The reconstruction of a near-century-old derelict public works facility in Minneapolis earns LEED Platinum—and the hearts and minds of the neighboring community.


By By Leslie Streicher, Associate Editor | March 1, 2012
The buildings rugged history of service is captured in the reused building mate
The buildings rugged history of service is captured in the reused building materials from the original structure. Bricks, timbe
This article first appeared in the March 2012 issue of BD+C.

Noise, odor, and visual pollution don’t usually come to mind when picturing a pleasant residential neighborhood in the Land of 10,000 Lakes. But for a tight-knit community in Minneapolis that has abutted the city’s Hiawatha Maintenance Facility for nearly a century, pollution in many forms was a daily reality.

The public works site was “a real eyesore,” said Marc Partridge, AIA, CID, LEED AP, a senior associate at local design firm RSP Architects. According to Steve Maurelli, a project manager at RSP, the buildings on the 10-acre site were sorely in need of repair and maintenance. The sense of irony—that a facility devoted to maintenance could itself be so ill-kempt—added to the long-simmering tension between the city and the residents of the adjacent neighborhood, who for decades felt that the city was exploiting them by allowing this blot on their visual landscape.

PROJECT SUMMARY
Hiawatha Maintenance Facility, Minneapolis, Minn.
Building Team

  • Owner/developer: City of Minneapolis
  • Architect: RSP Architects (submitting firm)
  • Structural engineer: Palanisami and Associates
  • MEP engineer: Paulson & Clarke Engineering Inc.
  • General contractor: Knutson Construction

General Information

  • Size: 33,0000-sf office space; 28,000-sf maintenance bay, 20,500-sf storage area
  • Construction cost: $10.8 million
  • Completion date: June 2010
  • Delivery method: Design-bid-build

Built in 1914 as a single brick warehouse and garage, the original building served as a horse infirmary for the local fire department. Population growth spurred the city to erect 18 more facilities, and for more than 90 years the Hiawatha facility has been home to the city’s streets and sewers department.

Tearing down the buildings and starting anew would have been a swift, albeit expensive solution, but the city wanted to preserve the rich history of the facility while also paying respect to the sensitivities of its neighbors.

“When we started this project, one of the goals was to recycle and reuse as much as we could,” said Greg Goeke, director of property services for the city of Minneapolis. The city’s Public Works Department has a “rich tradition” of public service, and repurposing the existing facilities was part of preserving that tradition. The result: about 98% of construction demolition waste from the project was reused.

Click here to view profiles of other reconstruction projects that have been recognized as part of BD+C's 28th Annual Reconstruction Awards.

New construction added space where needed without inflating the mass of the original structures. The original brick building was renovated to complement the surrounding community, while industrial materials were stored on the side of the building facing the highway, out of view of the neighbors.

A new circulating glass curtain wall brought light deep into the facility and made the exteriors more aesthetically pleasing. Recycled materials—metal beams, concrete slabs forming an exterior patio, and wood and bricks salvaged from the original blacksmith shop—lent an elegant but still understated feel to the façade.

According to RSP’s Partridge, an important goal of the renovation was to keep the building functional, not precious. “Public works is raw stuff, and we wanted the building to reflect that,” he said. “In terms of maintainability and the honesty of the materials, everything had a purpose. We wanted to make sure the palette was true to the work being done there.”

Effecting cultural change through design

Before the reconstruction began, city workers were isolated in their respective departments in various parts of the building, each group with its own lunchroom, kitchen, and equipment collection—a layout that lent itself to communication breakdowns and resulting inefficiencies.

2011 RECONSTRUCTION AWARD PRODUCT LIST
Hiawatha Maintenance Facility, Minneapolis, Minn.

Structural Steel: MacSteel
Overhead Door Aluminum: Haas
Structural Deck: Vulcraft-Nucor
Corrugated Metal: CMI Inc.
Lockers: The Locker Guy
Precast Concrete: FabCon
Aluminum Storefront Curtainwall: Old Castle
Ready-mix: Cemstone
Hollow Core Planks: Molin
Remix P/6473 Carpet: Milliken
Windows DH: Pella
Aluminum Storefront Entrances and Doors: Old Castle
Light Gauge Metal Items: Clarkwestern
Louvera: Nystrom
Linoleum: Forbo
Metal Stairs: Lapeyer
Una-Clad: C Firestone
VCT Tile: Daltile
Thermal Batt Insulation: Owens Corning
Insulation: Johns Manville
Gypcrete Green 2000: Maxxom
Alucobond: Alcan
Modular Carpet: Lee's Carpet
Gypsum Board: National Gypsum
Flagpoles: Poletech
Vinyle Tile: Daltile
Gymspum Board: USG
Vinyl Tile: Daltile
Tread Riser: Nora
Rubber Base: Roppe
Rubber Tiles: Nora
Translucent Panel: Kalwall
Misc. Metal Shapes: Nucor
Structural Steel Joists: Vulcraft-Nucor
Overhead Steel Doors: DoorLink

The Building Team—which, in addition to RSP Architects, included Palanisami and Associates (structural engineer), Paulson & Clark Engineering (MEP engineer), and Knutson Construction (GC)—set to work with the municipal administration to find ways to maximize workflow by opening up the floor plan. “We did a lot of programming to see what resources and tasks could be shared between groups, and then designed the space so that the groups were thrown together in shared experiences,” said Partridge. 

