Removable flood prevention system installed in one of New York City's largest office buildings

Removable flood prevention system installed in one of New York City's largest office buildings

55 Water Street is a virtual city unto itself, with enough excess power to support tenants for multiple days 


By Plaza Construction | March 31, 2014
Directly following Hurricane Sandy in October 2012, Plaza Construction was asked to start working on the development of a flood prevention solution for 55 Water Street, one of New York City’s largest office structures with 54 stories and 3.8 million square feet located in the financial district.  Hurricane Sandy was the second-costliest storm in U.S. history, with damages to New York City estimated at $50 billion due to storm surges flooding streets, tunnels and subway lines and cutting power in and around the city.
 
Plaza Construction, with a team of experts consisting of EKO Flood USA, architect HLW International, and engineer Thornton Tomasetti, along with New Water Street Corporation, the owner/operator of 55 Water Street managed the planning, design and permitting stages to produce the first permitted flood protection system for 55 Water Street. 
 
The new flood barrier protection system installed at 55 Water Street is designed to protect against an eight-foot flood line, higher than the 7-1/2 foot flood line recommended by FEMA to protect against storm surges for the next hundred years. The building was designed by renowned architect Emory Roth and the flood barrier protection system had to fit with the aesthetics of the building. Basically, it had to be invisible to the occupants and visitors of the building.
 
“Plaza was contracted by New Water Street Corporation to help them develop a flood protection system to guard against future storm surges that continue to be a major threat to the infrastructure of New York City and its neighboring communities,” said Richard Wood, CEO, Plaza Construction.  “Together with our partners, we created a simple, fast and easy solution in a modular set up, take down and store removable barrier flood protection system that is tested to withstand an 8-foot flood line.”
 
“The new flood protection system at 55 Water Street is designed to protect the entire building from flooding,” said George Acero, Executive Vice President, New Water Street Corporation. “For efficient preparedness, the building management plans to conduct drills on erecting and breaking down the system on an annual basis.”
 
The flood barrier system at 55 Water Street is based on a removable post and panel flood protection system that easily adapts to the requirements of a particular building site. The system at 55 Water Street is stored in the sub-level of the building and will require 30 men and eight hours to assemble into place, and completely protects the entire building against an 8-foot water line, preventing water from entering the building and seeping into the lower levels.
 
“The advanced design of the EKO system is new to the tri-state region, as we were presenting a unique concept for storm protection,” said Yu-chi Yang, the Project Architect at HLW International. “The final design resulted in a very comprehensive set of guidelines for reviewing similar proposals in the future.”
 
According to the Aine Brazil, Vice Chairman at Thornton Tomasetti, “The integration of the flood barrier system with the existing foundation wall was one key to the economic and practical feasibility, minimizing new foundations in the sidewalk, and providing the necessary continuity of the flood proofed bathtub as an extension of the existing 60 foot deep basement.”
 
Located in downtown Manhattan, 55 Water Street is a virtual city unto itself that provides a fail-safe operating environment. Powerful systems support massive capacities instilling confidence that any crisis can be readily addressed. An extraordinarily advanced technological infrastructure includes multiple redundancies in every major operating system from electric, HVAC, and telecom to life safety and security. Tenants can also avail themselves of sufficient excess power to operate without interruption for multiple days should an emergency situation arise. 
 
“Now with the installation of a removable, flood barrier protection system, 55 Water Street offers added protection in terms of guarding the building against flooding,” adds Mr. Acero.

Related Stories

| Jun 19, 2014

First look: JDS Architects' roller-coaster-like design for Istanbul waterfront development

The development's wavy and groovy design promises unobstructed views of the Marmara Sea for every unit.

| Jun 19, 2014

Singapore's 'Tree House' vertical gardens break Guinness World Record

The high-rise development will have a 24,638-sf vertical garden, breaking a Guinness World Record.

| Jun 18, 2014

Design tips for Alzheimer care facilities

A new white paper from the Alzheimer’s Foundation of America and Perkins Eastman details best design practices for residential care settings for individuals living with Alzheimer’s disease. 

| Jun 18, 2014

Largest Passive House structure in the U.S. to be built in Oregon

Orchards at Orenco, a 57-unit affordable housing complex in Hillsboro, Oregon, is the first of a three-phase, three-building complex.

| Jun 18, 2014

SOM's twisting tower wins design competition for Sweden's tallest skyscraper

The skyscraper, which will reach 230 meters and is named Polstjärnan, or "The Pole Star," is to be built in Gothenburg, Sweden. 

| Jun 18, 2014

Study shows walkable urbanism has positive economic impact

Walkable communities have a higher GDP, greater wealth, and higher percentages of college grads, according to a new study by George Washington University.

| Jun 18, 2014

Ware Malcomb names Sorensen Engineering Regional Manager

New hire will oversee firm's civil engineering practice in Los Angeles, San Diego, and Irvine.

| Jun 18, 2014

Arup uses 3D printing to fabricate one-of-a-kind structural steel components

The firm's research shows that 3D printing has the potential to reduce costs, cut waste, and slash the carbon footprint of the construction sector.

| Jun 18, 2014

Architecture Billings Index shows increase in design activity

The American Institute of Architects reported that the May ABI score was 52.6, up sharply from a mark of 49.6 in April. This score reflects an increase in design activity.

| Jun 17, 2014

Must see: If music were architecture in 27 illustrations

From Miles Davis to Björk to Manu Chao to Bach, Babina visualizes how these sounds will look like if they were visible in the form of architecture.

boombox1
boombox2
native1

More In Category


Construction Costs

Data center construction costs for 2024

Gordian’s data features more than 100 building models, including computer data centers. These localized models allow architects, engineers, and other preconstruction professionals to quickly and accurately create conceptual estimates for future builds. This table shows a five-year view of costs per square foot for one-story computer data centers. 


Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.


halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021