Structural engineering innovations were at the heart of a repositioning of the landmark 75 Rockefeller Plaza, former home of the Standard Oil Company. The project involved revitalizing the building’s façade and base metalwork, enhancing its lobby and retail spaces, and overhauling its mechanical systems and infrastructure.
To make way for new ground-floor retail and a more dramatic entrance and lobby, the team removed four columns at the ground floor, three of which supported existing transfer girders. When traditional approaches for transferring weight to accommodate the column removal proved too bulky and costly, the team adapted a structural approach common in bridge design: a composite-steel box girder. The solution met performance requirements and also coordinated with the planned sculpted lobby ceiling, which required the transfer members to be narrow and shallow.
Other innovations included the development of a unique “yolk” system, using 500-ton jacks, to preload a new steel box girder without the need for a temporary structure or shoring.
Project Summary
Honorable Mention
Building Team: Gilsanz Murray Steficek (submitting firm, SE) RXR Realty (developer, program manager) Kohn Pedersen Fox (architect) Robert Derector Associates (MEP) Orange County Ironworks (steel erector).
Details: 650,000 sf. Total cost: $150 million. Construction time: January 2013 to February 2017 Delivery method Design-bid-build.
SEE ALL OF THE 2017 RECONSTRUCTION AWARD WINNERS HERE
Related Stories
Reconstruction Awards | Nov 11, 2019
Woolworth Tower Residences: What a view!
The one-time tallest building in the world is now home to an exclusive residential clientele.
Reconstruction Awards | Nov 8, 2019
2019 Reconstruction Awards: The 1060 Project at Wrigley Field
Venerable Wrigley Field is raised up in a top-to-bottom restoration that took five years to complete.
Reconstruction Awards | Nov 6, 2019
2019 Reconstruction Awards: Betting on a city's future
Can a new resort and casino pump life into a city once renowned as the nation’s arms maker?
Reconstruction Awards | Dec 4, 2018
BD+C's 2018 Reconstruction Award Winners
Cincinnati Music Hall, MASS MoCA Building 6, and 20 Times Square are just a few of the projects recognized as 2018 Reconstruction Award winners.
Reconstruction Awards | Dec 3, 2018
2018 Reconstruction Awards: Honorable mentions
These four projects won honorable mentions in BD+C's 2018 Reconstruction Awards.
Reconstruction Awards | Dec 3, 2018
Elgin Tower: Elgin's heart beats again
A project team brings this Chicago suburb’s landmark tower back to life.
Reconstruction Awards | Nov 30, 2018
Hawaiian Dredging Construction Company Building: GC to the rescue
Hawaii’s largest contractor saves one of the state’s prized architectural landmarks—and now calls it home.
Reconstruction Awards | Nov 30, 2018
5 Beekman Hotel and Residences: Back in business
A landmark office tower becomes one of N.Y.’s hottest lifestyle hotel destinations.
Reconstruction Awards | Nov 29, 2018
700 Constitution: Healthy living
Hospital turned apartment brings luxury living to a D.C. neighborhood – and saves a valued piece of architecture.
Reconstruction Awards | Nov 28, 2018
IBEW Local 134 Union Hall: Union lights a 'beacon'
Electrical workers’ local converts an abandoned Chicago school into a brightly lit union hall.