Slow payments cost the construction industry $208 billion in 2022

Contractors

Slow payments cost the construction industry $208 billion in 2022

More than one-third of contractors say work has been delayed due to payment delays to workers, according to a new survey.


By Peter Fabris, Contributing Editor | December 6, 2022
Slow payments cost the construction industry $208 billion in 2022 Image by Tumisu from Pixabay
Image by Tumisu from Pixabay

The cost of floating payments for wages and invoices represents $208 billion in excess cost to the construction industry, a 53% increase from 2021, according to a survey by Rabbet, a provider of construction finance software.

Those costs are passed on to real estate developers and financiers in the form of project delays, added risk, and higher bids from contractors.

Other survey findings include:

  • 37% of all respondents report that work has been delayed or stopped due to a delay in payments to crew members
  • 62% of general contractors incurred billing charges, financing charges, or other costs when floating payments to others
  • There was an 8.5x increase in general contractors using retirement savings to float payments for their business

Though a 53% increase in the cost of slow payments in one year is major, it’s on par when considering the current economic environment, according to a Rabbet news release.

Some contractors said they are boosting their bids 5-10% to help absorb associated costs and are “pickier when selecting bids because of increasing labor and supply prices.”

Related Stories

| May 23, 2012

Arizona Army National Guard Readiness Center awarded LEED Silver

LEED certification of the AZ ARNG Readiness Center was based on a number of green design and construction features SAIC implemented that positively impacted the project and the broader community.

| May 23, 2012

New hospitals invest in data centers to manage growth in patient info

Silver Cross became one of the first hospitals to install patient tracking software so families know where a patient is at all times. New communication equipment supports wireless voice and data networks throughout the hospital, providing access to patients and their families while freeing clinicians to use phones and computers where needed instead of based on location.

| May 23, 2012

Summit Design+Build selected as GC for Chicago restaurant

Little Goat will truly be a multifunctional space.  Construction plans include stripping the 10,000 sq. ft. building down to the bare structure everywhere, the installation of a new custom elevator and adding square footage at the second floor with an addition.

| May 22, 2012

Batson-Cook names Partin VP of Business Development

Partin joins general contractor from Georgia Hospital Association.

| May 22, 2012

Casaccio Architects and GYA Architects join to form Casaccio Yu Architects

Architects Lee A. Casaccio, AIA, LEED AP, and George Yu, AIA, share leadership of the new firm.

| May 22, 2012

O’Connell Robertson acquires Mitchell Design Consultancy

Mary Ann A. Mitchell, AIA, IIDA, MDC principal and founder, joins O’Connell Robertson as part of the acquisition.

| May 21, 2012

$61,000 awarded to students in Cleveland’s ACE Mentor Program

Mayor Frank G. Jackson gives keynote address at scholarship event for 80 Cleveland Metropolitan School District students involved in the ACE Mentor Program, which provides guidance and assistance for students interested in careers in the integrated construction industry.

| May 21, 2012

Wayne, Pa.'s Radnor Middle School wins national green award

Radnor Middle School among the most sustainable schools in the U.S.

| May 21, 2012

Winchester High School receives NuRoof system

Metal Roof Consultants attended a school board meeting and presented a sloped metal retrofit roof as an alternative to tearing off the existing roof and replacing it with another flat roof.

| May 17, 2012

EMerge Alliance forms new Campus Microgrid Technical Standards Committee

Intel leading the charge to connect multiple DC microgrids throughout commercial buildings; others invited to join effort.

boombox1
boombox2
native1

More In Category



Curtain Wall

7 steps to investigating curtain wall leaks

It is common for significant curtain wall leakage to involve multiple variables. Therefore, a comprehensive multi-faceted investigation is required to determine the origin of leakage, according to building enclosure consultants Richard Aeck and John A. Rudisill with Rimkus. 


halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021