Shortage of skilled construction workers resulting in missed deadlines

Codes and Standards

Shortage of skilled construction workers resulting in missed deadlines

Some 40% of contractors have turned down project offers.


By Peter Fabris, Contributing Editor | March 27, 2019
Shortage of skilled construction workers resulting in missed deadlines

Photo: Pixabay/JonKline

A shortage of skilled construction labor is impacting the bottom line for contractors, according to the first-quarter 2019 Commercial Construction Index report by USG Corp. and the U.S. Chamber of Commerce.

The labor shortage has made it difficult for contractors to meet schedule deadlines. Seventy percent of contractors are struggling to meet project deadlines, the report says.

Forty percent of contractors said they have had to turn down project offers because they didn’t have enough people to do the work. The labor shortage has forced 81% of contractors to require employees to do extra work, and 63% say it has increased costs for new work.

Survey respondents said the key to attracting new workers is to emphasize the potential for high pay, good benefits, potential for career advancement, and the chance to work with advanced technology.

Related Stories

| Jul 12, 2012

New York’s One Bryant Park Bank of America tower is first new high-rise to achieve LEED Platinum

The new One Bryant Park Bank of America tower in midtown Manhattan is the first new commercial high-rise to achieve LEED Platinum certification.

| Jul 12, 2012

OSHA launches campaign to prevent heat illness

The Occupational Safety and Health Administration has launched its 2012 Heat Illness Prevention Campaign to educate employees and their employers about the hazards of working outdoors in heat, and how to prevent heat-related illnesses.

| Jul 12, 2012

Contractors have increasing concerns over new federal hiring quotas

A proposed rule by the U.S. Department of Labor's Office of Federal Contract Compliance Programs to increase disabled- and veteran-worker hiring quotas for federal contractors continues to raise deep concerns among contractors.

| Jul 5, 2012

Veterans Administration threatens to pull contract on new Orlando medical center

The Veterans Administration asked contractor Brasfield & Gorrie to get more workers on the job and figure out a way to get the job done faster, or the VA would pull the contract on the much-delayed Orlando VA Medical Center.

| Jul 5, 2012

Cost to contractors for new federal hiring quotas much higher than estimated, AGC says

Administration officials significantly underestimated the cost to construction employers of proposed new hiring quotas for federal contractors, according to analysis by the Associated General Contractors of America.

| Jul 5, 2012

Roof membrane could have prevented roof parking deck collapse, specialist says

The collapse of a section of a roof parking deck at the Algo Centre Mall in Elliot Lake in Ontario, Canada could have been prevented if the structure had a membrane, according to a concrete expert and specialist in structure analysis at McMaster University.

| Jul 5, 2012

New Joplin, Mo. hospital being built to withstand tornado that destroyed predecessor

After the May 22, 2011, EF-5 tornado destroyed St. John’s Regional Medical Center in Joplin, Mo., architects and engineers analyzed how the nine-story structure reacted to the storm.

| Jul 5, 2012

Continued tax breaks necessary for widespread adoption of net zero buildings

Tax breaks passed by the U.S. government to encourage construction of green buildings are set to expire in 2012 and 2013.

boombox1
boombox2
native1

More In Category


Resiliency

U.S. is reducing floodplain development in most areas

The perception that the U.S. has not been able to curb development in flood-prone areas is mostly inaccurate, according to new research from climate adaptation experts. A national survey of floodplain development between 2001 and 2019 found that fewer structures were built in floodplains than might be expected if cities were building at random.



halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021