Sacred synergy achieves goals for religious education [2013 Building Team Award winner]

Sacred synergy achieves goals for religious education [2013 Building Team Award winner]

A renovation/addition project at Columbia Theological Seminary unites a historic residence hall with a modern classroom facility.


By Raissa Rocha, Associate Editor | June 12, 2013
The tower at the Vernon S. Broyles Leadership Center unifies a new addition (lef
The tower at the Vernon S. Broyles Leadership Center unifies a new addition (left) with the rehabilitated Simons-Law building (right). The glass tower, which was built to support a future carillon, features brick piers that reinforce the projects neoGothic style.
This article first appeared in the BD+C June 2013 issue of BD+C.
Columbia Theological Seminary, just east of Atlanta, offers graduate degree programs and continuing education for professionals and lay people in the Presbyterian Church (USA). Devoted to the spiritual growth of students, the seminary’s Vernon S. Broyles Jr. Leadership Center features a modern new classroom facility plus a renovation of the adjacent Simons-Law building, a historic dormitory built in 1932. The project represents a successful collaboration between the owner and other Building Team members—fitting for an educational institution that ranks teamwork and cooperative decisionmaking among its core values.
 
The original master plan called for the demolition and replacement of Simons-Law. But team members Lord, Aeck & Sargent and New South Construction saw the building as important to the campus, and presented stakeholders (including donors) with a detailed cost analysis that compared new construction with an addition/renovation. They convinced the client to retain the historic structure. Smaller spaces such as offices and seminar rooms would be reprogrammed into Simons-Law, and a 16,000-sf L-shaped addition would house large lecture halls, high-tech seminar rooms, the campus bookstore, a media center, informal study spaces, and a gallery concourse devoted to religious artifacts.
 
To rehabilitate Simons-Law, the team replaced lighting, HVAC, plumbing, exterior windows, and interior walls and doors. Roof shingles were replaced with synthetic slate, and the structure’s brick and cast stone walls were cleaned and repaired.
 
The architect also took care to ensure the seamless combination of the Gothic building with its new neighbor. An arcade links Simons-Law’s iconic arched passageway with the new building, creating a cloistered courtyard that also functions as an outdoor classroom.
 
Daylighting was a concern for the large classroom spaces in the addition, which were outfitted with high-tech A/V systems. The goal was to minimize use of artificial lighting while also avoiding the need for motorized shades. After careful study, the architect, A/V consultant, and CM created a classroom environment that makes excellent use of natural daylight while also ensuring that students will be able to see projections.
 
Other sustainable strategies included construction of a cistern, allowing rainwater to be collected for irrigation; a new energy-efficient variable refrigerant flow mechanical system; and the harvesting of wood on-site for flooring. The efforts paid off in a successful bid for LEED Gold certification.
 
The focal point of the project, melding old and new construction, is a neo-Gothic glass-and-brick tower that welcomes visitors to the center. With flooring made from a tree that once stood where the tower was built, this element was designed to unite all aspects of the project. The Building Team provided appropriate structural support for a planned belfry carillon, which will ring chimes for future generations of leaders as they make their way across the scenic campus.
 
Project summary
BRONZE AWARD
 
Columbia Theological Seminary
Vernon S. Broyles Jr. Leadership Center
Decatur, Ga.
 
BUILDING TEAM
Submitting firm: Lord, Aeck & Sargent (architect)
Owner/developer: Columbia Theological Seminary
Structural: Uzun & Case Engineers
MEP: AHA Consulting Engineers
Program manager: Morgan Constructors
A/V consultant: Waveguide Consulting
Construction manager: New South Construction
 
GENERAL INFORMATION
Project size: 36,500 sf (16,000 sf new + 20,500 sf renovated)
Construction cost: $8.2 million
Construction time: February 2011 to January 2012
Delivery method: CM at risk

Related Stories

Cultural Facilities | Jul 19, 2015

SET Architects wins design competition for Holocaust Memorial

The design for the memorial in Bologna, Italy, is dominated by two large metal monolithic structures that represent the oppressive wooden bunks in concentration camps in Germany during World War II.

Sports and Recreational Facilities | Jul 17, 2015

Japan scraps Zaha Hadid's Tokyo Olympic Stadium project

The rising price tag was one of the downfalls of the 70-meter-tall, 290,000-sm stadium. In 2014, the cost of the project was 163 billion yen, but that rose to 252 billion yen this year.

Cultural Facilities | Jul 16, 2015

Louisville group plans to build world's largest disco ball

The sphere would more than double the size of the current record holder.

Education Facilities | Jul 14, 2015

Chile selects architects for Subantarctic research center

Promoting ecological tourism is one of this facility’s goals

BIM and Information Technology | Jul 14, 2015

New city-modeling software quantifies the movement of urban dwellers

UNA for Rhino 3D helps determine the impact that urban design can have on where pedestrians go.

Industrial Facilities | Jul 14, 2015

Tesla may seek to double size of Gigafactory in Nevada

Tesla Motors purchased an additional 1,200 acres next to the Gigafactory and is looking to buy an additional 350 acres. 

BIM and Information Technology | Jul 14, 2015

Nation’s first 'drone park' breaks ground in North Dakota

This is one of six testing sites around the country that are developing flight standards and evaluating the utility of drones for different tasks. 

Sponsored | Building Team | Jul 10, 2015

Are you the wrong type of ‘engaged’ leader?

Much of what’s written about employee engagement focuses on how leaders can help their employees become more involved at work. But what about the leaders themselves? 

Architects | Jul 9, 2015

NCARB: Record number of aspiring architects on path toward licensure

More than 37,170 design professionals either reported hours through the Intern Development Program or tested for the Architect Registration Examination last year, according to a new NCARB report.

Architects | Jul 7, 2015

Why AEC firms should be cultivating 'visible experts'

A new study pinpoints the true dollar value of having knowledge leaders and market shapers on your team.

boombox1
boombox2
native1

More In Category




Museums

The Tampa Museum of Art will soon undergo a $110 million expansion

In Tampa, Fla., the Tampa Museum of Art will soon undergo a 77,904-sf Centennial Expansion project. The museum plans to reach its $110 million fundraising goal by late 2024 or early 2025 and then break ground. Designed by Weiss/Manfredi, and with construction manager The Beck Group, the expansion will redefine the museum’s surrounding site.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021