Removable flood prevention system installed in one of New York City's largest office buildings

Removable flood prevention system installed in one of New York City's largest office buildings

55 Water Street is a virtual city unto itself, with enough excess power to support tenants for multiple days 


By Plaza Construction | March 31, 2014
Directly following Hurricane Sandy in October 2012, Plaza Construction was asked to start working on the development of a flood prevention solution for 55 Water Street, one of New York City’s largest office structures with 54 stories and 3.8 million square feet located in the financial district.  Hurricane Sandy was the second-costliest storm in U.S. history, with damages to New York City estimated at $50 billion due to storm surges flooding streets, tunnels and subway lines and cutting power in and around the city.
 
Plaza Construction, with a team of experts consisting of EKO Flood USA, architect HLW International, and engineer Thornton Tomasetti, along with New Water Street Corporation, the owner/operator of 55 Water Street managed the planning, design and permitting stages to produce the first permitted flood protection system for 55 Water Street. 
 
The new flood barrier protection system installed at 55 Water Street is designed to protect against an eight-foot flood line, higher than the 7-1/2 foot flood line recommended by FEMA to protect against storm surges for the next hundred years. The building was designed by renowned architect Emory Roth and the flood barrier protection system had to fit with the aesthetics of the building. Basically, it had to be invisible to the occupants and visitors of the building.
 
“Plaza was contracted by New Water Street Corporation to help them develop a flood protection system to guard against future storm surges that continue to be a major threat to the infrastructure of New York City and its neighboring communities,” said Richard Wood, CEO, Plaza Construction.  “Together with our partners, we created a simple, fast and easy solution in a modular set up, take down and store removable barrier flood protection system that is tested to withstand an 8-foot flood line.”
 
“The new flood protection system at 55 Water Street is designed to protect the entire building from flooding,” said George Acero, Executive Vice President, New Water Street Corporation. “For efficient preparedness, the building management plans to conduct drills on erecting and breaking down the system on an annual basis.”
 
The flood barrier system at 55 Water Street is based on a removable post and panel flood protection system that easily adapts to the requirements of a particular building site. The system at 55 Water Street is stored in the sub-level of the building and will require 30 men and eight hours to assemble into place, and completely protects the entire building against an 8-foot water line, preventing water from entering the building and seeping into the lower levels.
 
“The advanced design of the EKO system is new to the tri-state region, as we were presenting a unique concept for storm protection,” said Yu-chi Yang, the Project Architect at HLW International. “The final design resulted in a very comprehensive set of guidelines for reviewing similar proposals in the future.”
 
According to the Aine Brazil, Vice Chairman at Thornton Tomasetti, “The integration of the flood barrier system with the existing foundation wall was one key to the economic and practical feasibility, minimizing new foundations in the sidewalk, and providing the necessary continuity of the flood proofed bathtub as an extension of the existing 60 foot deep basement.”
 
Located in downtown Manhattan, 55 Water Street is a virtual city unto itself that provides a fail-safe operating environment. Powerful systems support massive capacities instilling confidence that any crisis can be readily addressed. An extraordinarily advanced technological infrastructure includes multiple redundancies in every major operating system from electric, HVAC, and telecom to life safety and security. Tenants can also avail themselves of sufficient excess power to operate without interruption for multiple days should an emergency situation arise. 
 
“Now with the installation of a removable, flood barrier protection system, 55 Water Street offers added protection in terms of guarding the building against flooding,” adds Mr. Acero.

Related Stories

University Buildings | May 17, 2023

New UC Irvine health sciences building supports aim to become national model for integrative health

The new College of Health Sciences Building and Nursing & Health Sciences Hall at the University of California Irvine supports the institution’s goal of becoming a national model for integrative health. The new 211,660-sf facility houses nursing, medical doctorate, pharmacy, philosophy, and public health programs in a single building.

Sponsored | Building Enclosure Systems | May 16, 2023

4 steps to a better building enclosure

Dividing the outside environment from the interior, the building enclosure is one of the most important parts of the structure. The enclosure not only defines the building’s aesthetic, but also protects occupants from the elements and facilitates a comfortable, controlled climate. With dozens of components comprising the exterior assemblies, from foundation to cladding to roof, figuring out which concerns to address first can be daunting.

Multifamily Housing | May 16, 2023

Legislators aim to make office-to-housing conversions easier

Lawmakers around the country are looking for ways to spur conversions of office space to residential use.cSuch projects come with challenges such as inadequate plumbing, not enough exterior-facing windows, and footprints that don’t easily lend themselves to residential use. These conditions raise the cost for developers.

Office Buildings | May 15, 2023

Sixteen-story office tower will use 40% less energy than an average NYC office building

This month marks the completion of a new 16-story office tower that is being promoted as New York City’s most sustainable office structure. That boast is backed by an innovative HVAC system that features geothermal wells, dedicated outdoor air system (DOAS) units, radiant heating and cooling, and a sophisticated control system to ensure that the elements work optimally together.

K-12 Schools | May 12, 2023

In Virginia, a new high school building helps reimagine the experience for 1,600 students

In Virginia, the City of Alexandria recently celebrated the topping out of a new building for Alexandria City High School. When complete in 2025, the high-performance structure will accommodate 1,600 students. 

University Buildings | May 11, 2023

New ‘bold and twisting’ building consolidates School of Continuing Studies at York University

The design of a new building that consolidates York University’s School of Continuing Studies into one location is a new architectural landmark at the Toronto school’s Keele Campus. “The design is emblematic of the school’s identity and culture, which is centered around accelerated professional growth in the face of a continuously evolving labor market,” according to a news release from Perkins&Will.

Hotel Facilities | May 9, 2023

A new camping destination near Utah’s Zion National Park offers a variety of all-season lodgings and amenities

Outdoor lodging brand AutoCamp has opened a new camping destination near Utah’s Zion National Park. A 16-acre property, AutoCamp Zion is located between the Virgin River and the desert of Southern Utah.

Headquarters | May 9, 2023

New Wells Fargo development in Texas will be bank’s first net-positive campus

A new Wells Fargo development in the Dallas metroplex will be the national bank’s first net-positive campus, expected to generate more energy than it uses. The 850,000-sf project on 22 acres will generate power from solar panels and provide electric vehicle charging stations.

Regulations | May 8, 2023

Supreme Court case likely to have huge impact on Clean Water Act

A case before the Supreme Court will likely determine how the Clean Water Act is interpreted and the ruling could open up new areas for development within or adjacent to wetlands.

Senior Living Design | May 8, 2023

Seattle senior living community aims to be world’s first to achieve Living Building Challenge designation

Aegis Living Lake Union in Seattle is the world’s first assisted living community designed to meet the rigorous Living Building Challenge certification. Completed in 2022, the Ankrom Moisan-designed, 70,000 sf-building is fully electrified. All commercial dryers, domestic hot water, and kitchen equipment are powered by electricity in lieu of gas, which reduces the facility’s carbon footprint.

boombox1
boombox2
native1

More In Category


Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.



halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021