School officials and parents are asking one question: Can design prevent another Sandy Hook? [2013 Giants 300 Report]

School officials and parents are asking one question: Can design prevent another Sandy Hook? [2013 Giants 300 Report]

The second deadliest mass shooting by a single person in U.S. history galvanizes school officials, parents, public officials, and police departments, as they scrambled to figure out how to prevent a similar incident in their communities. 


By Robert Cassidy, Editorial Director | July 22, 2013
Cherry Crest Elementary, Bellevue, Wash., is integrated with the landscape to cr
Cherry Crest Elementary, Bellevue, Wash., is integrated with the landscape to create varied learning environments. Classrooms are arranged in grade-level houses clustered around shared spaces; courtyards are used for outdoor lessons. The Building Team was led by NAC|Architecture. PHOTO: BENJAMIN BENSCHNEIDER PHOTOGRAPHY

Since last December 14, safety has become the paramount concern of every school official and school board member in this country. December 14, 2012, was the date on which 20-year-old Adam Lanza shot and killed 20 children and six adult staff members at Sandy Hook Elementary School, in Newtown, Conn. It was the second deadliest mass shooting by a single person in U.S. history, after the Virginia Tech tragedy of 2007.

Sandy Hook galvanized school officials, parents, public officials, and police departments, as they scrambled to figure out how to prevent a similar incident in their communities. Many asked: Could better design and construction of schools—preschool, elementary, and secondary—prevent or at least mitigate the casualty rate at another Sandy Hook? And could this be done not only for schools to be built in the future, where Building Teams would be working from a blank slate, but for the tens of thousands of extant schools from Maine to Hawaii, where physical conditions are often literally set in stone?

TOP K-12 SCHOOL SECTOR ARCHITECTURE FIRMS

 
2012 K-12 Revenue ($)
1 DLR Group $38,250,000
2 SHW Group $32,328,843
3 PBK $31,760,000
4 IBI Group $27,977,860
5 HMC Architects $25,407,164
6 Stantec $21,586,209
7 Fanning/Howey Associates $20,247,000
8 Perkins+Will $19,938,211
9 Heery International $16,561,303
10 LPA $14,438,017

TOP K-12 SCHOOL SECTOR ENGINEERING FIRMS

 
2012 K-12 Revenue ($)
1 AECOM Technology Corp. $100,150,000
2 URS Corp. $55,927,778
3 STV $45,937,000
4 Jacobs Engineering Group $36,550,000
5 Parsons Brinckerhoff $19,100,000
6 TTG $9,985,300
7 Shive-Hattery $7,379,425
8 BRPH $4,900,000
9 KCI Technologies $4,200,000
10 Dewberry $3,852,971

TOP K-12 SCHOOL SECTOR CONSTRUCTION FIRMS

 
2012 K-12 Revenue ($)
1 Gilbane $947,077,000
2 Balfour Beatty $483,944,476
3 Turner Corporation, The $357,910,000
4 CORE Construction Group $284,198,375
5 Skanska USA $273,418,351
6 McCarthy Holdings $260,000,000
7 Kraus-Anderson Construction $211,000,000
8 JE Dunn Construction $169,860,436
9 Consigli Construction $148,883,468
10 Barton Malow $139,236,049

These questions inspired a gathering of public officials, school designers and contractors, safety experts, and facility directors convened last February in Washington, D.C., by the Council of Educational Facilities Planners International. The daylong CEFPI Security Summit provided a framework in which to consider what school districts can do to provide a safer environment for children, teachers, and administrative staff. Following are the recommendations of immediate interest to the design and construction community.

Infrastructure needs beefing up, says CEFPI report

Emergency preparedness and response must be woven into the very fabric of school life, according to the CEFPI Security Summit report. The report recommends creating “concentric circles of protection” through the following means:

  • Providing the ability to lock students behind doors to protect them from aggression (door hardware companies report that they cannot keep up with demand for lock systems since Sandy Hook)
  • Shielding students from large windows
  • Safeguarding children when they meet in large groups for meals and assemblies
  • Installing high-security keying systems with control measures in place for master keys
  • Securing children, teachers, and staff via secured vestibules and remote access to select exterior and interior doors (through keyless entry systems)
  • Eliminating access to unauthorized persons by improving line-of-sight conditions and installing CCTV cameras
  • Protecting entrances through the use of bollards and safeguarding the exterior and perimeter—including playgrounds, athletic fields, and parking lots—via upgraded lighting and camera monitoring

Mass notifiation high on school districts' agenda

The CEFPI report also recommends action on crisis communications, notably:

  • Providing an effective public address system, with a backup power source
  • Use of multiple communications devices, including mobile panic devices worn by key administrators
  • Installation of security cameras and use of emergency radio channels

School districts are already acting. Plainfield District 202, the fourth-largest school district in Illinois, just ordered $180,000 worth of wireless alarm systems for its 30 schools.

As the fall term approaches, design and construction firms, as well as manufacturers of safety products and systems, will be called upon to safeguard the nation’s schoolchildren even more vigorously than in the past.

Read BD+C's full Giants 300 Report

Related Stories

Architects | Dec 9, 2019

Jonathan Moody promoted to CEO of Moody Nolan

New four-member Executive Team also named.

Big Data | Dec 4, 2019

AEC data's coming out party

AEC firms are finally putting to use project information they’ve been storing in their computers for years.

Building Owners | Dec 2, 2019

What building owners and AEC teams need to know about New York’s Climate Mobilization Act

On April 18, 2019, the New York City Council passed the Climate Mobilization Act, a suite of laws aimed to meet the city’s commitment to achieving carbon neutrality by 2050.

| Nov 26, 2019

Steinberg Hart and Holzman Moss Bottino Architecture combine to elevate design, expand opportunities and strengthen client relationships

This union creates a national architecture firm with enhanced design capabilities and expertise.

| Nov 8, 2019

Philadelphia architecture firm EwingCole acquires Baltimore firm Gaudreau

Philadelphia architecture firm EwingCole acquires Baltimore firm Gaudreau.

Multifamily Housing | Nov 7, 2019

Multifamily construction market remains strong heading into 2020

Fewer than one in 10 AEC firms doing multifamily work reported a decrease in proposal activity in Q3 2019, according to a PSMJ report.

Architects | Oct 29, 2019

Top takeaways from the Lean Construction Institute Congress 2019

More than 1,600 Lean experts gathered in Texas this month for LCI Congress 2019. Here are key takeaways from the event.

Giants 400 | Oct 25, 2019

Top 50 Airport Sector Architecture Firms for 2019

AECOM, Gensler, HNTB, Corgan, and HOK top the rankings of the nation's largest airport terminal sector architecture and architecture engineering (AE) firms, as reported in Building Design+Construction's 2019 Giants 300 Report.

Giants 400 | Oct 24, 2019

Top 125 Retail Architecture Firms for 2019

CallisonRTKL, Gensler, MG2, NELSON, and Stantec top the rankings of the nation's largest retail sector architecture and architecture engineering (AE) firms, as reported in Building Design+Construction's 2019 Giants 300 Report.

Architects | Oct 11, 2019

SMPS report tracks how AEC firms are utilizing marketing technology tools

With thousands of MarTech tools and apps on the market, design and construction firms are struggling to keep up.

boombox1
boombox2
native1

More In Category

Construction Costs

Data center construction costs for 2024

Gordian’s data features more than 100 building models, including computer data centers. These localized models allow architects, engineers, and other preconstruction professionals to quickly and accurately create conceptual estimates for future builds. This table shows a five-year view of costs per square foot for one-story computer data centers. 


Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.



Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021