Sacred synergy achieves goals for religious education [2013 Building Team Award winner]

Sacred synergy achieves goals for religious education [2013 Building Team Award winner]

A renovation/addition project at Columbia Theological Seminary unites a historic residence hall with a modern classroom facility.


By Raissa Rocha, Associate Editor | June 12, 2013
The tower at the Vernon S. Broyles Leadership Center unifies a new addition (lef
The tower at the Vernon S. Broyles Leadership Center unifies a new addition (left) with the rehabilitated Simons-Law building (right). The glass tower, which was built to support a future carillon, features brick piers that reinforce the projects neoGothic style.
This article first appeared in the BD+C June 2013 issue of BD+C.
Columbia Theological Seminary, just east of Atlanta, offers graduate degree programs and continuing education for professionals and lay people in the Presbyterian Church (USA). Devoted to the spiritual growth of students, the seminary’s Vernon S. Broyles Jr. Leadership Center features a modern new classroom facility plus a renovation of the adjacent Simons-Law building, a historic dormitory built in 1932. The project represents a successful collaboration between the owner and other Building Team members—fitting for an educational institution that ranks teamwork and cooperative decisionmaking among its core values.
 
The original master plan called for the demolition and replacement of Simons-Law. But team members Lord, Aeck & Sargent and New South Construction saw the building as important to the campus, and presented stakeholders (including donors) with a detailed cost analysis that compared new construction with an addition/renovation. They convinced the client to retain the historic structure. Smaller spaces such as offices and seminar rooms would be reprogrammed into Simons-Law, and a 16,000-sf L-shaped addition would house large lecture halls, high-tech seminar rooms, the campus bookstore, a media center, informal study spaces, and a gallery concourse devoted to religious artifacts.
 
To rehabilitate Simons-Law, the team replaced lighting, HVAC, plumbing, exterior windows, and interior walls and doors. Roof shingles were replaced with synthetic slate, and the structure’s brick and cast stone walls were cleaned and repaired.
 
The architect also took care to ensure the seamless combination of the Gothic building with its new neighbor. An arcade links Simons-Law’s iconic arched passageway with the new building, creating a cloistered courtyard that also functions as an outdoor classroom.
 
Daylighting was a concern for the large classroom spaces in the addition, which were outfitted with high-tech A/V systems. The goal was to minimize use of artificial lighting while also avoiding the need for motorized shades. After careful study, the architect, A/V consultant, and CM created a classroom environment that makes excellent use of natural daylight while also ensuring that students will be able to see projections.
 
Other sustainable strategies included construction of a cistern, allowing rainwater to be collected for irrigation; a new energy-efficient variable refrigerant flow mechanical system; and the harvesting of wood on-site for flooring. The efforts paid off in a successful bid for LEED Gold certification.
 
The focal point of the project, melding old and new construction, is a neo-Gothic glass-and-brick tower that welcomes visitors to the center. With flooring made from a tree that once stood where the tower was built, this element was designed to unite all aspects of the project. The Building Team provided appropriate structural support for a planned belfry carillon, which will ring chimes for future generations of leaders as they make their way across the scenic campus.
 
Project summary
BRONZE AWARD
 
Columbia Theological Seminary
Vernon S. Broyles Jr. Leadership Center
Decatur, Ga.
 
BUILDING TEAM
Submitting firm: Lord, Aeck & Sargent (architect)
Owner/developer: Columbia Theological Seminary
Structural: Uzun & Case Engineers
MEP: AHA Consulting Engineers
Program manager: Morgan Constructors
A/V consultant: Waveguide Consulting
Construction manager: New South Construction
 
GENERAL INFORMATION
Project size: 36,500 sf (16,000 sf new + 20,500 sf renovated)
Construction cost: $8.2 million
Construction time: February 2011 to January 2012
Delivery method: CM at risk

Related Stories

| Jul 2, 2014

First Look: Qatar World Cup stadium design references nomadic heritage

Organizers of the Qatar 2022 World Cup, the Supreme Committee for Delivery and Legacy, recently unveiled designs for the second stadium.

| Jul 2, 2014

SHoP designs what would be Brooklyn's tallest building

JDS Development partners with SHoP to construct a 70-story building at 775-feet tall, unprecedented for downtown Brooklyn.

| Jul 2, 2014

The doctor is in the firehouse: New clinic to be built in California fire station

Designed by WRNS Studio, the Firehouse Clinic will encourage local residents with limited healthcare access to consider them as an alternative to the emergency room, especially for preventive care. 

| Jul 2, 2014

Emerging trends in commercial flooring

Rectangular tiles, digital graphic applications, the resurgence of terrazzo, and product transparency headline today’s commercial flooring trends.

| Jul 2, 2014

Grimshaw's 'kit of parts' design scheme selected for Qatar sports facilities program

The series of projects, called the Al Farjan Recreational Sports Facilities, have been designed in such a way that the same basic design can be adapted to the specific requirements of each site.

| Jul 1, 2014

Peter Zumthor's LA art museum plan modified with bridge-like section across main thoroughfare

After his design drew concerns about potential damage to LA's La Brea Tar Pits, Peter Zumthor has dramatically revised his concept for the Los Angeles Museum of Art.

| Jul 1, 2014

China's wild circular skyscraper opens in Guangzhou [slideshow]

The 33-story Guanghzou Circle takes the shape of a giant ribbon spool, with the floor space housed in a series of boxes suspended between two massive "wheels." 

| Jul 1, 2014

Hyper-speed rendering: How Gensler turns BIM models into beauty shots in seconds

In search of a fast rendering solution, Gensler looked to the gaming and moviemaking industries for the next breakthrough tool: Octane Render.

| Jul 1, 2014

Sochi's 'kinetic façade' may steal the show at the Winter Olympics

The temporary pavilion for Russian telecom operator MegaFon will be wrapped with a massive digital "pin screen" that will morph into the shape of any face.

| Jul 1, 2014

7 ways to cut waste in BIM implementation

Process mapping, split models, and streamlined coordination meetings are among the timesaving techniques AEC firms are employing to improve BIM/VDC workflows.

boombox1
boombox2
native1

More In Category


Museums

The Tampa Museum of Art will soon undergo a $110 million expansion

In Tampa, Fla., the Tampa Museum of Art will soon undergo a 77,904-sf Centennial Expansion project. The museum plans to reach its $110 million fundraising goal by late 2024 or early 2025 and then break ground. Designed by Weiss/Manfredi, and with construction manager The Beck Group, the expansion will redefine the museum’s surrounding site.



Reconstruction & Renovation

Movement to protect historic buildings raises sharp criticism

While the movement to preserve historic buildings has widespread support, it also has some sharp critics with well-funded opposition groups springing up in recent years. Some opponents are linked to the Stand Together Foundation, founded and bankrolled by the Koch family’s conservative philanthropic organization, according to a column in Governing magazine.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021