Statue of Liberty update brings patrons closer to the action

Statue of Liberty update brings patrons closer to the action

While past renovation and restoration work on Liberty Island received more fanfare, the latest update arguably has had a greater impact on the three million people that visit the monument each year.


By David Barista, Editor-in-Chief | October 15, 2013
A yearlong renovation effort at Liberty Island involved inserting two staircases
A yearlong renovation effort at Liberty Island involved inserting two staircases and an elevator in the statues pedestal struct

While past renovation and restoration work on Liberty Island received more fanfare—particularly the tedious rebuilding of Lady Liberty’s copper skin in the mid- 1980s—the latest update arguably has had a greater impact on the three million people that visit the monument each year. What started out as a straightforward fire and life safety upgrade to bring the entire site up to code turned into a much grander mission for the Building Team: to improve the overall experience for visitors.

The scope of the project included the insertion of two enclosed exit staircases and an emergency evacuation elevator in the statue’s pedestal to replace outdated infrastructure, construction of two exit stairs from the terreplein at the base of the pedestal, and upgrades to all visitor facilities.

At each step of the project, the team factored visitor experience into its design solutions. The new pedestal staircases, for instance, were configured to offer more intimate views of the structure’s massive concrete walls and riveted steel members. 

STATUE OF LIBERTY NATIONAL MONUMENT
New York, N.Y.

Building Team 
Submitting firm: Mills + Schnoering Architects (architect) 
Owner: National Park Service 
Structural engineer: Keast & Hood 
MEP engineer: Joseph R. Loring & Associates 
Construction manager: Atkins North America 
General contractor: Joseph A. Natoli Construction
 
General Information 
Size: 52,790 sf 
Construction time: October 2011 to October 2012 
Delivery method: Design-bid-build

The team utilized laser scanning and BIM modeling to determine the optimal arrangement of the winding staircases and elevator shaft within the confined space. Their goal: to get as close as possible to the historic elements while still meeting fire/life safety and program requirements. In one section of the facility, for example, the bottom of an Eiffel steel beam forms the ceiling of the enclosed staircase, allowing patrons to reach up and touch the beam and its fasteners. High-efficiency lighting was used throughout to highlight the historic fabric and elements.

Complicating the project were the logistics of material and equipment delivery. Everything required for the project, including the labor force, had to be shipped by boat from Jersey City, N.J., and screened by the U.S. Park Police on every trip. All deliveries had to be scheduled in advance to ensure that USPP personnel and K9 teams were available. Stabilizing admixtures had to be added to the concrete to delay the curing process during the 35-minute barge ride. Once on Liberty Island, materials and equipment were moved by crane to four access points around the pedestal and carefully maneuvered inside the structure through the standard-size doors.

“Between working in the confined, historically sensitive spaces and managing the logistics of getting everything to the island, the team deserves this award,” said judge Daniel L. Doyle, PE, LEED AP O+M, President of Grumman/Butkus Associates (www.grummanbutkus.com).

 

Related Stories

| Mar 10, 2014

Field tested: Caterpillar’s Cat B15 rugged smartphone

The B15 is billed by Cat as “the most progressive, durable and rugged device available on the market today.” 

| Mar 10, 2014

5 rugged mobile devices geared for construction pros

BD+C readers share their most trusted smartphone and tablet cases. The editors select some of their faves, too. 

| Mar 7, 2014

Thom Mayne's high-tech Emerson College LA campus opens in Hollywood [slideshow]

The $85 million, 10-story vertical campus takes the shape of a massive, shimmering aircraft hangar, housing a sculptural, glass-and-aluminum base building.

| Mar 6, 2014

BD+C wants to hear about your breakthrough ideas and projects for the Giants 300 report

BD+C's 2014 Giants 300 survey form is now available. But completing the survey is just one way to participate in the July Giants issue. 

| Mar 6, 2014

Must see: Tour Seinfeld's apartment with virtual reality headset

Fans of the show can now explore a virtual 3D model of the iconic New York residence, thanks to one Web designer's painstaking effort.

| Mar 5, 2014

5 tile design trends for 2014

Beveled, geometric, and high-tech patterns are among the hot ceramic tile trends, say tile design experts.

| Mar 4, 2014

How EIFS came to America

Design experts from Hoffmann Architects offer a brief history of exterior insulation and finish systems in the U.S.

| Mar 4, 2014

If there’s no ‘STEM crisis,’ why build more STEM schools?

Before you get your shorts in a knot, I have nothing against science, technology, engineering, or even mathematics; to the contrary, I love all four “STEM” disciplines (I’m lying about the math). But I question whether we need to be building K-12 schools that overly emphasize or are totally devoted to STEM.

| Mar 3, 2014

Engineering and construction CEOs are cautiously optimistic about the global economy, says PwC

Firm leaders remain leery about the availability of skilled workers, the state of government debt and deficits, and rising material prices, according to PwC’s 2014 Global CEO Survey.

| Mar 1, 2014

Dramatic fractal roof highlights SOM's new Mumbai airport terminal [slideshow]

The terminal merges new technology and traditional regional architecture, notably in the fractal roof canopy that runs throughout the terminal. 

boombox1
boombox2
native1

More In Category

Construction Costs

Data center construction costs for 2024

Gordian’s data features more than 100 building models, including computer data centers. These localized models allow architects, engineers, and other preconstruction professionals to quickly and accurately create conceptual estimates for future builds. This table shows a five-year view of costs per square foot for one-story computer data centers. 


Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.



Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021