Reconstruction Awards: Reinvesting in a neighborhood’s future

Reconstruction Awards: Reinvesting in a neighborhood’s future

The reconstruction of a near-century-old derelict public works facility in Minneapolis earns LEED Platinum—and the hearts and minds of the neighboring community.


By By Leslie Streicher, Associate Editor | March 1, 2012
The buildings rugged history of service is captured in the reused building mate
The buildings rugged history of service is captured in the reused building materials from the original structure. Bricks, timbe
This article first appeared in the March 2012 issue of BD+C.

Noise, odor, and visual pollution don’t usually come to mind when picturing a pleasant residential neighborhood in the Land of 10,000 Lakes. But for a tight-knit community in Minneapolis that has abutted the city’s Hiawatha Maintenance Facility for nearly a century, pollution in many forms was a daily reality.

The public works site was “a real eyesore,” said Marc Partridge, AIA, CID, LEED AP, a senior associate at local design firm RSP Architects. According to Steve Maurelli, a project manager at RSP, the buildings on the 10-acre site were sorely in need of repair and maintenance. The sense of irony—that a facility devoted to maintenance could itself be so ill-kempt—added to the long-simmering tension between the city and the residents of the adjacent neighborhood, who for decades felt that the city was exploiting them by allowing this blot on their visual landscape.

PROJECT SUMMARY
Hiawatha Maintenance Facility, Minneapolis, Minn.
Building Team

  • Owner/developer: City of Minneapolis
  • Architect: RSP Architects (submitting firm)
  • Structural engineer: Palanisami and Associates
  • MEP engineer: Paulson & Clarke Engineering Inc.
  • General contractor: Knutson Construction

General Information

  • Size: 33,0000-sf office space; 28,000-sf maintenance bay, 20,500-sf storage area
  • Construction cost: $10.8 million
  • Completion date: June 2010
  • Delivery method: Design-bid-build

Built in 1914 as a single brick warehouse and garage, the original building served as a horse infirmary for the local fire department. Population growth spurred the city to erect 18 more facilities, and for more than 90 years the Hiawatha facility has been home to the city’s streets and sewers department.

Tearing down the buildings and starting anew would have been a swift, albeit expensive solution, but the city wanted to preserve the rich history of the facility while also paying respect to the sensitivities of its neighbors.

“When we started this project, one of the goals was to recycle and reuse as much as we could,” said Greg Goeke, director of property services for the city of Minneapolis. The city’s Public Works Department has a “rich tradition” of public service, and repurposing the existing facilities was part of preserving that tradition. The result: about 98% of construction demolition waste from the project was reused.

Click here to view profiles of other reconstruction projects that have been recognized as part of BD+C's 28th Annual Reconstruction Awards.

New construction added space where needed without inflating the mass of the original structures. The original brick building was renovated to complement the surrounding community, while industrial materials were stored on the side of the building facing the highway, out of view of the neighbors.

A new circulating glass curtain wall brought light deep into the facility and made the exteriors more aesthetically pleasing. Recycled materials—metal beams, concrete slabs forming an exterior patio, and wood and bricks salvaged from the original blacksmith shop—lent an elegant but still understated feel to the façade.

According to RSP’s Partridge, an important goal of the renovation was to keep the building functional, not precious. “Public works is raw stuff, and we wanted the building to reflect that,” he said. “In terms of maintainability and the honesty of the materials, everything had a purpose. We wanted to make sure the palette was true to the work being done there.”

Effecting cultural change through design

Before the reconstruction began, city workers were isolated in their respective departments in various parts of the building, each group with its own lunchroom, kitchen, and equipment collection—a layout that lent itself to communication breakdowns and resulting inefficiencies.

2011 RECONSTRUCTION AWARD PRODUCT LIST
Hiawatha Maintenance Facility, Minneapolis, Minn.

Structural Steel: MacSteel
Overhead Door Aluminum: Haas
Structural Deck: Vulcraft-Nucor
Corrugated Metal: CMI Inc.
Lockers: The Locker Guy
Precast Concrete: FabCon
Aluminum Storefront Curtainwall: Old Castle
Ready-mix: Cemstone
Hollow Core Planks: Molin
Remix P/6473 Carpet: Milliken
Windows DH: Pella
Aluminum Storefront Entrances and Doors: Old Castle
Light Gauge Metal Items: Clarkwestern
Louvera: Nystrom
Linoleum: Forbo
Metal Stairs: Lapeyer
Una-Clad: C Firestone
VCT Tile: Daltile
Thermal Batt Insulation: Owens Corning
Insulation: Johns Manville
Gypcrete Green 2000: Maxxom
Alucobond: Alcan
Modular Carpet: Lee's Carpet
Gypsum Board: National Gypsum
Flagpoles: Poletech
Vinyle Tile: Daltile
Gymspum Board: USG
Vinyl Tile: Daltile
Tread Riser: Nora
Rubber Base: Roppe
Rubber Tiles: Nora
Translucent Panel: Kalwall
Misc. Metal Shapes: Nucor
Structural Steel Joists: Vulcraft-Nucor
Overhead Steel Doors: DoorLink

The Building Team—which, in addition to RSP Architects, included Palanisami and Associates (structural engineer), Paulson & Clark Engineering (MEP engineer), and Knutson Construction (GC)—set to work with the municipal administration to find ways to maximize workflow by opening up the floor plan. “We did a lot of programming to see what resources and tasks could be shared between groups, and then designed the space so that the groups were thrown together in shared experiences,” said Partridge. 

