School officials and parents are asking one question: Can design prevent another Sandy Hook? [2013 Giants 300 Report]

School officials and parents are asking one question: Can design prevent another Sandy Hook? [2013 Giants 300 Report]

The second deadliest mass shooting by a single person in U.S. history galvanizes school officials, parents, public officials, and police departments, as they scrambled to figure out how to prevent a similar incident in their communities. 


By Robert Cassidy, Editorial Director | July 22, 2013
Cherry Crest Elementary, Bellevue, Wash., is integrated with the landscape to cr
Cherry Crest Elementary, Bellevue, Wash., is integrated with the landscape to create varied learning environments. Classrooms are arranged in grade-level houses clustered around shared spaces; courtyards are used for outdoor lessons. The Building Team was led by NAC|Architecture. PHOTO: BENJAMIN BENSCHNEIDER PHOTOGRAPHY

Since last December 14, safety has become the paramount concern of every school official and school board member in this country. December 14, 2012, was the date on which 20-year-old Adam Lanza shot and killed 20 children and six adult staff members at Sandy Hook Elementary School, in Newtown, Conn. It was the second deadliest mass shooting by a single person in U.S. history, after the Virginia Tech tragedy of 2007.

Sandy Hook galvanized school officials, parents, public officials, and police departments, as they scrambled to figure out how to prevent a similar incident in their communities. Many asked: Could better design and construction of schools—preschool, elementary, and secondary—prevent or at least mitigate the casualty rate at another Sandy Hook? And could this be done not only for schools to be built in the future, where Building Teams would be working from a blank slate, but for the tens of thousands of extant schools from Maine to Hawaii, where physical conditions are often literally set in stone?

TOP K-12 SCHOOL SECTOR ARCHITECTURE FIRMS

 
2012 K-12 Revenue ($)
1 DLR Group $38,250,000
2 SHW Group $32,328,843
3 PBK $31,760,000
4 IBI Group $27,977,860
5 HMC Architects $25,407,164
6 Stantec $21,586,209
7 Fanning/Howey Associates $20,247,000
8 Perkins+Will $19,938,211
9 Heery International $16,561,303
10 LPA $14,438,017

TOP K-12 SCHOOL SECTOR ENGINEERING FIRMS

 
2012 K-12 Revenue ($)
1 AECOM Technology Corp. $100,150,000
2 URS Corp. $55,927,778
3 STV $45,937,000
4 Jacobs Engineering Group $36,550,000
5 Parsons Brinckerhoff $19,100,000
6 TTG $9,985,300
7 Shive-Hattery $7,379,425
8 BRPH $4,900,000
9 KCI Technologies $4,200,000
10 Dewberry $3,852,971

TOP K-12 SCHOOL SECTOR CONSTRUCTION FIRMS

 
2012 K-12 Revenue ($)
1 Gilbane $947,077,000
2 Balfour Beatty $483,944,476
3 Turner Corporation, The $357,910,000
4 CORE Construction Group $284,198,375
5 Skanska USA $273,418,351
6 McCarthy Holdings $260,000,000
7 Kraus-Anderson Construction $211,000,000
8 JE Dunn Construction $169,860,436
9 Consigli Construction $148,883,468
10 Barton Malow $139,236,049

These questions inspired a gathering of public officials, school designers and contractors, safety experts, and facility directors convened last February in Washington, D.C., by the Council of Educational Facilities Planners International. The daylong CEFPI Security Summit provided a framework in which to consider what school districts can do to provide a safer environment for children, teachers, and administrative staff. Following are the recommendations of immediate interest to the design and construction community.

