Sacred synergy achieves goals for religious education [2013 Building Team Award winner]

Sacred synergy achieves goals for religious education [2013 Building Team Award winner]

A renovation/addition project at Columbia Theological Seminary unites a historic residence hall with a modern classroom facility.


By Raissa Rocha, Associate Editor | June 12, 2013
The tower at the Vernon S. Broyles Leadership Center unifies a new addition (lef
The tower at the Vernon S. Broyles Leadership Center unifies a new addition (left) with the rehabilitated Simons-Law building (right). The glass tower, which was built to support a future carillon, features brick piers that reinforce the projects neoGothic style.
This article first appeared in the BD+C June 2013 issue of BD+C.
Columbia Theological Seminary, just east of Atlanta, offers graduate degree programs and continuing education for professionals and lay people in the Presbyterian Church (USA). Devoted to the spiritual growth of students, the seminary’s Vernon S. Broyles Jr. Leadership Center features a modern new classroom facility plus a renovation of the adjacent Simons-Law building, a historic dormitory built in 1932. The project represents a successful collaboration between the owner and other Building Team members—fitting for an educational institution that ranks teamwork and cooperative decisionmaking among its core values.
 
The original master plan called for the demolition and replacement of Simons-Law. But team members Lord, Aeck & Sargent and New South Construction saw the building as important to the campus, and presented stakeholders (including donors) with a detailed cost analysis that compared new construction with an addition/renovation. They convinced the client to retain the historic structure. Smaller spaces such as offices and seminar rooms would be reprogrammed into Simons-Law, and a 16,000-sf L-shaped addition would house large lecture halls, high-tech seminar rooms, the campus bookstore, a media center, informal study spaces, and a gallery concourse devoted to religious artifacts.
 
To rehabilitate Simons-Law, the team replaced lighting, HVAC, plumbing, exterior windows, and interior walls and doors. Roof shingles were replaced with synthetic slate, and the structure’s brick and cast stone walls were cleaned and repaired.
 
The architect also took care to ensure the seamless combination of the Gothic building with its new neighbor. An arcade links Simons-Law’s iconic arched passageway with the new building, creating a cloistered courtyard that also functions as an outdoor classroom.
 
Daylighting was a concern for the large classroom spaces in the addition, which were outfitted with high-tech A/V systems. The goal was to minimize use of artificial lighting while also avoiding the need for motorized shades. After careful study, the architect, A/V consultant, and CM created a classroom environment that makes excellent use of natural daylight while also ensuring that students will be able to see projections.
 
Other sustainable strategies included construction of a cistern, allowing rainwater to be collected for irrigation; a new energy-efficient variable refrigerant flow mechanical system; and the harvesting of wood on-site for flooring. The efforts paid off in a successful bid for LEED Gold certification.
 
The focal point of the project, melding old and new construction, is a neo-Gothic glass-and-brick tower that welcomes visitors to the center. With flooring made from a tree that once stood where the tower was built, this element was designed to unite all aspects of the project. The Building Team provided appropriate structural support for a planned belfry carillon, which will ring chimes for future generations of leaders as they make their way across the scenic campus.
 
Project summary
BRONZE AWARD
 
Columbia Theological Seminary
Vernon S. Broyles Jr. Leadership Center
Decatur, Ga.
 
BUILDING TEAM
Submitting firm: Lord, Aeck & Sargent (architect)
Owner/developer: Columbia Theological Seminary
Structural: Uzun & Case Engineers
MEP: AHA Consulting Engineers
Program manager: Morgan Constructors
A/V consultant: Waveguide Consulting
Construction manager: New South Construction
 
GENERAL INFORMATION
Project size: 36,500 sf (16,000 sf new + 20,500 sf renovated)
Construction cost: $8.2 million
Construction time: February 2011 to January 2012
Delivery method: CM at risk

Related Stories

| Sep 20, 2012

Mid-box retail study shows lack of available sites in Chicago

Existing supply is tight everywhere and almost non-existent in the most attractive zones.

| Sep 20, 2012

Forrester begins construction of freestanding cancer center in Montgomery County, Md.

The new 51,000-square-foot building will include two linear accelerator vaults for radiation equipment.

| Sep 19, 2012

Modular, LEED-Gold Certified Dormitory Accommodates Appalachian State University Growth

By using modular construction, the university was able to open a dorm a full year earlier than a similar dorm built at the same time with traditional construction.

| Sep 19, 2012

ABI back into positive territory

South continues to lead regions in demand for design services.

| Sep 19, 2012

HGA Architects & Engineers moves offices in San Francisco

HGA’s San Francisco office has grown by nearly 25% in the past two years, adding shared expertise to the 120-person California practice, which includes the Sacramento and Los Angeles offices.

| Sep 19, 2012

Sasaki opens office in Shanghai

Office supports firm’s present and future work in China, throughout Asia.

| Sep 18, 2012

MBMA partners with ORNL for whole building energy efficiency study

The results are intended to advance energy efficiency solutions for new and retrofit applications.

| Sep 18, 2012

MKK opens office in North Dakota

MKK is currently working on seven projects in North Dakota, including a hotel, restaurant, truck stop, office building, and apartment complex.

| Sep 18, 2012

Firestone Building Products launches new website

Deep product information and innovative customer support tools are highlights.

| Sep 13, 2012

Leo A Daly Company promotes Kraskiewicz to senior vice president

Kraskiewicz, who most recently served as chief operations officer for the Leo A Daly division, will guide brand management, business development, operations and financial performance for 18 offices worldwide.

boombox1
boombox2
native1

More In Category



Urban Planning

The magic of L.A.’s Melrose Mile

Great streets are generally not initially curated or willed into being. Rather, they emerge organically from unintentional synergies of commercial, business, cultural and economic drivers. L.A.’s Melrose Avenue is a prime example. 


Curtain Wall

7 steps to investigating curtain wall leaks

It is common for significant curtain wall leakage to involve multiple variables. Therefore, a comprehensive multi-faceted investigation is required to determine the origin of leakage, according to building enclosure consultants Richard Aeck and John A. Rudisill with Rimkus. 

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021