Reconstruction Awards: Reinvesting in a neighborhood’s future

Reconstruction Awards: Reinvesting in a neighborhood’s future

The reconstruction of a near-century-old derelict public works facility in Minneapolis earns LEED Platinum—and the hearts and minds of the neighboring community.


By By Leslie Streicher, Associate Editor | March 1, 2012
The buildings rugged history of service is captured in the reused building mate
The buildings rugged history of service is captured in the reused building materials from the original structure. Bricks, timbe
This article first appeared in the March 2012 issue of BD+C.

Noise, odor, and visual pollution don’t usually come to mind when picturing a pleasant residential neighborhood in the Land of 10,000 Lakes. But for a tight-knit community in Minneapolis that has abutted the city’s Hiawatha Maintenance Facility for nearly a century, pollution in many forms was a daily reality.

The public works site was “a real eyesore,” said Marc Partridge, AIA, CID, LEED AP, a senior associate at local design firm RSP Architects. According to Steve Maurelli, a project manager at RSP, the buildings on the 10-acre site were sorely in need of repair and maintenance. The sense of irony—that a facility devoted to maintenance could itself be so ill-kempt—added to the long-simmering tension between the city and the residents of the adjacent neighborhood, who for decades felt that the city was exploiting them by allowing this blot on their visual landscape.

PROJECT SUMMARY
Hiawatha Maintenance Facility, Minneapolis, Minn.
Building Team

  • Owner/developer: City of Minneapolis
  • Architect: RSP Architects (submitting firm)
  • Structural engineer: Palanisami and Associates
  • MEP engineer: Paulson & Clarke Engineering Inc.
  • General contractor: Knutson Construction

General Information

  • Size: 33,0000-sf office space; 28,000-sf maintenance bay, 20,500-sf storage area
  • Construction cost: $10.8 million
  • Completion date: June 2010
  • Delivery method: Design-bid-build

Built in 1914 as a single brick warehouse and garage, the original building served as a horse infirmary for the local fire department. Population growth spurred the city to erect 18 more facilities, and for more than 90 years the Hiawatha facility has been home to the city’s streets and sewers department.

Tearing down the buildings and starting anew would have been a swift, albeit expensive solution, but the city wanted to preserve the rich history of the facility while also paying respect to the sensitivities of its neighbors.

“When we started this project, one of the goals was to recycle and reuse as much as we could,” said Greg Goeke, director of property services for the city of Minneapolis. The city’s Public Works Department has a “rich tradition” of public service, and repurposing the existing facilities was part of preserving that tradition. The result: about 98% of construction demolition waste from the project was reused.

Click here to view profiles of other reconstruction projects that have been recognized as part of BD+C's 28th Annual Reconstruction Awards.

New construction added space where needed without inflating the mass of the original structures. The original brick building was renovated to complement the surrounding community, while industrial materials were stored on the side of the building facing the highway, out of view of the neighbors.

A new circulating glass curtain wall brought light deep into the facility and made the exteriors more aesthetically pleasing. Recycled materials—metal beams, concrete slabs forming an exterior patio, and wood and bricks salvaged from the original blacksmith shop—lent an elegant but still understated feel to the façade.

According to RSP’s Partridge, an important goal of the renovation was to keep the building functional, not precious. “Public works is raw stuff, and we wanted the building to reflect that,” he said. “In terms of maintainability and the honesty of the materials, everything had a purpose. We wanted to make sure the palette was true to the work being done there.”

Effecting cultural change through design

Before the reconstruction began, city workers were isolated in their respective departments in various parts of the building, each group with its own lunchroom, kitchen, and equipment collection—a layout that lent itself to communication breakdowns and resulting inefficiencies.

2011 RECONSTRUCTION AWARD PRODUCT LIST
Hiawatha Maintenance Facility, Minneapolis, Minn.

Structural Steel: MacSteel
Overhead Door Aluminum: Haas
Structural Deck: Vulcraft-Nucor
Corrugated Metal: CMI Inc.
Lockers: The Locker Guy
Precast Concrete: FabCon
Aluminum Storefront Curtainwall: Old Castle
Ready-mix: Cemstone
Hollow Core Planks: Molin
Remix P/6473 Carpet: Milliken
Windows DH: Pella
Aluminum Storefront Entrances and Doors: Old Castle
Light Gauge Metal Items: Clarkwestern
Louvera: Nystrom
Linoleum: Forbo
Metal Stairs: Lapeyer
Una-Clad: C Firestone
VCT Tile: Daltile
Thermal Batt Insulation: Owens Corning
Insulation: Johns Manville
Gypcrete Green 2000: Maxxom
Alucobond: Alcan
Modular Carpet: Lee's Carpet
Gypsum Board: National Gypsum
Flagpoles: Poletech
Vinyle Tile: Daltile
Gymspum Board: USG
Vinyl Tile: Daltile
Tread Riser: Nora
Rubber Base: Roppe
Rubber Tiles: Nora
Translucent Panel: Kalwall
Misc. Metal Shapes: Nucor
Structural Steel Joists: Vulcraft-Nucor
Overhead Steel Doors: DoorLink

The Building Team—which, in addition to RSP Architects, included Palanisami and Associates (structural engineer), Paulson & Clark Engineering (MEP engineer), and Knutson Construction (GC)—set to work with the municipal administration to find ways to maximize workflow by opening up the floor plan. “We did a lot of programming to see what resources and tasks could be shared between groups, and then designed the space so that the groups were thrown together in shared experiences,” said Partridge. 

