Removable flood prevention system installed in one of New York City's largest office buildings

Removable flood prevention system installed in one of New York City's largest office buildings

55 Water Street is a virtual city unto itself, with enough excess power to support tenants for multiple days 


By Plaza Construction | March 31, 2014
Directly following Hurricane Sandy in October 2012, Plaza Construction was asked to start working on the development of a flood prevention solution for 55 Water Street, one of New York City’s largest office structures with 54 stories and 3.8 million square feet located in the financial district.  Hurricane Sandy was the second-costliest storm in U.S. history, with damages to New York City estimated at $50 billion due to storm surges flooding streets, tunnels and subway lines and cutting power in and around the city.
 
Plaza Construction, with a team of experts consisting of EKO Flood USA, architect HLW International, and engineer Thornton Tomasetti, along with New Water Street Corporation, the owner/operator of 55 Water Street managed the planning, design and permitting stages to produce the first permitted flood protection system for 55 Water Street. 
 
The new flood barrier protection system installed at 55 Water Street is designed to protect against an eight-foot flood line, higher than the 7-1/2 foot flood line recommended by FEMA to protect against storm surges for the next hundred years. The building was designed by renowned architect Emory Roth and the flood barrier protection system had to fit with the aesthetics of the building. Basically, it had to be invisible to the occupants and visitors of the building.
 
“Plaza was contracted by New Water Street Corporation to help them develop a flood protection system to guard against future storm surges that continue to be a major threat to the infrastructure of New York City and its neighboring communities,” said Richard Wood, CEO, Plaza Construction.  “Together with our partners, we created a simple, fast and easy solution in a modular set up, take down and store removable barrier flood protection system that is tested to withstand an 8-foot flood line.”
 
“The new flood protection system at 55 Water Street is designed to protect the entire building from flooding,” said George Acero, Executive Vice President, New Water Street Corporation. “For efficient preparedness, the building management plans to conduct drills on erecting and breaking down the system on an annual basis.”
 
The flood barrier system at 55 Water Street is based on a removable post and panel flood protection system that easily adapts to the requirements of a particular building site. The system at 55 Water Street is stored in the sub-level of the building and will require 30 men and eight hours to assemble into place, and completely protects the entire building against an 8-foot water line, preventing water from entering the building and seeping into the lower levels.
 
“The advanced design of the EKO system is new to the tri-state region, as we were presenting a unique concept for storm protection,” said Yu-chi Yang, the Project Architect at HLW International. “The final design resulted in a very comprehensive set of guidelines for reviewing similar proposals in the future.”
 
According to the Aine Brazil, Vice Chairman at Thornton Tomasetti, “The integration of the flood barrier system with the existing foundation wall was one key to the economic and practical feasibility, minimizing new foundations in the sidewalk, and providing the necessary continuity of the flood proofed bathtub as an extension of the existing 60 foot deep basement.”
 
Located in downtown Manhattan, 55 Water Street is a virtual city unto itself that provides a fail-safe operating environment. Powerful systems support massive capacities instilling confidence that any crisis can be readily addressed. An extraordinarily advanced technological infrastructure includes multiple redundancies in every major operating system from electric, HVAC, and telecom to life safety and security. Tenants can also avail themselves of sufficient excess power to operate without interruption for multiple days should an emergency situation arise. 
 
“Now with the installation of a removable, flood barrier protection system, 55 Water Street offers added protection in terms of guarding the building against flooding,” adds Mr. Acero.

Related Stories

Cultural Facilities | Jun 2, 2015

Snøhetta and Dialog to revitalize Willamette Falls area in Oregon

As part of the plan, an abandoned paper mill will be repurposed, while landscaping and running trails will be added.

Contractors | Jun 1, 2015

Nonresidential construction spending surges in April

Nonresidential construction is up by a solid 8.8% over the past year, consistent with ABC's forecast of high single-digit growth.

Office Buildings | Jun 1, 2015

Can you make a new building as cool as a warehouse?

Just as we looked at that boarded up warehouse and thought it could be something other, office towers can be reborn, writes CannonDesign's Robert Benson.

Fire and Life Safety | May 27, 2015

7 bold applications and innovations for fire and life safety

BD+C’s roundup features colorful sprinklers for offices, hotels, museums; a fire-rated curtain wall at a transit hub in Manhattan; a combination CO/smoke detector; and more.

BIM and Information Technology | May 27, 2015

4 projects honored with AIA TAP Innovation Awards for excellence in BIM and project delivery

Morphosis Architects' Emerson College building in Los Angeles and the University of Delaware’s ISE Lab are among the projects honored by AIA for their use of BIM/VDC tools.

Healthcare Facilities | May 27, 2015

Rochester, Minn., looks to escape Twin Cities’ shadow with $6.5 billion biotech development

The 20-year plan would also be a boon to Mayo Clinic, this city’s best-known address.

BIM and Information Technology | May 21, 2015

How AEC firms should approach BIM training

CASE Founding Partner Steve Sanderson talks about the current state of software training in the AEC industry and common pitfalls in AEC training.

Architects | May 20, 2015

Architecture billings remain stuck in winter slowdown

Regional business conditions continue to thrive in the South and West

University Buildings | May 19, 2015

Special Report: How your firm can help struggling colleges and universities meet their building project goals

Building Teams that want to succeed in the higher education market have to help their clients find new funding sources, control costs, and provide the maximum value for every dollar.

University Buildings | May 19, 2015

Renovate or build new: How to resolve the eternal question

With capital budgets strained, renovation may be an increasingly attractive money-saving option for many college and universities. 

boombox1
boombox2
native1

More In Category


Construction Costs

Data center construction costs for 2024

Gordian’s data features more than 100 building models, including computer data centers. These localized models allow architects, engineers, and other preconstruction professionals to quickly and accurately create conceptual estimates for future builds. This table shows a five-year view of costs per square foot for one-story computer data centers. 


Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.


halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021