Today, the Hiawatha facility takes in 33,000 sf of office space over two floors, a 28,000-sf maintenance bay, and 20,500 sf of storage. It is home to five public works departments whose workforce has experienced something of a collective cultural change as a result of the new space adjacencies. “Making the building more open brought everyone together,” said RSP’s Partridge. Daily task work has improved, response times have quickened, and overall functionality has been streamlined.

“They now realize how much more collaborative their work really is,” he said.

A tough building complex that reflects the hardy work being performed inside—this is what the Building Team envisioned. And it works. “On a day-to-day basis, our employees have an environment that works much better for them without compromising [individual departmental] goals,” said the city’s Greg Goeke—and a great justification for the project to earn Gold honors from BD+C’s Reconstruction Awards jury.

EXCEEDING EXPECTATIONS a commitment to the community

During the planning of the Hiawatha Maintenance Facility, a directive from the city of Minneapolis required the Building Team—RSP Architects, Palanisami and Associates (SE), Paulson & Clark Engineering (MEP), and Knutson Construction (GC)—to achieve LEED Gold certification. But with the high level of reused materials—nearly 98%—the team was able to reach even higher.

“Not only does a public works facility need to protect the city, it also needs to protect the environment,” said Greg Goeke, the city’s director of property services. “We have high recycled content that made achieving environmental goals fairly easy.”

Old timber repurposed for millwork, recycled switchboards and crane rails, and salvaged metal beams supporting the site’s fueling station helped earn the project LEED Platinum for new construction, the city’s first municipal building to earn this rating. An old open-grate bridge that used to cross the Mississippi River was converted into a perimeter fence.

Artifacts of the building’s past are now displayed along the walls, paying homage to the building’s nearly century-long history. Old photographs, remnants of an old asphalt plant, and materials from the infirmary were reincorporated into the building construct.

The project’s high level of sustainability demonstrated the city’s commitment to the local community’s welfare, said Goeke. By the end of the process, residents who had started out mistrusting the project became its strongest advocates. “People now see that something built nearly a century ago still has value today,” he said. +

Related Stories

Roofing | Jan 8, 2024

Researchers devise adaptive roof tile concept that adjusts to ambient temperatures

Scientists at the University of California Santa Barbara published a paper that proposes adaptive roof tile technology that can adjust to ambient temperatures. Using a wax motor, tiles could switch from a heating or cooling state enabling savings on heating and cooling costs.

MFPRO+ News | Jan 4, 2024

Bjarke Ingels's curved residential high-rise will anchor a massive urban regeneration project in Greece

In Athens, Greece, Lamda Development has launched Little Athens, the newest residential neighborhood at the Ellinikon, a multiuse development billed as a smart city. Bjarke Ingels Group's 50-meter Park Rise building will serve as Little Athens’ centerpiece.

MFPRO+ Special Reports | Jan 4, 2024

Top 10 trends in multifamily rental housing

Demographic and economic shifts, along with work and lifestyle changes, have made apartment living preferable for a wider range of buyers and renters. These top 10 trends in multifamily housing come from BD+C's 2023 Multifamily Annual Report.

Giants 400 | Jan 3, 2024

Top 200 Reconstruction Architecture Firms for 2023

Gensler, Stantec, HDR, Corgan, and PBK Architects top BD+C's ranking of the nation's largest building reconstruction/renovation architecture and architecture engineering (AE) firms for 2023, as reported in the 2023 Giants 400 Report.

Designers | Jan 3, 2024

Designing better built environments for a neurodiverse world

For most of human history, design has mostly considered “typical users” who are fully able-bodied without clinical or emotional disabilities. The problem with this approach is that it offers a limited perspective on how space can positively or negatively influence someone based on their physical, mental, and sensory abilities.

Giants 400 | Jan 2, 2024

Top 120 Hotel Architecture Firms for 2023

Gensler, WATG, HKS, DLR Group, and HBG Design top BD+C's ranking of the nation's largest hotel and resort architecture and architecture/engineering (AE) firms for 2023, as reported in Building Design+Construction's 2023 Giants 400 Report. 

Resiliency | Jan 2, 2024

Americans are migrating from areas of high flood risk

Americans are abandoning areas of high flood risk in significant numbers, according to research by the First Street Foundation. Climate Abandonment Areas account for more than 818,000 Census Blocks and lost a total of 3.2 million-plus residents due to flooding from 2000 to 2020, the study found.

MFPRO+ News | Jan 2, 2024

New York City will slash regulations on housing projects

New York City Mayor Eric Adams is expected to cut red tape to make it easier and less costly to build housing projects in the city. Adams would exempt projects with fewer than 175 units in low-density residential areas and those with fewer than 250 units in commercial, manufacturing, and medium- and high-density residential areas from environmental review. 

Contractors | Dec 22, 2023

DBIA releases two free DEI resources for AEC firms

The Design-Build Institute of America (DBIA) has released two new resources offering guidance and provisions on diversity, equity, and inclusion (DEI) on design-build projects.

MFPRO+ News | Dec 22, 2023

Document offers guidance on heat pump deployment for multifamily housing

ICAST (International Center for Appropriate and Sustainable Technology) has released a resource guide to help multifamily owners and managers, policymakers, utilities, energy efficiency program implementers, and others advance the deployment of VHE heat pump HVAC and water heaters in multifamily housing.

boombox1
boombox2
native1

More In Category

Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021