Infrastructure needs beefing up, says CEFPI report

Emergency preparedness and response must be woven into the very fabric of school life, according to the CEFPI Security Summit report. The report recommends creating “concentric circles of protection” through the following means:

  • Providing the ability to lock students behind doors to protect them from aggression (door hardware companies report that they cannot keep up with demand for lock systems since Sandy Hook)
  • Shielding students from large windows
  • Safeguarding children when they meet in large groups for meals and assemblies
  • Installing high-security keying systems with control measures in place for master keys
  • Securing children, teachers, and staff via secured vestibules and remote access to select exterior and interior doors (through keyless entry systems)
  • Eliminating access to unauthorized persons by improving line-of-sight conditions and installing CCTV cameras
  • Protecting entrances through the use of bollards and safeguarding the exterior and perimeter—including playgrounds, athletic fields, and parking lots—via upgraded lighting and camera monitoring

Mass notifiation high on school districts' agenda

The CEFPI report also recommends action on crisis communications, notably:

  • Providing an effective public address system, with a backup power source
  • Use of multiple communications devices, including mobile panic devices worn by key administrators
  • Installation of security cameras and use of emergency radio channels

School districts are already acting. Plainfield District 202, the fourth-largest school district in Illinois, just ordered $180,000 worth of wireless alarm systems for its 30 schools.

As the fall term approaches, design and construction firms, as well as manufacturers of safety products and systems, will be called upon to safeguard the nation’s schoolchildren even more vigorously than in the past.

Read BD+C's full Giants 300 Report

Related Stories

| Oct 31, 2013

CBRE's bold experiment: 200-person office with no assigned desks [slideshow]

In an effort to reduce rent costs, real estate brokerage firm CBRE created its first completely "untethered" office in Los Angeles, where assigned desks and offices are replaced with flexible workspaces. 

| Oct 30, 2013

15 stellar historic preservation, adaptive reuse, and renovation projects

The winners of the 2013 Reconstruction Awards showcase the best work of distinguished Building Teams, encompassing historic preservation, adaptive reuse, and renovations and additions.

| Oct 30, 2013

11 hot BIM/VDC topics for 2013

If you like to geek out on building information modeling and virtual design and construction, you should enjoy this overview of the top BIM/VDC topics.

| Oct 29, 2013

Increased backlogs, margins lead to renewed optimism in global construction

After prolonged economic uncertainty, a majority of executives in the global engineering and construction sector have fresh confidence in the growth prospects for the industry, according to KPMG International's 2013 Global Construction Survey. A general increase in backlogs and margins is giving cause for optimism across the industry, with further growth anticipated.

| Oct 29, 2013

BIG opens subterranean Danish National Maritime Museum [slideshow]

BIG (Bjarke Ingels Group) has completed the Danish National Maritime Museum in Helsingør. By marrying the crucial historic elements with an innovative concept of galleries and way-finding, BIG’s renovation scheme reflects Denmark's historical and contemporary role as one of the world's leading maritime nations.

| Oct 28, 2013

Urban growth doesn’t have to destroy nature—it can work with it

Our collective desire to live in cities has never been stronger. According to the World Health Organization, 60% of the world’s population will live in a city by 2030. As urban populations swell, what people demand from their cities is evolving.

| Oct 28, 2013

Metal roofs are topping more urban dwellings

Given their durability and ease of use, metal roofs have been a common feature on rural houses for decades. Now they’re becoming an increasingly popular choice on urban dwellings as well. 

| Oct 25, 2013

Hoffmann Architects announces launch of U.S. Capitol Dome restoration

The Architect of the Capitol will undertake comprehensive restoration of the 150-year-old cast iron Dome, which has not undergone a complete restoration since 1959-1960.

| Oct 23, 2013

AIA: Crowd-funding shows promise for financing real estate projects

The American Institute of Architects issued a statement on the SEC's recent 5-0 vote to propose rules aimed at letting startups tap large numbers of ordinary investors for small amounts of capital. 

| Oct 23, 2013

Gehry, Foster join Battersea Power Station redevelopment

Norman Foster and Frank Gehry have been selected to design a retail section within the £8 billion redevelopment of Battersea Power Station in London.

boombox1
boombox2
native1

More In Category

Great Solutions

41 Great Solutions for architects, engineers, and contractors

AI ChatBots, ambient computing, floating MRIs, low-carbon cement, sunshine on demand, next-generation top-down construction. These and 35 other innovations make up our 2024 Great Solutions Report, which highlights fresh ideas and innovations from leading architecture, engineering, and construction firms.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021