Richmond CenterStage, Richmond, Va.

Richmond CenterStage, Richmond, Va.


By By Jay W. Schneider, Editor | October 12, 2010

The Richmond CenterStage opened in 1928 in the Virginia capital as a grand movie palace named Loew’s Theatre. It was reinvented in 1983 as a performing arts center known as Carpenter Theatre and hobbled along until 2004, when the crumbling venue was mercifully shuttered. There were plans for a comprehensive historic restoration but the funding never materialized.

The complex was finally started on its path toward restoration in 2007, when the Richmond CenterStage Foundation secured the $62.2 million necessary to finance the rehab. 

With the Building Team of Wilson Butler Architects and Gilbane/Christman (CM) at the helm, the 148,245-sf historic theater wasn’t simply restored: It was reimagined, enlarged, and upgraded. The new 179,000-sf complex became home to four venues:

• Carpenter Theatre: the fully restored, original 1,760-seat auditorium with enlarged stage and an expanded lobby area.

• Gottwald Playhouse: a 200-seat black box theater.

• Genworth BrightLights Education Center: a training space for aspiring thespians.

• Rhythm Hall: a multipurpose venue. 

The building’s extra square footage came from annexing the former six-story Thalhimers Department Store (circa 1939) adjacent to the theater, demolishing parts of the building, and gutting the remainder. The former retail space was transformed into the additional performance and education venues, offices, dressing rooms, and other support spaces.

The conjoined buildings featured a variety of exterior materials, notably brick, terra cotta, and limestone, all in need of attention. The façades were repaired, two new curtain walls were installed in portions of the complex, and new windows and storefront systems were added along one side. Inside, modern acoustical, lighting, rigging, and building system improvements were installed.

The project reopened in September 2009 and became what Walker C. Johnson, FAIA, principal at Johnson Lasky Architects, Chicago, and honorary chair of BD+C’s Reconstruction Awards panel, called “a real sparkler in downtown Richmond.” BD+C

PROJECT SUMMARY

Building Team

Submitting firm: Gilbane/Christman (CM)

Owner/developer: City of Richmond

Architect: Wilson Butler Architects

MEP engineer: Girard Engineering

Structural engineer: Dunbar, Milby, Williams, Pittman and Vaughan

General Information

Size: 179,000 gsf

Construction cost: $62.2 million

Construction period: June 2007 to September 2009

Delivery method: CM at risk

Related Stories

Codes and Standards | Aug 3, 2022

Some climate models underestimate risk of future floods

Commonly used climate models may be significantly underestimating the risk of floods this century, according to a new study by Yale researchers.

| Aug 3, 2022

Designing learning environments to support the future of equitable health care

While the shortage of rural health care practitioners was a concern before the COVID-19 pandemic, the public health crisis has highlighted the importance of health equity in the United States and the desperate need for practitioners help meet the needs of patients in vulnerable rural communities.

Reconstruction & Renovation | Aug 3, 2022

Chicago proposes three options for Soldier Field renovation including domed stadium

The City of Chicago recently announced design concepts for renovations to Soldier Field, the home of the NFL’s Chicago Bears.

Codes and Standards | Aug 2, 2022

New tools help LEED projects reach health goals

The U.S. Green Building Council now offers tools to support the LEED Integrative Process for Health Promotion (IPHP) pilot credit.

Market Data | Aug 2, 2022

Nonresidential construction spending falls 0.5% in June, says ABC

National nonresidential construction spending was down by 0.5% in June, according to an Associated Builders and Contractors analysis of data published today by the U.S. Census Bureau.

K-12 Schools | Aug 1, 2022

Achieving a net-zero K-12 facility is a team effort

Designing a net-zero energy building is always a challenge, but renovating an existing school and applying for grants to make the project happen is another challenge entirely.

Healthcare Facilities | Aug 1, 2022

New Phoenix VA outpatient clinic is one of the largest veteran care facilities in the U.S.

The new Phoenix 32nd Street VA Clinic, spanning roughly 275,000 sf over 15 acres, is one of the largest veteran care facilities in the U.S.

Codes and Standards | Jul 29, 2022

Few projects and properties are being built beyond code

Clients and architects disagree on how well building to code provides resilience, according to a recent report by the American Institute of Architects (AIA) in partnership with Owens Corning.

Headquarters | Jul 29, 2022

Nike HQ’s newest, largest structure: the Serena Williams Building

In Beaverton, Ore., the new Serena Williams Building, at just over 1 million square feet, is the largest structure at Nike World Headquarters.

| Jul 28, 2022

Fanning Howey hires Dennis Bane, AIA, as Project Executive

Fanning Howey, an architecture, interiors and engineering firm specializing in learning environments, has hired Dennis Bane, AIA, ALEP, to serve as a Project Executive for the firm’s Indianapolis office.

boombox1
boombox2
native1

More In Category

Warehouses

California bill would limit where distribution centers can be built

A bill that passed the California legislature would limit where distribution centers can be located and impose other rules aimed at reducing air pollution and traffic. Assembly Bill 98 would tighten building standards for new warehouses and ban heavy diesel truck traffic next to sensitive sites including homes, schools, parks and nursing homes.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021