Sacred synergy achieves goals for religious education [2013 Building Team Award winner]

Sacred synergy achieves goals for religious education [2013 Building Team Award winner]

A renovation/addition project at Columbia Theological Seminary unites a historic residence hall with a modern classroom facility.


By Raissa Rocha, Associate Editor | June 12, 2013
The tower at the Vernon S. Broyles Leadership Center unifies a new addition (lef
The tower at the Vernon S. Broyles Leadership Center unifies a new addition (left) with the rehabilitated Simons-Law building (right). The glass tower, which was built to support a future carillon, features brick piers that reinforce the projects neoGothic style.
This article first appeared in the BD+C June 2013 issue of BD+C.
Columbia Theological Seminary, just east of Atlanta, offers graduate degree programs and continuing education for professionals and lay people in the Presbyterian Church (USA). Devoted to the spiritual growth of students, the seminary’s Vernon S. Broyles Jr. Leadership Center features a modern new classroom facility plus a renovation of the adjacent Simons-Law building, a historic dormitory built in 1932. The project represents a successful collaboration between the owner and other Building Team members—fitting for an educational institution that ranks teamwork and cooperative decisionmaking among its core values.
 
The original master plan called for the demolition and replacement of Simons-Law. But team members Lord, Aeck & Sargent and New South Construction saw the building as important to the campus, and presented stakeholders (including donors) with a detailed cost analysis that compared new construction with an addition/renovation. They convinced the client to retain the historic structure. Smaller spaces such as offices and seminar rooms would be reprogrammed into Simons-Law, and a 16,000-sf L-shaped addition would house large lecture halls, high-tech seminar rooms, the campus bookstore, a media center, informal study spaces, and a gallery concourse devoted to religious artifacts.
 
To rehabilitate Simons-Law, the team replaced lighting, HVAC, plumbing, exterior windows, and interior walls and doors. Roof shingles were replaced with synthetic slate, and the structure’s brick and cast stone walls were cleaned and repaired.
 
The architect also took care to ensure the seamless combination of the Gothic building with its new neighbor. An arcade links Simons-Law’s iconic arched passageway with the new building, creating a cloistered courtyard that also functions as an outdoor classroom.
 
Daylighting was a concern for the large classroom spaces in the addition, which were outfitted with high-tech A/V systems. The goal was to minimize use of artificial lighting while also avoiding the need for motorized shades. After careful study, the architect, A/V consultant, and CM created a classroom environment that makes excellent use of natural daylight while also ensuring that students will be able to see projections.
 
Other sustainable strategies included construction of a cistern, allowing rainwater to be collected for irrigation; a new energy-efficient variable refrigerant flow mechanical system; and the harvesting of wood on-site for flooring. The efforts paid off in a successful bid for LEED Gold certification.
 
The focal point of the project, melding old and new construction, is a neo-Gothic glass-and-brick tower that welcomes visitors to the center. With flooring made from a tree that once stood where the tower was built, this element was designed to unite all aspects of the project. The Building Team provided appropriate structural support for a planned belfry carillon, which will ring chimes for future generations of leaders as they make their way across the scenic campus.
 
Project summary
BRONZE AWARD
 
Columbia Theological Seminary
Vernon S. Broyles Jr. Leadership Center
Decatur, Ga.
 
BUILDING TEAM
Submitting firm: Lord, Aeck & Sargent (architect)
Owner/developer: Columbia Theological Seminary
Structural: Uzun & Case Engineers
MEP: AHA Consulting Engineers
Program manager: Morgan Constructors
A/V consultant: Waveguide Consulting
Construction manager: New South Construction
 
GENERAL INFORMATION
Project size: 36,500 sf (16,000 sf new + 20,500 sf renovated)
Construction cost: $8.2 million
Construction time: February 2011 to January 2012
Delivery method: CM at risk

Related Stories

| Feb 28, 2014

Six finalists selected in design competition for Canadian Holocaust monument

David Adjaye and Daniel Libeskind are among the finalists for the National Holocaust Monument, planned near the Canadian War Museum in Ottawa.

| Feb 27, 2014

Gensler reveals 44 design trends for the next decade

The 82-page report covers dozens of emerging trends in healthcare, commercial office, hospitality, tall buildings, and more.

| Feb 27, 2014

Target converts former prison dump into latest big-box store

Target's new San Rafael, Calif., location was built on the site of the former San Quentin prison dump. 

| Feb 27, 2014

Open or private offices? It depends on the business plan

Open layouts are grabbing headlines as a hallmark of the new workplace—think the Google campus or Facebook's headquarters. And for smaller-scale operations, open designs are often lauded for being less expensive than private office plans. But does that mean all offices should have an open layout?

| Feb 27, 2014

3 reasons to apply computational fluid dynamics on your next project

From right-sizing mechanical systems to understanding the impact of design alternatives, CFD offers a host of benefits for the Building Team. 

| Feb 27, 2014

12 facts about heat-treated glass: Why stronger isn’t always better

Glass is heat-treated for two reasons: the first is to increase its strength to resist external stresses such as wind and snow loads, or thermal loads caused by the sun’s energy. The second is to temper glass so that it meets safety glazing requirements defined by applicable codes or federal standards. 

| Feb 27, 2014

Metal Construction Association introduces two Environmental Product Declarations

Two Environmental Product Declarations (EPD), one for Metal Composite Material Panels and one for  Roll Formed Steel Panels for Roofs and Walls, are now available free of charge from the Metal Construction Association (MCA) on its website.

| Feb 27, 2014

Bluebeam Software launches Revu 12 for better field-ready document management and project collaboration

The latest version of the company’s flagship solution better enables users in document-intensive industries to digitally collaborate on project documents and more easily connect the office to the field.

| Feb 27, 2014

PocketCake lunches CPU designed for virtual reality simulations

The company's Virtual Reality Simulation Converter Assembly is three times more powerful than the average high-performance computer and allows for up to eight people to experience a virtual reality simulation at the same time.

| Feb 26, 2014

Adaptive reuse project brings school into historic paper mill

The project features nontraditional classrooms for collaborative learning, an arts and music wing, and a technologically sophisticated global resource center.

boombox1
boombox2
native1

More In Category


Museums

The Tampa Museum of Art will soon undergo a $110 million expansion

In Tampa, Fla., the Tampa Museum of Art will soon undergo a 77,904-sf Centennial Expansion project. The museum plans to reach its $110 million fundraising goal by late 2024 or early 2025 and then break ground. Designed by Weiss/Manfredi, and with construction manager The Beck Group, the expansion will redefine the museum’s surrounding site.



Reconstruction & Renovation

Movement to protect historic buildings raises sharp criticism

While the movement to preserve historic buildings has widespread support, it also has some sharp critics with well-funded opposition groups springing up in recent years. Some opponents are linked to the Stand Together Foundation, founded and bankrolled by the Koch family’s conservative philanthropic organization, according to a column in Governing magazine.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021