Slow payments cost GCs and subs $64 billion annually

Codes and Standards

Slow payments cost GCs and subs $64 billion annually

Study finds 51-day average payment turnaround.


By Peter Fabris, Contributing Editor | October 17, 2019

Courtesy Pixabay

Delayed payments are costing both general contractors and subcontractors tens of billions annually, according to a new study.

The study was conducted by construction finance platform Rabbet, formerly Contract Simply, in partnership with Procore Technologies. A similar study by Rabbet in 2018 found that slow payments cost subcontractors $40 billion.

This year, the company added general contractors to the study, and found payment delays cost all contractors an estimated $64 billion. More than 60% of subcontractors said they have decided not to bid on certain projects if the owner or general contractor has a reputation for paying late. Some 72% said they would offer a 1% to 5% discount for quicker payments.

Just 39% of subcontractors said that they are able to cover late payments with cash on hand. Slow payments by owners drive up the cost of projects by about 5.3%, according to the study. Owners also risk mechanic’s liens and project shutdowns when they pay late.

Related Stories

Codes and Standards | Nov 29, 2021

FAA seeking design of air traffic control towers of the future

Call for design submissions for safe, efficient structures.

Codes and Standards | Nov 28, 2021

Efficient electric water heaters in multifamily buildings significantly reduce carbon emissions

In buildings with 5+ units, water heating uses more energy than space heating, cooling, or lighting.

Codes and Standards | Nov 23, 2021

New York’s Labor Law Section 240 and how it affects general contractors

The ‘Scaffold Law’ was first enacted by the New York State Legislature in 1885 and is one of the single most-used laws in construction accident cases.

Codes and Standards | Nov 22, 2021

ABC’s Construction Technology Report finds focus on solving operational problems

More than half rely on project management software.

Codes and Standards | Nov 22, 2021

Contractors say 811 utility location system has significant flaws

More than half of firms in survey report damages, near misses because lines were unmarked or marked incorrectly.

Codes and Standards | Nov 19, 2021

Creating net-zero/net-positive buildings is top priority in Green Building Trends 2021 report

Findings also demonstrate compelling business case for building green.

Codes and Standards | Nov 19, 2021

Construction Startup Competition 2021 awards highlight tech innovations

AI-powered software to identify and explain critical issues in construction contracts takes top prize.

Codes and Standards | Nov 18, 2021

Infrastructure bill contains $5 billion for energy efficiency in buildings

Wide range of programs to reduce energy use, improve materials, train workers.

Codes and Standards | Nov 17, 2021

Skanska will provide embodied carbon assessments on all new projects over 53,000 sf

Will use the Embodied Carbon in Construction Calculator it helped create.

Codes and Standards | Nov 16, 2021

NOAA, Univ. of Maryland, and ASCE partner on climate-smart engineering codes, standards

Efforts will account for climate change in future infrastructure design and construction.

boombox1
boombox2
native1

More In Category

Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021