Today, the Hiawatha facility takes in 33,000 sf of office space over two floors, a 28,000-sf maintenance bay, and 20,500 sf of storage. It is home to five public works departments whose workforce has experienced something of a collective cultural change as a result of the new space adjacencies. “Making the building more open brought everyone together,” said RSP’s Partridge. Daily task work has improved, response times have quickened, and overall functionality has been streamlined.

“They now realize how much more collaborative their work really is,” he said.

A tough building complex that reflects the hardy work being performed inside—this is what the Building Team envisioned. And it works. “On a day-to-day basis, our employees have an environment that works much better for them without compromising [individual departmental] goals,” said the city’s Greg Goeke—and a great justification for the project to earn Gold honors from BD+C’s Reconstruction Awards jury.

EXCEEDING EXPECTATIONS a commitment to the community

During the planning of the Hiawatha Maintenance Facility, a directive from the city of Minneapolis required the Building Team—RSP Architects, Palanisami and Associates (SE), Paulson & Clark Engineering (MEP), and Knutson Construction (GC)—to achieve LEED Gold certification. But with the high level of reused materials—nearly 98%—the team was able to reach even higher.

“Not only does a public works facility need to protect the city, it also needs to protect the environment,” said Greg Goeke, the city’s director of property services. “We have high recycled content that made achieving environmental goals fairly easy.”

Old timber repurposed for millwork, recycled switchboards and crane rails, and salvaged metal beams supporting the site’s fueling station helped earn the project LEED Platinum for new construction, the city’s first municipal building to earn this rating. An old open-grate bridge that used to cross the Mississippi River was converted into a perimeter fence.

Artifacts of the building’s past are now displayed along the walls, paying homage to the building’s nearly century-long history. Old photographs, remnants of an old asphalt plant, and materials from the infirmary were reincorporated into the building construct.

The project’s high level of sustainability demonstrated the city’s commitment to the local community’s welfare, said Goeke. By the end of the process, residents who had started out mistrusting the project became its strongest advocates. “People now see that something built nearly a century ago still has value today,” he said. +

Related Stories

| Jun 26, 2013

New York’s ‘Scaffold Law’ may be altered to place larger burden on workers

New York's Scaffold Law, which “places the burden of responsibility on the contractor to prove that the job site was safe for workers,” could be facing a major change.

| Jun 26, 2013

Commercial real estate execs eye multifamily, retail sectors for growth, says KPMG report

The multifamily, retail, and hospitality sectors are expected to lead commercial building growth, according to the 2013 KPMG Commercial Real Estate Outlook Survey. 

| Jun 25, 2013

Mirvish, Gehry revise plans for triad of Toronto towers

A trio of mixed-use towers planned for an urban redevelopment project in Toronto has been redesigned by planners David Mirvish and Frank Gehry. The plan was announced last October but has recently been substantially revised.

| Jun 25, 2013

First look: Herzog & de Meuron's Jade Signature condo tower in Florida

Real estate developer Fortune International has released details of its new Jade Signature property, to be developed in Sunny Isles Beach near Miami. The luxury waterfront condo building will include 192 units in a 57-story building near high-end retail destinations and cultural venues.  

| Jun 25, 2013

DC commission approves Gehry's redesign for Eisenhower memorial

Frank Gehry's updated for a new Dwight D. Eisenhower memorial in Washington, D.C., has been approved by the Eisenhower Memorial Commission, reports the Washington Post. The commission voted unanimously to approve the $110 million project, which has been gestating for 14 years.

| Jun 21, 2013

AIA report: Greater collaboration, stiffer competition among top trends in architecture

A new 34-page report from AIA highlights key trends in the architecture marketplace and their impact on business and growth.

| Jun 20, 2013

Virtual meetings enhance design of University at Buffalo Medical School

HOK designers in New York, St. Louis and Atlanta are using virtual meetings with their University at Buffalo (UB) client team to improve the design process for UB’s new School of Medicine and Biomedical Sciences on the Buffalo Niagara Medical Campus.

| Jun 19, 2013

Architects upbeat about the construction market

Following the first reversal into negative territory in ten months in April, AIA's Architecture Billings Index bounced back in May, reaching 52.9.

| Jun 19, 2013

NSF Sustainability begins verifying EPDs that can be used for LEED V4

NSF Sustainability has verified Environmental Product Declarations (EPDs) for nylon carpet styles and colors manufactured by Mannington Commercial and for J+J Flooring Group’s Kinetex® flooring product and Invision brand modular styles that use eKo® backing.  

| Jun 19, 2013

Florida is latest battleground over LEED standards centered on certified wood

A nationwide battle over forest certification standards continues to be played out nationally and in Florida with legislation passed this month. 

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021