Sacred synergy achieves goals for religious education [2013 Building Team Award winner]

Sacred synergy achieves goals for religious education [2013 Building Team Award winner]

A renovation/addition project at Columbia Theological Seminary unites a historic residence hall with a modern classroom facility.


By Raissa Rocha, Associate Editor | June 12, 2013
The tower at the Vernon S. Broyles Leadership Center unifies a new addition (lef
The tower at the Vernon S. Broyles Leadership Center unifies a new addition (left) with the rehabilitated Simons-Law building (right). The glass tower, which was built to support a future carillon, features brick piers that reinforce the projects neoGothic style.
This article first appeared in the BD+C June 2013 issue of BD+C.
Columbia Theological Seminary, just east of Atlanta, offers graduate degree programs and continuing education for professionals and lay people in the Presbyterian Church (USA). Devoted to the spiritual growth of students, the seminary’s Vernon S. Broyles Jr. Leadership Center features a modern new classroom facility plus a renovation of the adjacent Simons-Law building, a historic dormitory built in 1932. The project represents a successful collaboration between the owner and other Building Team members—fitting for an educational institution that ranks teamwork and cooperative decisionmaking among its core values.
 
The original master plan called for the demolition and replacement of Simons-Law. But team members Lord, Aeck & Sargent and New South Construction saw the building as important to the campus, and presented stakeholders (including donors) with a detailed cost analysis that compared new construction with an addition/renovation. They convinced the client to retain the historic structure. Smaller spaces such as offices and seminar rooms would be reprogrammed into Simons-Law, and a 16,000-sf L-shaped addition would house large lecture halls, high-tech seminar rooms, the campus bookstore, a media center, informal study spaces, and a gallery concourse devoted to religious artifacts.
 
To rehabilitate Simons-Law, the team replaced lighting, HVAC, plumbing, exterior windows, and interior walls and doors. Roof shingles were replaced with synthetic slate, and the structure’s brick and cast stone walls were cleaned and repaired.
 
The architect also took care to ensure the seamless combination of the Gothic building with its new neighbor. An arcade links Simons-Law’s iconic arched passageway with the new building, creating a cloistered courtyard that also functions as an outdoor classroom.
 
Daylighting was a concern for the large classroom spaces in the addition, which were outfitted with high-tech A/V systems. The goal was to minimize use of artificial lighting while also avoiding the need for motorized shades. After careful study, the architect, A/V consultant, and CM created a classroom environment that makes excellent use of natural daylight while also ensuring that students will be able to see projections.
 
Other sustainable strategies included construction of a cistern, allowing rainwater to be collected for irrigation; a new energy-efficient variable refrigerant flow mechanical system; and the harvesting of wood on-site for flooring. The efforts paid off in a successful bid for LEED Gold certification.
 
The focal point of the project, melding old and new construction, is a neo-Gothic glass-and-brick tower that welcomes visitors to the center. With flooring made from a tree that once stood where the tower was built, this element was designed to unite all aspects of the project. The Building Team provided appropriate structural support for a planned belfry carillon, which will ring chimes for future generations of leaders as they make their way across the scenic campus.
 
Project summary
BRONZE AWARD
 
Columbia Theological Seminary
Vernon S. Broyles Jr. Leadership Center
Decatur, Ga.
 
BUILDING TEAM
Submitting firm: Lord, Aeck & Sargent (architect)
Owner/developer: Columbia Theological Seminary
Structural: Uzun & Case Engineers
MEP: AHA Consulting Engineers
Program manager: Morgan Constructors
A/V consultant: Waveguide Consulting
Construction manager: New South Construction
 
GENERAL INFORMATION
Project size: 36,500 sf (16,000 sf new + 20,500 sf renovated)
Construction cost: $8.2 million
Construction time: February 2011 to January 2012
Delivery method: CM at risk

Related Stories

| Nov 18, 2013

How do construction professionals use social media?

LinkedIn is the social network used by most construction professionals, according to the results of a newly released national survey conducted by the Construction Marketing Association. 

| Nov 17, 2013

How to spend your first 15 minutes with a prospect

Every business development person has been there. You’ve finally earned a few minutes to impress a prospect that you’ve been pursuing. This is your opportunity to shine. What do you say?

| Nov 17, 2013

Meet up with the BD+C team at Greenbuild. Drinks are on us!

To all our friends in the AEC industry, you are cordially invited to join the BD+C team at several fun events during the Greenbuild show this week. No RSVP required. Just show up and enjoy. 

| Nov 15, 2013

Halls of ivy keep getting greener and greener

Academic institutions have been testing the limits of energy-conserving technologies, devising new ways to pay for sustainability extras, and extending sustainability to the whole campus.

| Nov 15, 2013

Pedia-Pod: A state-of-the-art pediatric building module

This demonstration pediatric treatment building module is “kid-friendly,” offering a unique and cheerful environment where a child can feel most comfortable. 

| Nov 15, 2013

Metal makes its mark on interior spaces

Beyond its long-standing role as a preferred material for a building’s structure and roof, metal is making its mark on interior spaces as well. 

| Nov 14, 2013

Fan of Frank Lloyd Wright? Here's your chance to run his architecture school

The Frank Lloyd Wright School of Architecture has launched a search for a new director. Deadline for applications is January 6, 2014.

| Nov 13, 2013

Government work keeps green AEC firms busy

With the economy picking up, many stalled government contracts are reaching completion and earning their green credentials.

| Nov 13, 2013

First look: Renzo Piano's addition to Louis Kahn's Kimbell Art Museum [slideshow]

The $135 million, 101,130-sf colonnaded pavilion by the famed architect opens later this month. 

| Nov 11, 2013

4 trends driving the recovering commercial construction sector

Jones Lang LaSalle research reveals a four-point “new look” for the post-recession construction industry.

boombox1
boombox2
native1

More In Category


Museums

The Tampa Museum of Art will soon undergo a $110 million expansion

In Tampa, Fla., the Tampa Museum of Art will soon undergo a 77,904-sf Centennial Expansion project. The museum plans to reach its $110 million fundraising goal by late 2024 or early 2025 and then break ground. Designed by Weiss/Manfredi, and with construction manager The Beck Group, the expansion will redefine the museum’s surrounding site.



Reconstruction & Renovation

Movement to protect historic buildings raises sharp criticism

While the movement to preserve historic buildings has widespread support, it also has some sharp critics with well-funded opposition groups springing up in recent years. Some opponents are linked to the Stand Together Foundation, founded and bankrolled by the Koch family’s conservative philanthropic organization, according to a column in Governing magazine.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021