Richmond CenterStage, Richmond, Va.

Richmond CenterStage, Richmond, Va.


By By Jay W. Schneider, Editor | October 12, 2010

The Richmond CenterStage opened in 1928 in the Virginia capital as a grand movie palace named Loew’s Theatre. It was reinvented in 1983 as a performing arts center known as Carpenter Theatre and hobbled along until 2004, when the crumbling venue was mercifully shuttered. There were plans for a comprehensive historic restoration but the funding never materialized.

The complex was finally started on its path toward restoration in 2007, when the Richmond CenterStage Foundation secured the $62.2 million necessary to finance the rehab. 

With the Building Team of Wilson Butler Architects and Gilbane/Christman (CM) at the helm, the 148,245-sf historic theater wasn’t simply restored: It was reimagined, enlarged, and upgraded. The new 179,000-sf complex became home to four venues:

• Carpenter Theatre: the fully restored, original 1,760-seat auditorium with enlarged stage and an expanded lobby area.

• Gottwald Playhouse: a 200-seat black box theater.

• Genworth BrightLights Education Center: a training space for aspiring thespians.

• Rhythm Hall: a multipurpose venue. 

The building’s extra square footage came from annexing the former six-story Thalhimers Department Store (circa 1939) adjacent to the theater, demolishing parts of the building, and gutting the remainder. The former retail space was transformed into the additional performance and education venues, offices, dressing rooms, and other support spaces.

The conjoined buildings featured a variety of exterior materials, notably brick, terra cotta, and limestone, all in need of attention. The façades were repaired, two new curtain walls were installed in portions of the complex, and new windows and storefront systems were added along one side. Inside, modern acoustical, lighting, rigging, and building system improvements were installed.

The project reopened in September 2009 and became what Walker C. Johnson, FAIA, principal at Johnson Lasky Architects, Chicago, and honorary chair of BD+C’s Reconstruction Awards panel, called “a real sparkler in downtown Richmond.” BD+C

PROJECT SUMMARY

Building Team

Submitting firm: Gilbane/Christman (CM)

Owner/developer: City of Richmond

Architect: Wilson Butler Architects

MEP engineer: Girard Engineering

Structural engineer: Dunbar, Milby, Williams, Pittman and Vaughan

General Information

Size: 179,000 gsf

Construction cost: $62.2 million

Construction period: June 2007 to September 2009

Delivery method: CM at risk

Related Stories

| Mar 5, 2012

Perkins Eastman pegs O’Donnell to lead K-12 practice

O’Donnell will continue the leadership and tradition of creative design established by firm Chairman and CEO Bradford Perkins FAIA, MRAIC, AICP in leading this market sector across the firm’s 13 offices domestically and internationally.

| Mar 5, 2012

Moody+Nolan designs sustainable fire station in Cincinnati

Cincinnati fire station achieves LEED Gold certification.

| Mar 5, 2012

Gilbane Building Co. wins top honors at ASA Houston awards ceremony

Gilbane was also named General Contractor of the Year for the seventh time in 11 years and won the inaugural Safety Program of the Year award.

| Mar 5, 2012

Franklin Institute in Philadelphia selects Skanska to construct new pavilion

The building has been designed by SaylorGregg Architects and will apply for LEED Silver certification.

| Mar 2, 2012

By the Numbers

66 skyscrapers to built in China over six years; 1,000 questions in the Modern Architecture game; 21,000 new jobs. 

| Mar 1, 2012

Intelligent construction photography, not just pretty pictures

Our expert tells how to organize construction progress photos so you don’t lose track of all the valuable information they contain.

| Mar 1, 2012

AIA: A clear difference, new developments in load-bearing glass

Earn 1.0 AIA/CES learning units by studying this article and successfully completing the online exam.

| Mar 1, 2012

8 tips for architects to consider before LED installation

Lighting experts offer Building Team members critical information to consider before upgrading lighting systems to LEDs.

| Mar 1, 2012

Reconstruction Awards: Reinvesting in a neighborhood’s future

The reconstruction of a near-century-old derelict public works facility in Minneapolis earns LEED Platinum—and the hearts and minds of the neighboring community.

boombox1
boombox2
native1

More In Category




Museums

UT Dallas opens Morphosis-designed Crow Museum of Asian Art

In Richardson, Tex., the University of Texas at Dallas has opened a second location for the Crow Museum of Asian Art—the first of multiple buildings that will be part of a 12-acre cultural district. When completed, the arts and performance complex, called the Edith and Peter O’Donnell Jr. Athenaeum, will include two museums, a performance hall and music building, a grand plaza, and a dedicated parking structure on the Richardson campus.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021