Richmond CenterStage, Richmond, Va.

Richmond CenterStage, Richmond, Va.


By By Jay W. Schneider, Editor | October 12, 2010

The Richmond CenterStage opened in 1928 in the Virginia capital as a grand movie palace named Loew’s Theatre. It was reinvented in 1983 as a performing arts center known as Carpenter Theatre and hobbled along until 2004, when the crumbling venue was mercifully shuttered. There were plans for a comprehensive historic restoration but the funding never materialized.

The complex was finally started on its path toward restoration in 2007, when the Richmond CenterStage Foundation secured the $62.2 million necessary to finance the rehab. 

With the Building Team of Wilson Butler Architects and Gilbane/Christman (CM) at the helm, the 148,245-sf historic theater wasn’t simply restored: It was reimagined, enlarged, and upgraded. The new 179,000-sf complex became home to four venues:

• Carpenter Theatre: the fully restored, original 1,760-seat auditorium with enlarged stage and an expanded lobby area.

• Gottwald Playhouse: a 200-seat black box theater.

• Genworth BrightLights Education Center: a training space for aspiring thespians.

• Rhythm Hall: a multipurpose venue. 

The building’s extra square footage came from annexing the former six-story Thalhimers Department Store (circa 1939) adjacent to the theater, demolishing parts of the building, and gutting the remainder. The former retail space was transformed into the additional performance and education venues, offices, dressing rooms, and other support spaces.

The conjoined buildings featured a variety of exterior materials, notably brick, terra cotta, and limestone, all in need of attention. The façades were repaired, two new curtain walls were installed in portions of the complex, and new windows and storefront systems were added along one side. Inside, modern acoustical, lighting, rigging, and building system improvements were installed.

The project reopened in September 2009 and became what Walker C. Johnson, FAIA, principal at Johnson Lasky Architects, Chicago, and honorary chair of BD+C’s Reconstruction Awards panel, called “a real sparkler in downtown Richmond.” BD+C

PROJECT SUMMARY

Building Team

Submitting firm: Gilbane/Christman (CM)

Owner/developer: City of Richmond

Architect: Wilson Butler Architects

MEP engineer: Girard Engineering

Structural engineer: Dunbar, Milby, Williams, Pittman and Vaughan

General Information

Size: 179,000 gsf

Construction cost: $62.2 million

Construction period: June 2007 to September 2009

Delivery method: CM at risk

Related Stories

Architects | May 9, 2017

Spiezle Architectural Group looks to the future

Now in its seventh decade, the firm expands its portfolio and moves into a larger HQs.

Architects | May 9, 2017

Movers + Shapers: The social connector

Studio Gang gains fans with buildings that unite people and embrace the outside world.

Architects | May 5, 2017

An acquisition extends Eppstein Uhen Architects’ national footprint

Has architects in 35 states after acquiring Burkettdesign in Denver.

Great Solutions | May 5, 2017

No nails necessary: Framing system comes together with steel zip ties and screws

Clemson University’s School of Architecture develops a patent-pending construction method that is gaining attention for its potential use in rapid, low-tech sustainable housing.

Multifamily Housing | May 3, 2017

Silicon Valley’s high-tech oasis

An award-winning rental complex takes its design cues from its historic location in Silicon Valley.

Architects | May 3, 2017

Avoiding trouble in paradise: Tips on building successfully in the Caribbean

The island setting itself is at the root of several of these disruptive assumptions.

Multifamily Housing | May 2, 2017

Multifamily housing: 7 exciting, inspiring innovations [AIA Course]

This AIA CES course features seven novel approaches developers and Building Teams are taking to respond to competitive pressures and build more quickly and with more attractive offerings.

Healthcare Facilities | May 1, 2017

Designing patient rooms for the entire family can improve patient satisfaction and outcomes

Hospital rooms are often not designed to accommodate extended stays for anyone other than the patient, which can have negative effects on patient outcome.

Architects | Apr 27, 2017

Number of U.S. architects holds steady, while professional mobility increases

New data from NCARB reveals that while the number of architects remains consistent, practitioners are looking to get licensed in multiple states.

boombox1
boombox2
native1

More In Category


Museums

The Tampa Museum of Art will soon undergo a $110 million expansion

In Tampa, Fla., the Tampa Museum of Art will soon undergo a 77,904-sf Centennial Expansion project. The museum plans to reach its $110 million fundraising goal by late 2024 or early 2025 and then break ground. Designed by Weiss/Manfredi, and with construction manager The Beck Group, the expansion will redefine the museum’s surrounding site.



Reconstruction & Renovation

Movement to protect historic buildings raises sharp criticism

While the movement to preserve historic buildings has widespread support, it also has some sharp critics with well-funded opposition groups springing up in recent years. Some opponents are linked to the Stand Together Foundation, founded and bankrolled by the Koch family’s conservative philanthropic organization, according to a column in Governing magazine.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021