‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Codes and Standards

‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Study finds significant problems with how city manages capital projects.


By Peter Fabris, Contributing Editor | April 24, 2017

PIxabay Public Domain

A new report released by the Center for an Urban Future found significant flaws in how New York City manages capital projects for libraries and cultural institutions.

These projects encounter “staggering delays and exorbitant costs” the report says. The median new library and cultural project takes about seven years to complete and costs $930 per square foot, or roughly twice the cost of building a new office tower in the city, the report says.

The report, a joint project with the Citizens Budget Commission, analyzed 144 capital projects for libraries and cultural organizations completed between fiscal years 2010 and 2014. All were managed by the city’s Department of Design and Construction (DDC).

The report found that even seemingly routine maintenance projects end up taking years. For instance, the median mechanical system upgrade—including replacement and installation of fire alarms, boilers, and heating/cooling systems—took 4.3 years to complete. The study also found that when institutions are granted permission to self-manage capital projects, which is allowed on rare occasions, the projects typically take a fraction of the time and cost roughly 40% less.

Related Stories

| Jun 21, 2012

California adds window film to building code

California is the first state to add window film into its building code. Window film, a polymer material, offers cost-effective energy savings.

| Jun 21, 2012

New ISO standard to improve environmental management of concrete

A new ISO standard will help the construction industry better manage the environmental impacts of concrete.

| Jun 21, 2012

On net-zero projects, Building Teams will be held accountable for energy-efficiency performance

The building team will be held accountable for how net-zero energy buildings perform two, five, and maybe ten years after completion.

| Jun 14, 2012

USGBC co-founder launches rating system for building product manufacturers

U.S. Green Building Council co-founder David Gottfried’s new venture, Regenerative Ventures, has established a rating system for building product manufacturers.

| Jun 14, 2012

Green standard set for single-ply roofing membrane

A sustainability standard has been established for single-ply roofing membranes used on commercial buildings.

| Jun 14, 2012

Minnesota Vikings stadium plan gets legislative go-ahead

Legislation that approved the construction of a new billion dollar stadium for the Minnesota Vikings passed the Minnesota legislature.

| Jun 14, 2012

Report alleges New York’s prevailing construction wages are miscalculated, costing billions

A miscalculation in how prevailing wages are calculated in New York reportedly costs the state $3 billion a year in public-infrastructure projects.

| Jun 14, 2012

AGC, other business groups oppose hiring rules for disabled

Business groups have asked the U.S. Department of Labor to reconsider a proposed hiring quota aimed at federal contractors pertaining to people with disabilities.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021