Office Fit-Out Cost Guide found supply chain constraints and shifting consumer demands will continue to add pressure to costs, both in materials and labor.
 
Increases in construction and customer demand for durable and non-durable goods have driven supply chain disruptions over the past two years. COVID-19 outbreaks and labor shortages have also wreaked havoc through ports and on trucking, transportation, and distribution capacities. The supply chain stress indices for both China and the U.S. ended 2021 up over 40% from pre-pandemic levels.
 
For office construction and fit-outs, these stressors have created increased delays, greater uncertainty, and higher costs. There appears to be some light at the end of the tunnel, though,
as the supplier delivery index that measures manufacturer delays has been receding
since the middle of 2021, the report says.
 
The waning of the pandemic may add more fuel to cost pressures, however, as office tenants are targeting the first half of 2022 for employees to return to a more standard office attendance model. “As office space usage increases, we expect organizations will expand their piloting and testing of different types of layouts related to hybrid work,” the report says. “This is likely to increase the amount of fit-out and office space construction activity in the coming quarters, creating even more demand for materials and labor.”

Related Stories

Codes and Standards | Sep 15, 2016

OSHA appoints new director for its construction directorate

The forty-year industry veteran has been a GC and business owner.

Energy | Sep 13, 2016

Oberlin College to hold conference on post-fossil fuel economy

The gathering will address climate change and new sources of energy.

Industry Research | Sep 12, 2016

Evidence linking classroom design to improved learning mounts

A study finds the impact can be as much as 25% per year.

Legislation | Sep 8, 2016

Half of U.S. states now allow design-build on public projects

Missouri is the latest to enact design-build legislation.

Codes and Standards | Sep 8, 2016

Vapor intrusion risk addressed in new ASTM guide update

The updates address industry confusion over how to handle the issue.

BIM and Information Technology | Sep 7, 2016

Energy Star Portfolio Manager tool updated to factor in waste management

The costs and benefits of managing 29 types of waste are now included.

Wood | Sep 6, 2016

Atlanta suburb prohibits wood-framed construction for high rises

The new building code prevents any structure with more than three stories from being built from a CLT frame.

Codes and Standards | Sep 1, 2016

Overuse of air conditioning hurts office productivity

A study found temperatures in the low 70s reduce worker performance.

Regulations | Aug 31, 2016

FEMA wants to toughen flood regulation on projects using federal funds

The proposal ‘would essentially rewrite the current 100-year flood standard.’

Sustainability | Aug 30, 2016

New federal project plans must include climate impacts

Agencies must quantify the specific impacts when possible.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021