‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Codes and Standards

‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Study finds significant problems with how city manages capital projects.


By Peter Fabris, Contributing Editor | April 24, 2017

PIxabay Public Domain

A new report released by the Center for an Urban Future found significant flaws in how New York City manages capital projects for libraries and cultural institutions.

These projects encounter “staggering delays and exorbitant costs” the report says. The median new library and cultural project takes about seven years to complete and costs $930 per square foot, or roughly twice the cost of building a new office tower in the city, the report says.

The report, a joint project with the Citizens Budget Commission, analyzed 144 capital projects for libraries and cultural organizations completed between fiscal years 2010 and 2014. All were managed by the city’s Department of Design and Construction (DDC).

The report found that even seemingly routine maintenance projects end up taking years. For instance, the median mechanical system upgrade—including replacement and installation of fire alarms, boilers, and heating/cooling systems—took 4.3 years to complete. The study also found that when institutions are granted permission to self-manage capital projects, which is allowed on rare occasions, the projects typically take a fraction of the time and cost roughly 40% less.

Related Stories

Codes and Standards | Jun 18, 2015

New document addresses school safety and security

In an effort to balance security and fire safety features within codes, standards and planning, NFPA hosted a two-day workshop, “School Safety, Codes and Security”, last December. The findings are now available in an NFPA report.

Codes and Standards | Jun 18, 2015

Two myths regarding NFPA 101 Life Safety Code debunked

NFPA life safety engineer Ron Coté settles the debate over second egress doors and exit signs.

Codes and Standards | Jun 18, 2015

How to prevent corrosion in sprinkler system piping

The technical committees responsible for NFPA 13, Installation of Sprinkler Systems, have been looking at ways to eliminate or reduce corrosion in sprinkler systems for several revision cycles.

Codes and Standards | Jun 11, 2015

Steel Framing Alliance updates ‘Thermal Design and Code Compliance for Cold-Formed Steel Walls’ design guide

Includes results of new tests and addresses IECC and ASHRAE compliance paths.

Codes and Standards | Jun 11, 2015

Helena, Mont., may charge commercial developers a fee to fund public art

The fee would apply to new construction or alteration of nonresidential buildings of at least 20,000 sf.

Codes and Standards | Jun 11, 2015

DBIA releases new document on choosing a project delivery method

Provides owners and others with factors to consider when choosing the best method of delivery for their project.

High-rise Construction | Jun 5, 2015

Japanese policymakers discuss mandate for toilets in elevators

This quirky-sounding building code is a safety measure for the earthquake-prone nation.

Codes and Standards | Jun 4, 2015

OSHA publishes guide to restroom access for transgender workers

The guide advises employers to allow employees to use restrooms that correspond to their gender identity.

Codes and Standards | Jun 4, 2015

Guide helps Building Teams maximize team integration

The guide includes forms to support a two- to four-hour workshop to help an owner select the most appropriate delivery strategy. 

Codes and Standards | Jun 4, 2015

NIBS, RICS to explore P3 as tool to achieve high-performance buildings

The idea of applying the P3 concept more to buildings, and especially building performance, is a potentially promising new avenue in the U.S., according to the trade groups.

boombox1
boombox2
native1

More In Category

Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021