Supply chain constraints, shifting consumer demands adding cost pressures to office fit-outs

Codes and Standards

Supply chain constraints, shifting consumer demands adding cost pressures to office fit-outs

Contractors expect continuing increases in material lead time, project timelines this year.
 


By Peter Fabris, Contributing Editor | April 25, 2022
Office fit out
Courtesy Pexels.

Cushman & Wakefield’s 2022 Americas Office Fit-Out Cost Guide found supply chain constraints and shifting consumer demands will continue to add pressure to costs, both in materials and labor.
 
Increases in construction and customer demand for durable and non-durable goods have driven supply chain disruptions over the past two years. COVID-19 outbreaks and labor shortages have also wreaked havoc through ports and on trucking, transportation, and distribution capacities. The supply chain stress indices for both China and the U.S. ended 2021 up over 40% from pre-pandemic levels.
 
For office construction and fit-outs, these stressors have created increased delays, greater uncertainty, and higher costs. There appears to be some light at the end of the tunnel, though,
as the supplier delivery index that measures manufacturer delays has been receding
since the middle of 2021, the report says.
 
The waning of the pandemic may add more fuel to cost pressures, however, as office tenants are targeting the first half of 2022 for employees to return to a more standard office attendance model. “As office space usage increases, we expect organizations will expand their piloting and testing of different types of layouts related to hybrid work,” the report says. “This is likely to increase the amount of fit-out and office space construction activity in the coming quarters, creating even more demand for materials and labor.”

Related Stories

Codes and Standards | Nov 29, 2018

USGBC and BRE form partnership

Two green standards groups will collaborate on standards, platforms, and research.

Codes and Standards | Nov 29, 2018

Parking garages in N.Y. State will have to be inspected every three years

Professional engineer must assess conditions.

Codes and Standards | Nov 28, 2018

To build water-efficient cities, water managers and urban planners must coordinate better

Lack of time and resources, and practitioners not in habit of working together hamper efforts.

Codes and Standards | Nov 26, 2018

All LEED-certified buildings eligible for LEED recertification

Projects must submit 12 months of data demonstrating continued or improved performance.

Codes and Standards | Nov 20, 2018

OSHA publishes updates to crane operator certification requirements

Long-delayed rules accept certifications by type or type and capacity.

Codes and Standards | Nov 19, 2018

Guide offers understanding of elements that create successful multi-floor communal spaces

CTBUH technical document analyzes how to approach tall urban habitat.

Codes and Standards | Nov 16, 2018

2018 International Green Construction Code released

Updated version helps governments streamline code development and adoption.

Codes and Standards | Nov 15, 2018

New versions of DOE’s EnergyPlus engine and the OpenStudio software development kit released

New offerings resolve over 70 bugs and offer new features.

Codes and Standards | Nov 14, 2018

Obsolete safety standards may have been used in cleanup of former naval shipyard

San Francisco redevelopment site work may have been racked by fraud.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021