Today, the Hiawatha facility takes in 33,000 sf of office space over two floors, a 28,000-sf maintenance bay, and 20,500 sf of storage. It is home to five public works departments whose workforce has experienced something of a collective cultural change as a result of the new space adjacencies. “Making the building more open brought everyone together,” said RSP’s Partridge. Daily task work has improved, response times have quickened, and overall functionality has been streamlined.

“They now realize how much more collaborative their work really is,” he said.

A tough building complex that reflects the hardy work being performed inside—this is what the Building Team envisioned. And it works. “On a day-to-day basis, our employees have an environment that works much better for them without compromising [individual departmental] goals,” said the city’s Greg Goeke—and a great justification for the project to earn Gold honors from BD+C’s Reconstruction Awards jury.

EXCEEDING EXPECTATIONS a commitment to the community

During the planning of the Hiawatha Maintenance Facility, a directive from the city of Minneapolis required the Building Team—RSP Architects, Palanisami and Associates (SE), Paulson & Clark Engineering (MEP), and Knutson Construction (GC)—to achieve LEED Gold certification. But with the high level of reused materials—nearly 98%—the team was able to reach even higher.

“Not only does a public works facility need to protect the city, it also needs to protect the environment,” said Greg Goeke, the city’s director of property services. “We have high recycled content that made achieving environmental goals fairly easy.”

Old timber repurposed for millwork, recycled switchboards and crane rails, and salvaged metal beams supporting the site’s fueling station helped earn the project LEED Platinum for new construction, the city’s first municipal building to earn this rating. An old open-grate bridge that used to cross the Mississippi River was converted into a perimeter fence.

Artifacts of the building’s past are now displayed along the walls, paying homage to the building’s nearly century-long history. Old photographs, remnants of an old asphalt plant, and materials from the infirmary were reincorporated into the building construct.

The project’s high level of sustainability demonstrated the city’s commitment to the local community’s welfare, said Goeke. By the end of the process, residents who had started out mistrusting the project became its strongest advocates. “People now see that something built nearly a century ago still has value today,” he said. +

Related Stories

| Aug 11, 2010

Construction Specifications Institute to end support of MasterFormat 95 on December 31, 2009

The Construction Specifications Institute (CSI) announced that the organization will cease to license and support MasterFormat 95 as of December 31, 2009. The CSI Board of Directors voted to stop licensing and supporting MasterFormat 95 during its June 16, 2009, meeting at the CSI Annual Convention in Indianapolis.

| Aug 11, 2010

Gensler among eight teams named finalists in 'classroom of the future' design competition

Eight teams were recognized today as finalists of the 2009 Open Architecture Challenge: Classroom. Finalists submitted designs ranging from an outdoor classroom for children in inner-city Chicago, learning spaces for the children of salt pan workers in India, safe spaces for youth in Bogota, Colombia and a bamboo classroom in the Himalayan mountains.

| Aug 11, 2010

F&S Partners merges with SmithGroup

F&S Partners, a Dallas architecture firm specializing in the design of educational, recreational, and religious projects, has merged with SmithGroup, a top 10 U.S. architecture/engineering firm. The 40-person office in Dallas will carry the name SmithGroup/F&S.

| Aug 11, 2010

Will Alsop to head up new RMJM studio

Will Alsop, the internationally acclaimed British architect and designer of the Glenwood Waterfront project on the Hudson River, is to turn his attention once again to the U.S. after announcing he is to create a studio called “Will Alsop at RMJM,” as part of the RMJM worldwide architectural firm.

| Aug 11, 2010

AECOM, WATG top BD+C's ranking of the nation's 75 largest hotel design firms

A ranking of the Top 75 Hotel Design Firms based on Building Design+Construction's 2009 Giants 300 survey. For more Giants 300 rankings, visit http://www.BDCnetwork.com/Giants

| Aug 11, 2010

Parsons Brinckerhoff, Dewberry among nation's largest multifamily design firms, according to BD+C's Giants 300 report

A ranking of the Top 75 Multifamily Design Firms based on Building Design+Construction's 2009 Giants 300 survey. For more Giants 300 rankings, visit /giants

| Aug 11, 2010

USGBC’s Greenbuild 2009 brings global ideas to local main streets

Save the planet with indigenous knowledge. Make permanent water part of your life. Dive deep water for clues to environmental success.  Connect site selection to successful creative concepting. Explore the unknown with Discovery Channel’s best known guide. These are but a few of the big ideas participants can connect to at USGBC’s Greenbuild International Conference and Expo, taking place on November 11-13, 2009 in Phoenix, Ariz.

boombox1
boombox2
native1

More In Category




Adaptive Reuse

Detroit’s Michigan Central Station, centerpiece of innovation hub, opens

The recently opened Michigan Central Station in Detroit is the centerpiece of a 30-acre technology and cultural hub that will include development of urban transportation solutions. The six-year adaptive reuse project of the 640,000 sf historic station, created by the same architect as New York’s Grand Central Station, is the latest sign of a reinvigorating Detroit.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021