‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Codes and Standards

‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Study finds significant problems with how city manages capital projects.


By Peter Fabris, Contributing Editor | April 24, 2017

PIxabay Public Domain

A new report released by the Center for an Urban Future found significant flaws in how New York City manages capital projects for libraries and cultural institutions.

These projects encounter “staggering delays and exorbitant costs” the report says. The median new library and cultural project takes about seven years to complete and costs $930 per square foot, or roughly twice the cost of building a new office tower in the city, the report says.

The report, a joint project with the Citizens Budget Commission, analyzed 144 capital projects for libraries and cultural organizations completed between fiscal years 2010 and 2014. All were managed by the city’s Department of Design and Construction (DDC).

The report found that even seemingly routine maintenance projects end up taking years. For instance, the median mechanical system upgrade—including replacement and installation of fire alarms, boilers, and heating/cooling systems—took 4.3 years to complete. The study also found that when institutions are granted permission to self-manage capital projects, which is allowed on rare occasions, the projects typically take a fraction of the time and cost roughly 40% less.

Related Stories

Legislation | Aug 10, 2016

Calif. bill would speed up environmental lawsuits on certain projects

A nine-month limit has been proposed for some $100 million-plus projects.

Resiliency | Aug 10, 2016

White House pushes for better finance strategies for disaster mitigation and resilience

The move highlights innovative insurance, mortgage, tax, and finance-based strategies.

Regulations | Aug 9, 2016

New trend eases parking requirements for U.S. cities

Transit-oriented development and affordable housing are spurring the movement. 

Regulations | Aug 8, 2016

EPA toughens rules to reduce formaldehyde exposure from composite wood products

Products will now have to be labeled as compliant to the new rules.

Regulations | Aug 5, 2016

Stop-work orders in New York City up sharply this year

The orders come after a rise in the number of deadly accidents that have occurred in the past few years.

Sustainability | Aug 4, 2016

S.F. Bay Area voters approve first-of-its-kind tax to fight impact of climate change

The funds from the tax will be used to restore wetlands

Concrete | Aug 2, 2016

Concrete Association builds case against cross-laminated timber

The campaign asserts that not enough is known about CLT in construction

Seismic Design | Jul 28, 2016

Risk of man-made earthquakes now factor in seismic hazard analysis

Significant risk increases seen in some areas of the U.S.  

Resiliency | Jul 27, 2016

New York’s resilience plans not taking long-term view, critics charge

Continued waterfront development may be regretted later this century.  

Green Specifications | Jul 26, 2016

New Miami Beach law requires LEED certification on projects larger than 7,000 sf

LEED Silver the prescribed standard on buildings larger than 50,000 sf.

boombox1
boombox2
native1

More In Category

Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021